How to Relocate your Building | Revit 2020

แชร์
ฝัง
  • เผยแพร่เมื่อ 1 ธ.ค. 2024

ความคิดเห็น • 90

  • @chrispomfret8592
    @chrispomfret8592 4 หลายเดือนก่อน +1

    I've been using Revit since 2007 and occasionally I have not had survey's before commencing projects. I've previously sucked up the pain of moving the levels and then went around and corrected things. I wish I knew about relocating years ago. There re so many things we all can learn. Thank you!
    If you wonder if Revit can do something...well it probably can.

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 หลายเดือนก่อน

      Well said, and thank so much for the kind words! Relocating a project is so helpful in specific situations. Glad you found it helpful. And it’s so true that Revit can do just about anything.

  • @hayattt
    @hayattt 3 ปีที่แล้ว +2

    THANKYOU VERY MUCH I DIDNT HAVE TO ACTUALLY USE THE RELOCATE PROJECT BUT MOVING THE BASE POINT DID EVERYTHING . ALTHOUGH LOVED HOW YOU COVERED ALL THE POSSIBLE PROBLEMS AND THEIR SOLUTION

  • @rodrigobizarro4735
    @rodrigobizarro4735 ปีที่แล้ว +1

    man, you just saved me, that’s exactly what a needed, thanks a lot!!!

  • @addisoncalvin8375
    @addisoncalvin8375 3 หลายเดือนก่อน +1

    Very Helpful
    thanks

  • @DubeThabo
    @DubeThabo 2 ปีที่แล้ว +1

    Exactly what I have been looking for. Thank you

  • @yifupan798
    @yifupan798 2 ปีที่แล้ว +1

    this is amazing! thank u!

  • @mthornhill1961
    @mthornhill1961 4 ปีที่แล้ว +2

    This was very helpful. Thanks!

  • @markkibui8035
    @markkibui8035 3 ปีที่แล้ว

    YOU JUST SAVED ME

    • @markkibui8035
      @markkibui8035 3 ปีที่แล้ว

      But moving the project base point wasn't working as intended. Maybe I missed something. However the relocate tool worked well. Thanks

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว

      Very good to hear, I am glad it helped!

    • @markkibui8035
      @markkibui8035 3 ปีที่แล้ว

      @@ArchitectureVanguard I had issues when it came to exporting an IFC of the model to Navisworks. The model wasn't on the same level with the IFC from the architect. Just a heads up for those who will export the model

  • @hugoedelarosa
    @hugoedelarosa 9 หลายเดือนก่อน

    I am gonna need to watch this video several times before I grasp what is going on here. Luckily my building is also at 100 ft elevation.
    Wish Revit had a tool to do all this without moving existing conditions and objects that go through a building. I'll move my terrain down, but then I'll have to lower piers, cable trays, cable tray t-supports, pumps, etc. The project manager wants to raise the building 1.5 inches, but I'll only do it one time.

  • @harshavardhankhurd1315
    @harshavardhankhurd1315 6 หลายเดือนก่อน

    Can you demonstrate a video to relocate the building in the horizontal direction. Will be helpful. Loved the presentation style of your content.

  • @madhousebuilders9861
    @madhousebuilders9861 4 หลายเดือนก่อน

    how about moving the model to the proper coordinates without ruining the model

  • @samw1111
    @samw1111 2 ปีที่แล้ว +1

    Hey there, Ive followed all your steps and it all seems to work. however now when i load in my Survey CAD files with real world coordinates, they load in moved as well. Ive tried loading in a fresh CAD file as well. but still loads to the new moved location.
    Im currently moving a bridge model down by about 250mm.

    • @ArchitectureVanguard
      @ArchitectureVanguard  2 ปีที่แล้ว

      You m ight check your project based point or shared coordinates if you use those. You can alter those without using the relocate building tool but they will move when you do use the relocate building tool.

  • @zaydzaidi5240
    @zaydzaidi5240 3 ปีที่แล้ว +1

    thank you so much!!

  • @janniemeyer9951
    @janniemeyer9951 10 หลายเดือนก่อน

    Confusing. I need to raise my model by 700mm and reflect that in the height above see level. Moving the site down?

  • @Helena-uv9bv
    @Helena-uv9bv 10 หลายเดือนก่อน +2

    6:20 is where the video starts... honest suggestion you ramble way too much, I got nothing from the first 6 minutes

  • @danielmitrofanov9877
    @danielmitrofanov9877 8 หลายเดือนก่อน

    How you can explain how to rotate my sight?

