#1 - PMP Exam Earned Value Course (Calculate EAC)

แชร์
ฝัง
  • เผยแพร่เมื่อ 15 ธ.ค. 2024

ความคิดเห็น • 63

  • @govindayadav5251
    @govindayadav5251 ปีที่แล้ว +2

    Amazing..
    Was confused for many days.
    Now it's clear
    Thanks..

    • @Praizion
      @Praizion  ปีที่แล้ว

      Glad to hear that! Thanks for commenting and best wishes Govinda!

  • @bamakaze
    @bamakaze 3 ปีที่แล้ว +2

    Great work! Loved this video!

    • @Praizion
      @Praizion  3 ปีที่แล้ว +1

      Thank you so much!

  • @christianodorsa77
    @christianodorsa77 8 ปีที่แล้ว +3

    EAC's are now crystal clear ! Thanks Phil and Praizion team. Watching all your videos to fine tune my studies let's see if I can make it on this May 30th.

    • @Praizion
      @Praizion  8 ปีที่แล้ว +2

      Thanks buddy. You can do it! Take our EVM Mock test when you get a sec! EARNED VALUE APOCALYPSE QUIZ: tiny.cc/evmapoc2
      PASSWORD: pmpstudent

    • @Praizion
      @Praizion  8 ปีที่แล้ว

      Congrats Christiano! You did it!

  • @stevennicol2744
    @stevennicol2744 6 ปีที่แล้ว +1

    Thanks Phil... I have an exam scheduled in 3 weeks. I am spending lots of time, hopefully not too much on Cost Management. Your explanations are second to none... short and sweet... Thanks from Steve

    • @Praizion
      @Praizion  6 ปีที่แล้ว

      Thank you Steven! Yes be careful with cost. Remember EXECUTING is the "little BIG kahuna" on the exam!

  • @najeebahmed4922
    @najeebahmed4922 8 ปีที่แล้ว +2

    Dear Phil,
    Thx for your videos and easy to understand coaching methods.
    You are rightly shockec as I got around 15 EVM questions in my PMP exam today, including TCPI, EAC and BAC but I am confident that I got all of them correct and they were easy marks for me.
    Oh and I did clear the exam today.
    Thx once again for your excellent service to project management community.
    Regards,

    • @Praizion
      @Praizion  8 ปีที่แล้ว

      AWESOME Najeeb! Congratulations!!! Thanks for your support!

  • @anitha978
    @anitha978 4 ปีที่แล้ว +1

    Hiiiiii..Phil, as I have mentioned early, you made me fall in love with PMBOK and I followed your videos and passed the exam. 3ATs n 2 ATs. Thank you once again :)

    • @Praizion
      @Praizion  4 ปีที่แล้ว +1

      Hearty congrats Anitha! Thank you :)

  • @melanieirschick6986
    @melanieirschick6986 6 ปีที่แล้ว +2

    Thank you Phill for explaining it in such a simplistic manner. It really helped bring clarity to my confusion.

  • @kionbristow7268
    @kionbristow7268 5 ปีที่แล้ว +2

    Thanks for the explanation and solid examples! Such clarity is appreciated.

  • @ishaqhussain3892
    @ishaqhussain3892 4 ปีที่แล้ว +1

    Marvellous!! It was excellent explanation which I was getting confused since 8 months....
    Thanks alotttt.

    • @Praizion
      @Praizion  3 ปีที่แล้ว

      Happy to help Ishaq.

  • @chukwuemekakingsleyeze6340
    @chukwuemekakingsleyeze6340 5 ปีที่แล้ว +7

    When I pass my PMP exam, I will buy you a beer. You just switched the light bulb in my head on. Thanks Phil

    • @Praizion
      @Praizion  5 ปีที่แล้ว

      Thanks Buddy! My Lager days are behind me LOL....but a Perrier with a wicked lime for sure 😂

    • @Somoneleftthetoiletseatup
      @Somoneleftthetoiletseatup 10 หลายเดือนก่อน

      Did you pass@@Praizion

  • @oluwagbengajohnsonbankole6786
    @oluwagbengajohnsonbankole6786 4 ปีที่แล้ว

    Eku ise sir. Olorun ama sagbara dotun. I love this video

  • @abunura2013
    @abunura2013 5 ปีที่แล้ว +1

    Comparative EAC studies compare the predictive accuracy of two or more EAC formulas. The general approach is
    They adjusted the data for problems created by scope and baseline
    changes, and evaluated formula accuracy by stage of completion

    • @Praizion
      @Praizion  5 ปีที่แล้ว

      Interesting! Please share a link! Thank you!

  • @anilsson8343
    @anilsson8343 7 ปีที่แล้ว +1

    Thanks Phil! Great explainaion. Much clearer now!

    • @Praizion
      @Praizion  7 ปีที่แล้ว

      Thank you Ami!

  • @l.r.gutliffe1005
    @l.r.gutliffe1005 4 ปีที่แล้ว +1

    fantastic! thank you so much!!!!

    • @Praizion
      @Praizion  4 ปีที่แล้ว

      You're very welcome!

