JC le Roux
JC le Roux
  • 11
  • 116 411
Tutorial - How to create a planned percentage (% Planned) field in Microsoft Projects.
In this video, we're going to show you how to calculate the planned percentage in Microsoft Projects. If you're a project manager or just someone who uses Microsoft Projects for tracking and planning your projects, this tutorial is for you. We'll take you through a step-by-step process on how to set up and calculate the planned percentage of your project, which is a key metric for measuring project progress. Whether you're a beginner or an experienced user, this video is sure to enhance your understanding of Microsoft Projects and help you track your projects with ease. So, grab a pen and paper and let's get started!"
I've posted the details of the formulas on our website here - lerouxconsulting.co.za/informative-video-series
For more information on our MS Project course for Engineering and Construction Professionals - www.lerouxconsulting.com/ms-project-construction/
มุมมอง: 24 274

วีดีโอ

Le Roux Consulting
มุมมอง 2472 ปีที่แล้ว
Le Roux Consulting
Boost your ability to evaluate EOT's using CCS Candy
มุมมอง 2.2K2 ปีที่แล้ว
I wrote an article for the Builder an Architect magazine in July 2021 where I provided a number of ways in which principal agents can enhance their ability to evaluate extension of time claims. The principles focus on the submission of a programme that has the required integrity to accurately show or calculate the impact of delays on a schedule. I've been asked by a lot of readers to give some ...
The principles of WBS planning for scheduling in CCS Candy
มุมมอง 5K3 ปีที่แล้ว
This is a preview of one of the lessons in our online CCS Candy Planning and Scheduling course. We explore the principles of WBS and how important it is to conceptualise a proper WBS for your project before scheduling can start. To get more information on our CCS Candy Planning and Scheduling course, go to bit.ly/CCSCANDY
How to add Variable Material Resource Costs in MS Project
มุมมอง 14K3 ปีที่แล้ว
This is an MS Project tutorial for construction schedules that show you how you can add variable material resource costs into your MS Project schedule. Variable material cost will contract and expand as your duration on a task increases or decreases.
How to create hammocks in MS Project
มุมมอง 7K4 ปีที่แล้ว
For any advanced scheduler, Hammocks must form part of your skill set. A hammock is a very versatile task that can assist you in your construction scheduling effort. In this video I show you why hammocks are important and how you can add hammocks to your MS project construction schedule. If you are interested in learning how to compile a real construction schedule using MS Project, check out ou...
How to compile a construction schedule if you are a Subcontractor
มุมมอง 5K4 ปีที่แล้ว
Subcontractors will know how difficult it is to compile a construction schedule that is coordinated with the main contractor's programme. As a subcontractor you also know how difficult it is to prove entitlement of claims and how easily contractors bully you to take liability for delays that weren't your fault. In this video I show subcontractors how they can use a simple system to compile prog...
Prospective delay analysis using MS Project
มุมมอง 42K4 ปีที่แล้ว
Having the ability to perform prospective delay analysis on your schedule is a critical skill that any contractor, engineer or principal agent must posses. In this video I show you a practical example of how you can apply prospective analysis using a schedule in MS Project.
How to use Cost Rate Tables in MS Project
มุมมอง 6K4 ปีที่แล้ว
In this video, we will look at some practical tips of applying different rates to your tasks in MS Project and using the cost rate tables.
How to compile your tender estimate using MS Project
มุมมอง 4.5K4 ปีที่แล้ว
For contractors who price a lot of lump sum contracts, having an effective system to compile your tender price can have a huge impact on the amount and quality of tenders you are able to submit in a month. Tender submissions drive your company's revenue. If you don't tender enough, you won't have work. If you tender inaccurately, you'll soon be out of business. So how can you use a system that ...
Why is it important to Cost load a construction schedule in MS Project?
มุมมอง 6K4 ปีที่แล้ว
This video is part of our online MS project course for construction and engineering professionals. I've been asked many times, "why is it important to cost load a schedule". In this video I give a quick breakdown of why it is so important, what methods you can use to cost load and what you can achieve once you cost-loaded your MS project schedule

ความคิดเห็น

  • @anshulkushwaha4350
    @anshulkushwaha4350 3 วันที่ผ่านมา

    can we also use it to create a planned percentage based on late dates?

