    Thanks for this video particularly. So far I've seen planners updating activities line by line with percentage which was quite a job for a 3k activities project. Now it looks so much easier. Although as far as I understand some fields are not updatable

  • @syedatrafabbas8216
    @syedatrafabbas8216 2 ปีที่แล้ว +1

    To convert the cell of an exported p6 file from general to text, can we use format painter?

  • @tgmkrishnan2007
    @tgmkrishnan2007 3 หลายเดือนก่อน

    Thanks Osama

  • @rhnasir
    @rhnasir 2 ปีที่แล้ว

    There is an issue on importing the dates from excel you did not mention it , as P6 accept it as text , it is always did not work