  • @razern420
    @razern420 ปีที่แล้ว

    Hey man , i meant to find how to move the whole building tbh , any method? , it keeps unjoining elements

  • @sams_3d_stuff
    @sams_3d_stuff 3 ปีที่แล้ว

    THANKS!

  • @ethaniandragoneel7813
    @ethaniandragoneel7813 4 ปีที่แล้ว +1

    Hey, thanks for the video! Here's a few questions:
    1-I have a site that's at a really high elevation(let's say a 100M above the base pt), and wanted to see if I could bring everything down, as in have the origin set to 100M itself?
    2-Since i modelled the site already, when i tried your method, it change the elevation levels to 100M onwards, but the project base point moved a 100M below the site..that can't be good right?
    3-Also the site moves along with it, so when i moved the site 100M lower to bring it to the level that used to say 0M and now says100M, the spot elevation is fine but the topo points say they're at 0mm above the ground.
    4-does the survey point need to be changed or can i ignore that? Also, is this because the project base point needs to be a certain way i.e, clipped or unclipped?

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว +1

      1- I would move the project base point. This will move that point but not the building.
      2- that is really fine, at that point it just comes down to the numbers that you want to show, 100 or one or something like that.
      3-that may be because of the base point. If you want the numbers to be changed, move the base point, if you want every model element to move then use relocate building.
      4-the base point being clipped or pinned wouldn’t matter. And you can ignore the survey point unless you are linking in a shared site or need to coordinate that point with a survey you’re bringing in.

    • @ethaniandragoneel7813
      @ethaniandragoneel7813 4 ปีที่แล้ว

      @@ArchitectureVanguard Thanks a ton! You've helped a lot!!

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      Glad to hear it!

  • @polly_loves12
    @polly_loves12 9 หลายเดือนก่อน

    What do u do if u have to keep the project base point at zero ?

  • @ca-rd4444
    @ca-rd4444 3 ปีที่แล้ว

    HI I moved the project up but al it did was my my survey point down. I initial made my project at 0' for base and survey but now I know my survey point is 98' for finish floor. I want my levels to show project base point elevation as 0' and my survey reference spot elevation to show as 98'. I have tried about 100 ways from Sunday with no success any Ideas?

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว

      You might look into changing the Z value in the project base point or survey base point. My guess is you would want to change project.

  • @GDImhoff
    @GDImhoff 3 ปีที่แล้ว

    Question.
    I own and operate a Cad / Bim production service
    I have just received a design model from a designer. I need to rotate the entire model 90 degrees to get the plans to fit on the sheet. how do I do that without messing up the model.

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว

      Gary, you would want to simply rotate project north. This would rotate the view without actually rotating the model so you could fit it on a sheet, etc.

  • @maryamghaderibafti7473
    @maryamghaderibafti7473 ปีที่แล้ว +1

    appreciate

  • @tahirzahidishrat1324
    @tahirzahidishrat1324 3 ปีที่แล้ว

    Hi. I am fixing a model made by a third party. It's an exploded axonometric so floor-wise the model's been displaced vertically. However, they haven't used the displace items tools so the vertical displacement is in the model not just the view. Can you offer some advice on how to fix this? I tried changing the base offset constraints but the walls don't move up or down because an error pops up since they're linked to windows and doors.

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว +1

      Gosh, this is tough other than remodeling. I would say for a wall for example copying the entire wall with things hosted by the wall, changing the constraints of the wall to what they should be, pasting in same place so everything goes back, then finally using the windows/doors of the pasted elements and moving those to the new wall location. I hope that helps!

    • @tahirzahidishrat1324
      @tahirzahidishrat1324 3 ปีที่แล้ว

      Thanks!

  • @drewkingson
    @drewkingson 3 วันที่ผ่านมา +1

    someone asks you for the time and you take 3 days to explain it to them

  • @ArchiTech-fq4xe
    @ArchiTech-fq4xe 3 ปีที่แล้ว

    You only need yo touch th project basepoint will remain zeron and survey point will remain will have a value.