  • @milner267
    @milner267 23 วันที่ผ่านมา

    Thanks JC. for clarity, I saw you sped through the part where you'd have to baseline the newly added tasks. would that baseline activity have to be done every single time a new task is added?

  • @sameerapremarathna3956
    @sameerapremarathna3956 หลายเดือนก่อน

    Please upload more videos

  • @shivsaurabh5922
    @shivsaurabh5922 หลายเดือนก่อน

    Your starting assumption is wrong. % complete in msp means ( % planned complete) and we have to customise formula for % actual complete

    • @JCleRouxx
      @JCleRouxx หลายเดือนก่อน

      Not sure what you base this on. % complete is only populated once you start adding actual values to the schedule.

    • @shivsaurabh5922
      @shivsaurabh5922 หลายเดือนก่อน

      @@JCleRouxx correct, my mistake

  • @roldanduarteholguin7102
    @roldanduarteholguin7102 3 หลายเดือนก่อน

    We want to share with Companies, Universities and Governments 57 years of successful professional experience in several countries, in Oil and Gas, Petrochemical, Steel, Hydroelectric, Engineering and Construction Projects. Since 1981 we have been developing the Digital Twin, which is the most complete technological tool to optimize all types of Compa-nies, Cities and Countries. th-cam.com/video/eadaQiL_AK0/w-d-xo.html th-cam.com/video/fXlp4QLdWQs/w-d-xo.html

  • @roldanduarteholguin7102
    @roldanduarteholguin7102 3 หลายเดือนก่อน

    Export the Azure, Chat GPT, Revit, Plant 3D, Civil 3D, Inventor, ENGI file of the Building or Refinery to Excel, prepare Budget 1 and export it to COBRA. Prepare Budget 2 and export it to Microsoft Project. Solve the problems of Overallocated Resources, Planning Problems, prepare the Budget 3 with which the construction of the Building or the Refinery is going to be quoted.

  • @Johanswnpl
    @Johanswnpl 4 หลายเดือนก่อน

    Faaaaaanks !!

    • @JCleRouxx
      @JCleRouxx หลายเดือนก่อน

      You're weeeeelcome! 😊😊

  • @AJ-nm9gb
    @AJ-nm9gb 4 หลายเดือนก่อน

    but isnt cost same? , in real world cost per litre of fuel keeps changing right?

  • @abdellahfaouzi1412
    @abdellahfaouzi1412 4 หลายเดือนก่อน

    Thank you so much you saved my life !!!! I subscribed to your channel . For those who found the problem of the appearance of zero (0) for all values, you must check that you saved baseline of your project.

    • @JCleRouxx
      @JCleRouxx หลายเดือนก่อน

      That's great news! Thanks for the additional tip.

  • @gopalmahajan4140
    @gopalmahajan4140 5 หลายเดือนก่อน

    That activity will be critical than, how to avoid that activity in the critical activity chart?

  • @ig7061
    @ig7061 5 หลายเดือนก่อน

    Hello, thanks for the video. I have one issue that I cannot fix. For example, I have a project manager who is involved in the whole project from start to finish, but it is very difficult to assign to him all the tasks that I have in the project because they overlap, and it is too hard to control from an overallocations point of view. Is there any trick to assign the project manager (PM) to the entire project without causing overallocations?

    • @gopalmahajan4140
      @gopalmahajan4140 5 หลายเดือนก่อน

      PM can be allocated to the activities explained. The common resources can be used there. This shall not hamper

  • @mohasoamakara5085
    @mohasoamakara5085 5 หลายเดือนก่อน

    This is awesome. May I ask how can I contact you? I would like to volunteer in one of your projects!

