Very beautiful explanation......all details measured.... This video is very important for all civil engineering student's....because theory is not important but practical is most important 👌 👏 👍 Thanks a lot....🙏🙏
The soil sample used in the CBR test should pass from 20 mm size and retained on 4.75 mm size. Is it correct? Or, the soil pass from 20 mm sieve can be completely used without control the 4.75 mm sieve. Could you explain this clearly please? Thank you.
If all material passes a 19.0-mm sieve, the entire gradation shall be used for preparing specimens for compaction without modification. If there is material retained on the 19 mm sieve, the material retained on the19 mm sieve shall be removed and replaced by an equal amount of material passing the 19.0-mm sieve and retained on the 4.75-mm sieve obtained by separation from portions of the sample not otherwise used for testing. From a sample having a mass of 35 kg or more, select a representative portion having a mass of approximately 11 kg for a moisture density test and divide the remainder of the sample to obtain three representative portions having a mass of approximately 6.8 kg each.
If I test one mould with 10kN Proving ring capacity and other mould of same soil with 5OkN capacity Proving ring.! Do I get same CBR values??? If not how it varies.!?? Plz explain sir.!! Waiting for your reply!!
The capacity of proving ring only metters when CBR % is high Soil normally cen be tested with 10kn however when you are testing Wmm material which required 100% CBR value then you have to use 50kn ring
In highway 19 mm sieve is very important , in all gradation you will find 19 mm sieve , 20 mm sieve is never used in highway, it is used in concreting work only, 19 mm sieve is used in soil , CTB , BM , DBM , BC , SURFACE DRESSING , STONE MASTIC ASPHALT, BITUMEN COLD MIX ,DLC & PQC.I think you got your answer.
Modified compaction mould) As per IS 2720 (Part VIII) 1980, IS 10074 Cylindrical mould of Mild steel having volume of 2250 cc with an internal diameter of 150 ± 0.1mm and an internal effective height of 127.3 mm ± 0.1mm. Fitted with a detachable base plate and removable extension collar with 60mm height.
Very beautiful explanation......all details measured....
This video is very important for all civil engineering student's....because theory is not important but practical is most important 👌 👏 👍
Thanks a lot....🙏🙏
@@NidhiPandit-kv1qk Thank you very much
Excellent Video ever in my life. Excellent...Excellent...Excellent
Thank You for appreciation
instablaster
Great sir... Great... No word to explain
Thanks a lot
Great.... Work is done with higher accuracy... Thanks sir
Very very useful video l hope you will prepare other videos too. Thanks so much
Superb work sir,
Love from Pakistan ❤
Excellent video. A detailed video. Helpful for all.
Glad it was helpful!
Thanks a million,what a great video kudos
The best CBR tutorial video!
Thank you
Sir aap ki sb vedoes bahut acchi hoti hai thanks
Very nice you have been super liked by Civil Engg testing walk
Excellent job please do a video on field cbr
Hello sir
In this video you explain very well
Really appreciate
However should be mentioned test reference and swelling%
Sir .. how you are taking proving ring reading. Are you multiplying every division with 5.?
great work! Can i use this video for my class?
nic team work & effort thanks sir
Very good video 👏
The soil sample used in the CBR test should pass from 20 mm size and retained on 4.75 mm size. Is it correct? Or, the soil pass from 20 mm sieve can be completely used without control the 4.75 mm sieve. Could you explain this clearly please? Thank you.
If all material passes a 19.0-mm sieve, the entire gradation shall be used for preparing specimens for compaction without modification. If there is material retained on the 19 mm sieve, the material retained on the19 mm sieve shall be removed and replaced by an equal amount of material passing the 19.0-mm sieve and retained on the 4.75-mm sieve obtained by separation from portions of the sample not otherwise used for testing. From a sample having a mass of 35 kg or more, select a representative portion having a mass of approximately 11 kg for a moisture density test and divide the remainder of the sample to obtain three representative portions having a mass of approximately 6.8 kg each.
@@HIGHWAYGUIDE Thanks for your clear answer..
Sir har mould main omc same rakhna kyaa ya phir increase karna hai
Good information 👍
Sir, why we took the %MDD as 97.00% at the end of the video ?
As the compaction % of subgrade is 97%
@@HIGHWAYGUIDE How did we find the value of 97% in the video? I couldn't find it, sir.
very nice video 👏👏👍👍hat's off you
Sir weight off compectd soil me m2 ka value kaha se liye hai plse sir reply
Sir ye 56blows konsi is code pe likha hai? Is 2720 part 16 pe to milla nhi
ASTM me dekho
To good sir its so use full
Sir if we don't want to soaking strength of CBR value is it necessary to conduct soaking CBR results as per is condition.
Yes
You did not take a dial gauge reading before and after the soaking to determine the swell
You are right
Sir is it possible to came compaction over 100 in cbr
Excellent work
wow . Perfect. Thank YOU
Thank you too!
@@HIGHWAYGUIDE sir how we can touch with you.. For asking questions?
