How to perform Recovery & Revised Schedule

แชร์
ฝัง
  • เผยแพร่เมื่อ 20 ต.ค. 2024
  • How to perform Recovery & Schedule Plan Step by Step :
    1-ADD OR REMOVE ANY APPROVED SCOPE CHANGES.
    2-FIX OUT OF SEQUENCE ACTIVITIES.
    3-FIX PROJECT AND MILESTONES DATES TO MEET THE APPROVED NEW DATES (USING
    CRASHING/FAST TRACKING).
    4-FIX REMAINING EARLY START DATES FOR IN PROGRESS ACTIVITIES TO BE = DATA DATE + 1
    5- COST LOADING (IF THERE IS ANY).
    6- FIX THE REMAINING DURATION (GET RID OF DECIMALS).
    7-FIX ACTUAL START DATES BY CALCULATING THE ACTUAL DURATION DEPENDING ON ORIGINAL
    DURATION.
    8-PERFORM GLOBAL CHANGE FOR COMPLETED AND IN PROGRESS ACTIVITIES.
    Important Note :
    When doing Recovery or Revised schedule, we should use the last updated approved schedule.