  • @user-ih5qf9oj6f
    @user-ih5qf9oj6f 5 หลายเดือนก่อน

    Hi, can i get some help. Actually i just need to show my target % vs actual % I've been searching 100 videos, and none have done so. is microsoft project unable to do such simple task? im abit frustrated

  • @milner267
    @milner267 7 หลายเดือนก่อน

    Thanks so much for sharing. a question for you: is there a way to show this as either an "S-curve" within the report tab, or within task usage?

    • @milner267
      @milner267 4 หลายเดือนก่อน

      Hi JC, still interested in this topic. is it possible to see within task usage? because while it is possible to see at at a status data, what was planned, key stakeholders would want to know what that curve would look like. any help would be appreciated

  • @jonnyland7
    @jonnyland7 8 หลายเดือนก่อน

    Great! it solved my problem in a big project!

    • @JCleRouxx
      @JCleRouxx หลายเดือนก่อน

      Awesome!

  • @weamibrahem4736
    @weamibrahem4736 8 หลายเดือนก่อน

    Very interested.. Can we get the formula that you used

    • @JCleRouxx
      @JCleRouxx หลายเดือนก่อน

      You can find the formula here - bit.ly/3KxKyI2

  • @benpienaar2310
    @benpienaar2310 9 หลายเดือนก่อน

    Thank you Kobus! Almost all of my headings and tasks calculates the % planned perfectly except a few Headings that shows ERRORS. Any advice?

    • @user-em5kq8rm6w
      @user-em5kq8rm6w 9 หลายเดือนก่อน

      Did you set the baseline?

    • @benpienaar2310
      @benpienaar2310 9 หลายเดือนก่อน

      @@user-em5kq8rm6w That helped! Thank you!

    • @nimarafienejad6466
      @nimarafienejad6466 6 หลายเดือนก่อน

      I faced the same issue and after few hours noted that those Task lines added to schedule after setting the Baseline. maybe this is your issue as well?

  • @ig7061
    @ig7061 9 หลายเดือนก่อน

    Thanks !!!

  • @aseyeaflakpui3859
    @aseyeaflakpui3859 9 หลายเดือนก่อน

    Hi JC, Thank you for this video. I am facing a challenge here. I followed all the steps but I am getting 100% for all activities including the ones yet to start. What could be the problem?

    • @aseyeaflakpui3859
      @aseyeaflakpui3859 9 หลายเดือนก่อน

      I think I've found what the problem is. I hadn't set my status date. Thank you

  • @dantevanniekerk
    @dantevanniekerk 10 หลายเดือนก่อน

    Kobus... How do I get hold of you to make use of your services?

  • @dunyojustice4050
    @dunyojustice4050 10 หลายเดือนก่อน

    Please how can have access to the software I'm interested

  • @honeystarism
    @honeystarism 11 หลายเดือนก่อน

    Hi, thank you for this tutorial. I tried following the steps, but some of the tasks are #ERROR. Is this caused by the duration, as some of my tasks are in weeks and months. Can you help? Thank you.

    • @nimarafienejad6466
      @nimarafienejad6466 6 หลายเดือนก่อน

      I faced the same issue and after few hours noted that those Task lines added to schedule after setting the Baseline. maybe this is your issue as well?

  • @funfunny9319
    @funfunny9319 11 หลายเดือนก่อน

    Thanks JC for sharing this. Am I correct if I say every time you insert delays, you set a new base line? If yes, how we can record lets say 20 different delays on a project? I am asking this because we can set up to 11 baselines on microsoft project.

  • @TheEugenezandberg
    @TheEugenezandberg 11 หลายเดือนก่อน

    Awesome vid ! Only problem is that I keep getting a syntax error when using your formula .. I even tried to "retype" the highlighted error but to no avail :( Any advice ?