  • @lewisgledhill6111
    @lewisgledhill6111 4 ปีที่แล้ว +2

    Hi, I have recently started using Revit and have come across this video. I am currently working with two separate models which have been created in inventor, and are now imported into the same Revit project. The two separate models make up different parts of a building, and the problem I am having is ensuring that the two models are set to the correct coordinates. The first model is runs of cable tray throughout the building, and the second model is the actual building itself. I need to make sure that the two link together properly. Is this someone you can assist with?

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      Sure, a good start would be to link in the main model then second, link the model with the cable trays. When linking in the cable tray model, make sure to link using the "Auto - Origin to Origin" then try "Auto Project Base Point to Project Base Point" and see if the model comes in correctly. If neither of those work then you likely need to address the models individually in inventor. Assuming they are both correctly modeled together in Inventor, you should be able to bring them into Revit linked correctly. I believe Revit 2021 has actually linking of Inventor files which would make this even easier than having to do some different export. Hopefully that addresses what you are looking for.

  • @Jeeshk
    @Jeeshk 4 ปีที่แล้ว

    Is there a way to relocate model and have it moved from the internal origin aswell. Eg. If I draw a pipe I get my spot elevation right but the default parameter for invert elevation is not right.

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      Interesting, you may need to move them separately is all. . You cannot move the internal origin, but is the project base point you will want to move.

    • @Jeeshk
      @Jeeshk 4 ปีที่แล้ว

      @@ArchitectureVanguard Yup had to move the entire model.

  • @alvinperumal8463
    @alvinperumal8463 4 ปีที่แล้ว

    Hi, good morning, thanks a lot for your tutorial. I have another question regarding the site plan(i am new to revit). When i orientate the site plan to true north, why wouldn't the building orientate with the site plan.Thanks again.

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      Are you saying that all your plan elements move/rotate but your building does? I would take a look at what did move. Was it specifically 2D or 3D. It could just be that. Assuming you completed the transform correctly, it may be that the 3D model did not move but True North did but at the same time you 2D elements did.. Hope that helps.

  • @cfraga111
    @cfraga111 4 ปีที่แล้ว

    HI, I HAVE A PROJECT AT 0'-0" BUT THE ARCH. RAISE 1'-2" THE GROUND, SO ALL THE ELEVATION NEED TO BE 1'-2" HIGHER WHAT IS THE EASY WAY TO DO IT? THANKS

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      If you need to physically move object and not just adjust the numbers then you will have to select what you want and move it. The relocate building tool will move everything, therefore, simply changing the elevation of it all. Assuming you have things associated to levels, then I would move the level to match the architecture. You will then have to move everything else in the model that is not associated to a level the same distance. Save an archived copy of the model before attempting this as a lot could break. Hope that helps!

    • @cfraga111
      @cfraga111 4 ปีที่แล้ว

      @@ArchitectureVanguard appreciate my friend, i select all elevation and move up and work for me. thanks

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      Very nice, glad to hear!

  • @TusharMhaskar
    @TusharMhaskar ปีที่แล้ว

    thanks

  • @triprot3465
    @triprot3465 3 ปีที่แล้ว

    I think I followed your suggestions correctly, but when I label the contours they are all around +/- 0' when they should be around +/- 360'. I modeled the building and would like to show finish floor at 0'-0" and created the toposurface by placing points over a linked topo map BEFORE I saw your video and used the relocate project tool. Did I do something wrong or have to start over?

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว

      You might just need to change your spot elevations to read from the survey. Check the type properties that it is reading from the survey. Otherwise, I would relocate the building again and see what happens.

  • @stevendincognito5177
    @stevendincognito5177 3 ปีที่แล้ว

    I'm working in ver. 2018 student. I followed your instruction exactly as you laid out. I found the project base point and changed it to -465' since the elevation here centers the building on the site elevation in the real world. Nothing changed in my level elevations in my elevation view. Prior to viewing your video I had developed a site plan at the default level on zero the same as where I modeled the building. Any time I change the plotted points to anything below the building I don't see any grade lines in the negative direction but I do see them in the positive direction. So that lead me to search for a solution and I found your video very convincing but the solution did not play out as planed. Any suggestions?

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว

      It almost sounds like you did everything correct, you just might need to edit the view range of your site plan so that the view extends below 0'. Give that a try.

  • @rajushaw6340
    @rajushaw6340 4 ปีที่แล้ว

    Hey,
    I'm facing a problem in Revit regarding Elevation, In my project base point and survey point both are at 0'-0" but when I'm export this model looks like the model automatically moves it down negative (-)508'.How this problem has occurred. Can you please help me. if you help me I will be highly obliged to you. Please help me as quick as possible for you.

