Thank you. I have a question after I disconnected the supply from the main power in the case of the test.... After the generator starts and supplies the emergency switch board, what will be the fate of the electricity generated during the emergency, because in the case of the examination, the main generator is the one that supplies the power,
Sir, during the test of Emergency Generator, the TIE BREAKER between MSB and ESB will automatically open. then the MSB has still normal power. But the ESB is totally blackout during the test and the back up Emergency generator will start and gives supply to ESB.
Yes, to avoid damaging the radar and other bridge equipment. always inform the bridge duty officer to shutdown radar and ecdis prior blackout simulation test.
Wow very good post migo.. good working habits. ❤❤❤❤
thank you for your great video sir, thats really help..
Thank you
Thank you Lecky
Thank you and pls make another video how to setting the 45 sec time relay and point as the located
Great video
Thank you for watching sir..
Thanks for your vidoe
thank you.keep watching
Ayos ka lecky
Thank You Sir,
Thanks a lot
Thank you. I have a question after I disconnected the supply from the main power in the case of the test.... After the generator starts and supplies the emergency switch board, what will be the fate of the electricity generated during the emergency, because in the case of the examination, the main generator is the one that supplies the power,
Sir, during the test of Emergency Generator, the TIE BREAKER between MSB and ESB will automatically open. then the MSB has still normal power. But the ESB is totally blackout during the test and the back up Emergency generator will start and gives supply to ESB.
Sir how to solve problem in case emergency generator cannot auto load when main generator black out
For on load test should we required to turn off radar equipment etc ...kindly reply
Yes, to avoid damaging the radar and other bridge equipment. always inform the bridge duty officer to shutdown radar and ecdis prior blackout simulation test.
@@leckylouie yup ...many Thanks
Sir paano Yung dalswang g/e nka parallel tapos pag tsnggalen Ang load Ng Isang g/e nag prefential trip
SIR SAAN MAKITA ANG TIMER RELAY PARA MEET NIYA YONG BELOW 45 SECOND.
sir,.sa.loob ng.emergency.switchboard, andoon ang mga.timer relay. naka.set ng.SECONDS.