  • #XLPE #PowerCable #Cable #2500SQMM #Electrical #Tray #work #making #to #tray #for #all #tips #Electrical #Tray #work #Supportstructure #UndergroundCable #IndoorTermination #SheathTest #OutdoorTermination #GIS #SurgeArrester #Installation #CableSealingEnd #MetalFrame #cableunload #cablepulling #cablelaying
    It is important to verify the cable has been installed appropriately. As the cables are generally laid in trench or in conduit systems, it can be difficult to inspect the cable for physical damage that may have occurred during installation.
    This is when a sheath integrity test should be performed. This gives us a good baseline to compare to after the cable has been installed and whether damage has occurred during installation.
    The sheath integrity test consists of a DC voltage injection on the screen wires of generally 10kV. The voltage is maintained for 1 minute where no breakdowns must occur to prove the integrity of the outer sheath covering.
    Preparation Procedure
    1. Outer sheaths at both ends to be scraped and solvent cleaned to remove all traces of semi-conductive covering. A small portion of graphite coating to be removed 100 mm away from each end
    2. Cable ends to be supported, behind cleaned area, with suitable supports, i.e. wood-blocks
    3. Connect the cable core to an earthing point to prevent the core being charged. Now that the lead alloy sheaths have been isolated, the test can take place.
    4. Connect the test equipment with one wire clamp to the lead alloy sheath of one phase
    5. Before switching on, make sure that no one can get within reach of parts of the cable system where the high voltage is applied. Put up warning tapes and/or signs, which state the situation and station some watchmen along the route and at the other cable end.
    6. Slowly rotate the voltage selector (1 kV per second in intervals) until10kV test voltage is reached. The voltage to be maintained for 1 minute, and the leakage current after this time to be recorded
    7. After switching off, earth the lead alloy using earth rod before removing the clamp.
    8. Repeat these procedures for the other two phases.
    9. Before and after carrying DC voltage test, insulation resistance of the outer sheath to be tested by injecting 1kV DC. Results of IR values shall be calculated per Km of cable and to be recorded in the attached form.
    More on:
    Foundation- • Transmission Lines | F...
    Rock Anchor Foundation - • Transmission Lines | R...
    Erection- • Transmission Lines | T...
    Under Ground Cable- • UNDERGROUND CABLE | La...
    OPGW- • UNDERGROUND CABLE | La...
    Pile Load Test- • Pile Load Test
    Scaffolding- • Scaffolding
    Erection- • Transmission Lines I T...
    Stringing- • Transmission Lines | S...
    Conductor Sagging- • Transmission Lines | C...
    Tower Testing- • Transmission Lines | T...
    GIS Termination- • UNDERGROUND CABLE | GI...
    Shotcrete- • Shotcrete | Gunite | S...
    Monopole Erection (Suspension)- • Video
    Monopole Erection (Tension)- • Monopole Erection | Te...
    Cable Installation- • Underground Cable
    Subscribe: / pritamsingharoy
    Enjoy Watching!

ความคิดเห็น • 8

  • @superlocator69
    @superlocator69 11 หลายเดือนก่อน +1

    I highly suggest you earth the phases when doing sheath tests. Also, always use a discharge or earthing stick to make sure the test object is discharged after test.

  • @amazingvideos100subscriber4
    @amazingvideos100subscriber4 2 ปีที่แล้ว +1

    Great

  • @Alzhirskii
    @Alzhirskii 3 ปีที่แล้ว +2

    Hi,
    In wich standard we can find the table of acceptance critera ?

  • @richardsarmiento0526
    @richardsarmiento0526 หลายเดือนก่อน

    Hello. May I ask if what code is your reference for the acceptance criteria

  • @kushsharma3059
    @kushsharma3059 2 หลายเดือนก่อน

    What does -1 microampere leakage current signifies?

  • @ahmedzubair1706
    @ahmedzubair1706 6 หลายเดือนก่อน

    Hello is there any other way to test sheath of 132kV xlpe cable?

  • @muhammadshabbir8224
    @muhammadshabbir8224 2 ปีที่แล้ว

    Kindly upload working video of sheat fault location HVB10 or shirlla Cable fault locator