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      I would also check your internal origin point if you are in Revit 2020. Let me know if that does not solve the issue.

    • @rajushaw6340
      @rajushaw6340 4 ปีที่แล้ว

      @@ArchitectureVanguard My Origin point also 0'-0 ".I'm using the 2019 Revit file. Still, I'm facing this problem.

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      Maybe it is an import option of the program you are importing this into. It appears as though you are correct in how you have your Revit model setup. What program are you exporting to?

    • @rajushaw6340
      @rajushaw6340 4 ปีที่แล้ว

      I'm exporting this model in naviswroks 2019. Also when I'm linking this model in other Revit files then the model looks like -508' negative. One thing I found when I cheek the elevation my current level is shown -508'.But My project base point and survey point is shown 0'-0".
      How it possible. I'm a little bit confused about how to kill this issue.

  • @christopherbryjowski2882
    @christopherbryjowski2882 2 ปีที่แล้ว +1

    Good Lord ...Thanks for this tutorial and maybe my comment will help you as well. The way you are explaining it is A MESS. Be focus 1. there is a problem we are starting with 2 is the end of the journey point ....just trace a straight line between them and explain the topic step by step without grasping all branches. Please have a look at your cursor...while explaining.....yea threats exactly what you do. Regards

  • @wrighthausracing9641
    @wrighthausracing9641 3 ปีที่แล้ว

    I don't know why the topography moves up with it when we are trying to keep sea level correct. I am not sure who thought that was a good idea. I am just simply trying to lower the house into the topography better. Too bad it's not just moving the project based point which you would call level 0" then simply move the project based point and everything follows. I could have swore that's how it works have been ripping my hair out just trying to do something so simple.

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว

      Assuming you are using the relocate project tool in section or elevation? The only reason things should move if the move tool is being used.

    • @wrighthausracing9641
      @wrighthausracing9641 3 ปีที่แล้ว

      @@ArchitectureVanguard Yes I used the same tool you did and topography goes with it. The then manually move it back. Glad I watched your video or all I would have never noticed anything was even happening.

    • @wrighthausracing9641
      @wrighthausracing9641 3 ปีที่แล้ว

      @@ArchitectureVanguard You would think the revit topography is directly associated with the sea level conditions. Come on revit!!!

    • @wrighthausracing9641
      @wrighthausracing9641 3 ปีที่แล้ว

      @@ArchitectureVanguard It took me hours to figure it out now it's a 10 second move.

    • @ArchitectureVanguard
      @ArchitectureVanguard  3 ปีที่แล้ว

      Haha I agree, it is too bad this is the case but at least we have a fix!

  • @ArchiTech-fq4xe
    @ArchiTech-fq4xe 3 ปีที่แล้ว

    You cant just put a value to the elevation it affect the pjbp

  • @bramblestown
    @bramblestown 6 วันที่ผ่านมา

    Good video, music is annoying

  • @ssnanj8014
    @ssnanj8014 4 ปีที่แล้ว

    HI.We are using Revit 2018. after completion of model including all annotations, spot elevations and coordinates , our Client wanted to move the building 3m on east and 1.8m on north direction. moving by physically seems will delete many elements itself also 2d annotation won't move. kindly advise

    • @ArchitectureVanguard
      @ArchitectureVanguard  4 ปีที่แล้ว

      You are able to relocate the project in plan using the relocate tool as well. I would draw a detail line on a floor plan and move the model from the start and end point of the line. That will only move the origin of the model. If you need to keep the site in place and move the building itself then you will need to physically move the site or the building. When it comes to 2D elements, you could group all 2D elements as a detail group, cut the group, move the building, paste the detail group in same place, then move the 2D group the same as the building. May or may not work with hosted annotations though.

    • @ssnanj8014
      @ssnanj8014 4 ปีที่แล้ว

      @@ArchitectureVanguard Thanks . let me try as you advised.

  • @LEOPARDO_VDC
    @LEOPARDO_VDC ปีที่แล้ว +4

    GET TO THE POINT

  • @rabiacherkouk590
    @rabiacherkouk590 2 ปีที่แล้ว +1

    Hmar

  • @ArchiTech-fq4xe
    @ArchiTech-fq4xe 3 ปีที่แล้ว +1

    All you do is all wrong.