For those who want to know the changes made to the Update #01 project, so they can follow, here they are: 1. Successor Activity of CON-1060, that is CON-1070, has a lag of 5 days 2. Successor Activity of CON-1120, that is CON-1130, has a lag of 5 days 3. Predecessor Activity of CON-1180, that is CON-1130 is added, without lag. (Correction) Pause @0:50 to verify.
There is not a 30 day lag between CON-1180 and CON-1190. Instead, what is creating the gap is that there is a relationship between CON-1130 and CON-1190.
@@PJMScheduling Thank you for the correction, and I'd like to express my heartfelt gratitude for your incredibly detailed playlist tutorial on TH-cam. It has been immensely beneficial in aiding my learning of this software.
For those who don't know where the PJMSS-BL1 *Baseline Schedule* went: 1. Open PJMSS-UP1 *Update #01* project. 2. Project tab > Assign Baseline 3. Primary > (Remove *Baseline Schedule*) > OK 4. Project tab > Maintain Baseline 5. (Select *Baseline Schedule*) > Restore > YES to unlink 6. Go to Projects 7. PJMSS-UP1 *Update #01* is now under Updates WBS optional: 8. Cut and Paste PJMSS-UP1 *Update #01* to Baseline WBS
For those who want to know the changes made to the Update #01 project, so they can follow, here they are:
1. Successor Activity of CON-1060, that is CON-1070, has a lag of 5 days
2. Successor Activity of CON-1120, that is CON-1130, has a lag of 5 days
3. Predecessor Activity of CON-1180, that is CON-1130 is added, without lag. (Correction)
Pause @0:50 to verify.
There is not a 30 day lag between CON-1180 and CON-1190. Instead, what is creating the gap is that there is a relationship between CON-1130 and CON-1190.
@@PJMScheduling Thank you for the correction, and I'd like to express my heartfelt gratitude for your incredibly detailed playlist tutorial on TH-cam. It has been immensely beneficial in aiding my learning of this software.
it was a great list of tutorials.. watched every bit of it
Thank you! So glad it helped and it was very kind of you to leave a comment.
thanks for all videos.
For those who don't know where the PJMSS-BL1 *Baseline Schedule* went:
1. Open PJMSS-UP1 *Update #01* project.
2. Project tab > Assign Baseline
3. Primary > (Remove *Baseline Schedule*) > OK
4. Project tab > Maintain Baseline
5. (Select *Baseline Schedule*) > Restore > YES to unlink
6. Go to Projects
7. PJMSS-UP1 *Update #01* is now under Updates WBS
optional:
8. Cut and Paste PJMSS-UP1 *Update #01* to Baseline WBS
It looks like the comparison tool job sessions is not available anymore? Does anyone know why or is it just my having trouble accessing? Thanks.
Hi Carlos, it's available at tools.pjmss.com/
nice. where are the subsequent lectures??
You'll have to share some ideas of what you'd like to see! Here are my other P6 videos: th-cam.com/play/PLb4HL9nfn-ei_GUpAozd4jbL4XJzDimbG.html
After these 10 parts of schedule from scratch which part is next
To resource loading and further cost loading
Thanks for the ideas! I've done quite a few cost loading videos, but maybe I'll add resource loading and a cost loading one specific for this series.