    Note there are a few more areas shown in appendix a 21 in the book after the acceptance criteria:
    •Project-level quality tolerances Specification of any tolerances that may apply for the acceptance criteria
    •Acceptance method Statement of the means by which acceptance will be confirmed. This may simply be a case of confirming that the project product and/or outcomes have been approved, or may involve describing complex handover arrangements for the project product, including any phased handover of the project product’s components
    •Acceptance responsibilities Definition of who will be responsible for confirming acceptance.