    • @JCleRouxx
      @JCleRouxx 11 หลายเดือนก่อน

      Hi Eugene, difficult to tell without looking at the input. It may just be a misplaced space or bracket causing the issue?

    • @TheEugenezandberg
      @TheEugenezandberg 11 หลายเดือนก่อน

      @@JCleRouxx I was very careful to follow the exact sintex and spacing but still doesn't work

  • @user-jo5cx1wn2h
    @user-jo5cx1wn2h 11 หลายเดือนก่อน

    Thank you. the video was great.

    • @JCleRouxx
      @JCleRouxx หลายเดือนก่อน

      Thanks man! So happy you found it valuable.

  • @nazirramguthee6568
    @nazirramguthee6568 11 หลายเดือนก่อน

    Hey JC, what is the document you presented in the last section called?

  • @adrianmondolo
    @adrianmondolo 11 หลายเดือนก่อน

    Hi! I have a question. Is there any way to change the actual status date? in order to open the project and have the time to create a report with the status of one week ago for example.

    • @JCleRouxx
      @JCleRouxx 11 หลายเดือนก่อน

      You will have to set the status date on the Project tab each time.

  • @shaileshmodhia7600
    @shaileshmodhia7600 11 หลายเดือนก่อน

    Sir nice explained. However formulas used in customised columns could not be seen. Will u provide the formulas

    • @JCleRouxx
      @JCleRouxx 11 หลายเดือนก่อน

      You can find the formulas here - lerouxconsulting.com/ms-project-for-construction-articles-and-resources/creating-a-planned-percentage-complete-field-in-microsoft-project

  • @adrianmondolo
    @adrianmondolo ปีที่แล้ว

    you are the love of my life!! you explained this really easy and slow. I couldn't ask for more. Thank you sooooo much! 🥰

    • @JCleRouxx
      @JCleRouxx 11 หลายเดือนก่อน

      🤣 Great to hear. You'll have to get past my wife first though!

  • @user-zf3rx6ci8d
    @user-zf3rx6ci8d ปีที่แล้ว

    The deeper you get into the subtasks, the less accurate it becomes. Level 1 +- 1%, level 2 from %1 to 2%, level 3 up to 3%. i use the formula set at your link page. did i set something wrong?

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Interesting. The formula gives me solid accuracy even in lower levels. Just double check if you've set the summary settings correctly?

  • @gayatrilshinde1560
    @gayatrilshinde1560 ปีที่แล้ว

    is we have column name baseline estimated start and finish date or we have to use baselinestart and finish date

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Use the Baseline Estimated Start and Baseline Estimated Finish in the formula. These are standard fields in MSP already.

  • @pwardseitz
    @pwardseitz ปีที่แล้ว

    Very interesting use of this tool. The big question is how does actual cost data get entered? If it can pull from the accounting software, this is an exciting way forward for us. If it involves manual entry, not so much.

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Good point. I'm sure you would be able to draw it in from Excel, so if you can get your actuals out into excel and bundle them under the BOQ items, it should be possible.

  • @morganshongwe6501
    @morganshongwe6501 ปีที่แล้ว

    Wow Thanks JC this really worked, ive been strugling

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Aah Morgan, great news. I've also had my fair share of struggling with this %-complete column.

  • @JuanPerez-hb5kb
    @JuanPerez-hb5kb ปีที่แล้ว

    Hi JC, I am JC as well. I really liked the tutorial on the correct way to show Planned %. I do have a question, does MS Project have Labor Units? I have not seen this

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Hi JC! . MS Project can only show labor units in "manhours". You can certainly export the data and then convert it if you like.

  • @milkymikez100
    @milkymikez100 ปีที่แล้ว

    Great thanks

  • @user-yg6ud4ui8p
    @user-yg6ud4ui8p ปีที่แล้ว

    Beautiful

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Thanks Ben!