Dia of mould 150mm & Height of mould 175 then volume of mould 2250 ? How it is
175 height is including with collar which is 50 mm so while calculating volume , you have to take height 175 - 50 = 125 mm
Generally mould height is considered 127.4. You can measure it in laboratory.
Sir kuch case mai all moulds pr 56 blows dete hai. But is video mai 10 25 56 aise diye. Aisa kyu sir
This is not as per IS code
Please see in description
at minute 25:12 some mistake
If mistake so nice of you
sir when you compacted 10 its each layer 10 compaction?
Yes
@@HIGHWAYGUIDE sir how to calculate concentrate load ?
If I test one mould with 10kN Proving ring capacity and other mould of same soil with 5OkN capacity Proving ring.!
Do I get same CBR values??? If not how it varies.!??
Plz explain sir.!! Waiting for your reply!!
Same CBR value but you have to change calibration factor.
The capacity of proving ring only metters when CBR % is high
Soil normally cen be tested with 10kn however when you are testing
Wmm material which required 100% CBR value then you have to use 50kn ring
sir aap jo bhi test batate hain uska exel sheet jarur dal dijiye sir taki hamlog ko bhi help ho jaye
Mould no.08 is 11350 not 10350
Good morning sir,why taken CBR Penetration,2.5&5 some body peoples tell that's standard load given is code,any coinsder 2& 7.5
No idea what is the opinion of people ?
Peoples are also tell mention code,so he coinsder,But why only 2.5 MM& 5MM Penetration standard reading coinsder
CBR KE value 100 % se jyada ho skti h kya sub base layer ke liye
Yes
Sir GSB ka CBR Kaise karte h?
CO efficient foctar kaishe nikale sir aap ne div multiple kar rahe hai sir please calculation .
Already posted a video
Thank u sir
Sir aap ke video Gjab hai m bhut dekhta hu
Nice vidio sir
Thanks for appreciation.
Sir 56 blows se bhi kar sakte h
As per IS code 56 blows is allowed
2.5 & 5.0 per standard division kya hai sir please bataye
Unable to understand your question.
2.5- 1370
5-2055
Sir How calculate the CBR at 98Percent dry density
Please see the last part of the video
Sir how to calculate load ? Formula
Please see full video
test is gsb ka cbr hai sir.soil ka cbr
Shandar jabardast jindabad
Formula me kon si value put krni h ..formula me put krke btao.or ye v btao ki value kahan se leni h
I have already posted video in detail please go through.
Kitni bar compact karna padta hai
Request you please see full video.
Sir, material कितना लेते हैं weight
All is mentioned in my video , see with interest.
How to get proving ring load factor
Clith-cam.com/video/XCqC8GC-TA8c/w-d-xo.htmlk on below link
Awesome sir
Keep on watching
Pl post the how to calculate percentage MDD video sir
Will do soon
5 kg hi surcharge wto Kyu rakhte hain
It is codal provision.
Hello sir
Can u tell me how to calculate proving ring constant
th-cam.com/video/XCqC8GC-TA8/w-d-xo.html
Total capacity / Total division
Thnx for tutorials
Thanks for appreciation.
Sir yh detail kaun s code m h
AASHTO T 193-99 ,2003
Excellent
Thanks
Multiplying factor kaise calculate kre
th-cam.com/video/XCqC8GC-TA8/w-d-xo.html
good video
Simple wagth Kitna liya
Please see full video
Sir 19 sive kaha hoti he o to 20 ki hoti he
In highway 19 mm sieve is very important , in all gradation you will find 19 mm sieve , 20 mm sieve is never used in highway, it is used in concreting work only, 19 mm sieve is used in soil , CTB , BM , DBM , BC , SURFACE DRESSING , STONE MASTIC ASPHALT, BITUMEN COLD MIX ,DLC & PQC.I think you got your answer.
Sir % of mdd kaise nikalte hai
OK , I will post separate video.
Great 😊
Thanks for the visit
But sir only 10 stock
Please see whole video.
Could u send this code plz...sir
Download this code , AASHTO T 193-99 ,2003
Sir omc and mdd ka bi video banao plz
Already posted
Thanks you
Welcome
👍👍👍
Super
Sir calculation ke sath samjhana tha
Please see whole video with interest
@@HIGHWAYGUIDE sir bol bol ke samjhate hai to Jada samajh me aata hai
Nice....
Thanks for appreciation.
Great
Thanks
Sir 20.7 kese aaya Plz tell ne
See last part of the video
can someone explain to me how to convert 70kg/cm^2 to 1370kg plz???
mould dia is 5cm hence 1370/(area of mould)=70kg/cm^2
👍👍👍👍👍👍☺☺☺😊☺
If the dia of mould is 15 cm and height of mould is 17.5 cm then how the volume comes as 2250 cc ?
Modified compaction mould) As per IS 2720 (Part VIII) 1980, IS 10074
Cylindrical mould of Mild steel having volume of 2250 cc with an internal diameter of 150 ± 0.1mm and an internal effective height of 127.3 mm ± 0.1mm.
Fitted with a detachable base plate and removable extension collar with 60mm height.
175-47.7=127.3 mm
47.7 is the spacer height
👍👍👍👍👍