MS Project tutorial for Civil Engineering|with Hindi subtitles|vtu students|

แชร์
ฝัง
  • เผยแพร่เมื่อ 27 ส.ค. 2024
  • The MS project is one of the software which is must learn software for Civil Engineers. In this video, you will learn planning and scheduling of construction project by using MS project. This video tutorial is for beginners. Learn the basics of software with in 30 minutes. Without skip watch the entire video to learn the software easily. The videos consists of English and Hindi subtitles.

ความคิดเห็น • 22

  • @getfanmedia
    @getfanmedia ปีที่แล้ว

    Great

  • @farooqbashir4111
    @farooqbashir4111 2 ปีที่แล้ว

    Thanks, Very Good, Preparation and Explaining the Lecture. Very useful and guidance to students. Specially, I am Learning and improving my Skills. Again Thank You.

  • @rakeshranjan7525
    @rakeshranjan7525 2 ปีที่แล้ว

    Nice

  • @bvsnagababu7954
    @bvsnagababu7954 2 ปีที่แล้ว

    Plz make video on report generation and earned value

  • @jerrymathew3355
    @jerrymathew3355 3 ปีที่แล้ว

    So is it better to set Max in decimal rather than %?Can we continue assigning decimal values to material ?What would be difference?How to differentiate cost assigned if a person is working on 2 projects?Per day cost can be given to a project engineer then let 40 % and 60% be assigned based on persons involvement in 2 different projects.Then what would be next step and how will cost be allocated in that case if person has a salary of 30000

    • @roarkacademy-civilengineer5905
      @roarkacademy-civilengineer5905  3 ปีที่แล้ว

      Refer IS 7272 code if your are from India, else refer your respective countries labor productivity code.
      we hope we have answered your questions.
      Thanks for watching the videos.

    • @jerrymathew3355
      @jerrymathew3355 3 ปีที่แล้ว

      @@roarkacademy-civilengineer5905 not clear

    • @jerrymathew3355
      @jerrymathew3355 3 ปีที่แล้ว

      @@roarkacademy-civilengineer5905 I am not asking about the civil standard but resource working and cost allocation doubt.

    • @roarkacademy-civilengineer5905
      @roarkacademy-civilengineer5905  3 ปีที่แล้ว

      @@jerrymathew3355 Hi
      1) So is it better to set Max in decimal rather than %?
      yes
      2) Can we continue assigning decimal values to material ?
      Yes, assign the decimal for materials
      3)What would be difference?
      we are allocating the persons/materials, so its better to assign in terms of decimal rather than percentage.
      4) How to differentiate cost assigned if a person is working on 2 project
      If a person is working for multiple projects then his cost will not be going to differ coz, for example head mason cost is 1500rs means his cost will be same for the different projects, so need to make the difference in the cost.
      5) how will cost be allocated in that case if person has a salary of 30000.
      In general the Engineers are allotted for particular project/task , if that task/project completed then he will be allotted to the another project/task.
      6) Multiple projects-
      plane and schedule separately for different projects by using MS Project. Allocate the persons based on that.

  • @srinjoydas6644
    @srinjoydas6644 2 ปีที่แล้ว

    Thank you

  • @santoshnamdev1238
    @santoshnamdev1238 2 ปีที่แล้ว

    किसी एक बिल्डिंग प्रोजेक्ट्स की प्लानिंग कैसे करते उसका वीडियो शेयर कीजिये सर

  • @jerrymathew3355
    @jerrymathew3355 3 ปีที่แล้ว

    How to set actual start and end date as it is very difficult to track start end for each task for a project with 1000 tasks and most of the time no one has a record that when exactly things started.

    • @roarkacademy-civilengineer5905
      @roarkacademy-civilengineer5905  3 ปีที่แล้ว

      Hi
      In general in the construction site all the activity details are tracked regularly by the concern persons and updated according to that in the MSP/primeavera.

  • @mohdasadullakhan6095
    @mohdasadullakhan6095 3 ปีที่แล้ว

    Please know how to add resources site engineer for all task as 1 engineer is sufficient for project,as engineer look for all task in field tell me I want to know it

    • @roarkacademy-civilengineer5905
      @roarkacademy-civilengineer5905  3 ปีที่แล้ว

      Hi,
      Yes, one Engineer is sufficient to look after the small project. Just for an example, I assumed that, one task will start before ending of the another task. It is not possible to allocate the same person for both the works which are at the same time, thats way I have increased the resources.I hope I have answered your question.
      Thanks for watching the video, keep supporting, like, share and subscribe to channel.

  • @shababimran
    @shababimran 2 ปีที่แล้ว

    How to prepare s curve?

  • @shababimran
    @shababimran 2 ปีที่แล้ว

    Video is not visible properly