  • @abhishekdwivedi1692
    @abhishekdwivedi1692 ปีที่แล้ว

    Very nice presentation. 👍👍

  • @Shahadaleqiel
    @Shahadaleqiel ปีที่แล้ว

    Hi, I face an issue we are behind schedule and the summary task shows we are ahead, that incorrect. so I follow the same as you did but I got an error in the summary task. how can I fix that? thanks in advance!

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Hi Shahad. There can be many reasons for this. It could be that some of the tasks below the summary task is not included in Baseline, or that a Baseline does not exist for certain tasks. Also check that the status date is correctly set, check for any manual schedule tasks.

    • @Shahadaleqiel
      @Shahadaleqiel ปีที่แล้ว

      @@JCleRouxx can you please help me with that I tried to fix the issues for 2 months if you can give me your email so we can discuss these issues it will be much appreciated! this task Is much important to me

    • @Shahadaleqiel
      @Shahadaleqiel ปีที่แล้ว

      Hi, when I followed up on the steps, I got 1 for all activities in the Updated % planned? so the planned percentages change to 100% based on the Updated % planned column those are issues I face now .. can you help with that?

  • @susuchen4638
    @susuchen4638 ปีที่แล้ว

    Hello JC; I watched your video about the pROJECT, i want ask you how you make the sheet with dependencies and delayed shecedule,

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Hi Susu. You can simply add those fields in your view to have the same sheet. To do the update requires a more complex process which is a bit cumbersome to explain here. Have a look at our other videos or consider the course where this is explained in detailed, step-by-step.

  • @getfanmedia
    @getfanmedia ปีที่แล้ว

    good work

  • @aadiritz
    @aadiritz ปีที่แล้ว

    Is there a way to show the previous end date and new end date together on the Gant? Or Baseline is the only to view it?

  • @Benza96
    @Benza96 ปีที่แล้ว

    Hello Kobus, what I have come to realize is that you would have a scenario as the one you have just discussed in this video, whereby the contractor has his responsibility in impacting a delay and so has the client (in my case as a result of variations) ...what I need to know is how is it fair to factor in the contractor's risk impact if at the end the contractor incurs delay damages per contract Simply put why calculate a finish variance if you are determining impact of delay in an ongoing active project?

  • @milner267
    @milner267 ปีที่แล้ว

    Thank you Mr. Le Roux, as this video was very education and inspiring. I must ask, however; wouldn't an accurate % complete calculation be the (ACTUAL COST - COST VARIANCE) / BASELINE COST? I ask because using the actual cost which would have been along the course of the project, may seem to bloat the progress percentage, in my opinion. Thank you again

  • @benchalk3579
    @benchalk3579 ปีที่แล้ว

    Hi JC, do you have a downloadable template for this ?

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Hi Ben, we do share a lot of templates as part of our MSP course. You can check it out at www.lerouxconsulting.com/ms-project-construction/

  • @enochsithole2993
    @enochsithole2993 ปีที่แล้ว

    Hi JC . Do not have course that one can do with you for MS Project

    • @JCleRouxx
      @JCleRouxx ปีที่แล้ว

      Hi Enoch. Yes indeed, check out our course at www.lerouxconsulting.com/ms-project-construction/ .

  • @mresso8489
    @mresso8489 2 ปีที่แล้ว

    Download link for any PO Construction LOG ?

  • @ujangsonjaya8348
    @ujangsonjaya8348 2 ปีที่แล้ว

    Very helpful. Good video that explains prospective analysis in a easy to understand, to know, to prepare. love much

    • @JCleRouxx
      @JCleRouxx 2 ปีที่แล้ว

      Glad you enjoyed it!

  • @shalukawijesiri9292
    @shalukawijesiri9292 2 ปีที่แล้ว

    591 subscribers explain how much people hate these advertisements. After everything its not a promotion at all

  • @infrared8068
    @infrared8068 2 ปีที่แล้ว

    Sir, your tutorials are awesome. I want your Ms project material for practice