  • @AnuragSingh-tz1wr
    @AnuragSingh-tz1wr 8 ปีที่แล้ว +2

    This was very useful, thanks for the explanation I am much more confident in solving EAC questions now.

    • @Praizion
      @Praizion  8 ปีที่แล้ว

      Thanks Anurag. All the best on your test!

  • @fistonndongalo139
    @fistonndongalo139 4 ปีที่แล้ว +1

    Thank you very much for this great lesson .

  • @gbemisowemimo6084
    @gbemisowemimo6084 4 ปีที่แล้ว +1

    Thanks Phil for explicitly breaking down EAC calculations.
    I used this & some of your other TH-cam tutorials to prep for my PMP exams.. I passed in August 2020. Your tutorials are very very much on point.
    Thanks & Keep up the good work

    • @Praizion
      @Praizion  4 ปีที่แล้ว

      Congratulations 🎉 Thanks 🙏

  • @Hariwa.m
    @Hariwa.m 4 ปีที่แล้ว +1

    Thank you so much, but would be great if you could zoom it a little bit out.

    • @Praizion
      @Praizion  3 ปีที่แล้ว

      Thanks for the suggestion.

  • @astridpotter9548
    @astridpotter9548 7 ปีที่แล้ว +1

    Great explanation, thanks a lot Phill!

    • @Praizion
      @Praizion  7 ปีที่แล้ว

      Thanks Astrid.

  • @haileysailor
    @haileysailor 7 ปีที่แล้ว +4

    I understand when to use each formulas. However, I don't understand how to determine when each will occur. For example, EAC=BAC/CPI. This formula is under the assumption that the CPI will be constant throughout the project. HOW am I able to assume that the CPI will be constant? Under what basis? What key information will tell me that the CPI will remain constant throughout the project? Thanks

    • @Praizion
      @Praizion  7 ปีที่แล้ว

      The question will always have some clues. Take our Earned Value Apocalypse quiz. Google "earned value apocalypse" and it should come up. The questions normally state COST PERFORMANCE IS TYPICAL (meaning it can be expected to continue) or they may state CPI will remain constant or CPI will not change or is not expected to change or based on your current cumulative cost performance. Stuff like that.
      Now if it says A-typical, then that means it will not be continuing into the future so use another formula like the one for ETC work being performed at the budgeted rate.

    • @juristuCDPC
      @juristuCDPC 4 ปีที่แล้ว

      @@Praizion any recent, working link to that?

  • @rheuer111
    @rheuer111 7 ปีที่แล้ว +1

    Great video -- many thanks!

    • @Praizion
      @Praizion  7 ปีที่แล้ว

      Thank you Robert!

  • @kurtmcmichael2045
    @kurtmcmichael2045 4 ปีที่แล้ว +1

    Great information. Hope it’s still good for 6th edition

    • @Praizion
      @Praizion  4 ปีที่แล้ว

      It is! EAC does not change. Same old Kurt.

  • @mohammedaltaf4877
    @mohammedaltaf4877 7 ปีที่แล้ว +1

    Excellent way to explanation thanks

    • @Praizion
      @Praizion  7 ปีที่แล้ว

      Thanks Mohammed.

  • @mohamedhusseien332
    @mohamedhusseien332 9 ปีที่แล้ว +2

    Merry Christmas Mr unique

  • @roselin76
    @roselin76 8 ปีที่แล้ว +1

    This is superb!

    • @Praizion
      @Praizion  8 ปีที่แล้ว

      Thanks Roselin!

  • @angelarichmond8898
    @angelarichmond8898 4 ปีที่แล้ว +1

    THANK YOU!

    • @Praizion
      @Praizion  3 ปีที่แล้ว

      You're welcome Angela!

  • @hasanmikrani3304
    @hasanmikrani3304 5 ปีที่แล้ว +1

    Great

  • @michaelb.5091
    @michaelb.5091 7 ปีที่แล้ว +1

    Damn these EACs! Good tutorial!

    • @Praizion
      @Praizion  7 ปีที่แล้ว

      LOL! Aren't they awful Michael? Gotta swot them all like fleas! Glad the tutorial helps!

  • @cheikhamifaye
    @cheikhamifaye 6 ปีที่แล้ว

    Thank you so much Phil!

  • @zeinebkechiche8924
    @zeinebkechiche8924 6 ปีที่แล้ว

    Mr.Phill if the BAC contains Management reserves what would this change ?

    • @Praizion
      @Praizion  6 ปีที่แล้ว +1

      OMG! NOoooo! No management reserves in the Budget at Completion! Contingency reserves only!
      The Project Budget has management reserves but that is useless in the EVM context :)
      Join www.savageonsaturday.com to discuss these and other queries!

    • @zeinebkechiche8924
      @zeinebkechiche8924 6 ปีที่แล้ว

      Mr Phil I asked this question because we refer the BAC to the total budget of the pj i was confused that's why I asked thanks for your help

    • @zeinebkechiche8924
      @zeinebkechiche8924 6 ปีที่แล้ว

      Maybe it was a wrong question but i was so confused

    • @Praizion
      @Praizion  6 ปีที่แล้ว +1

      No its a great question and now I understand. Sorry the world of EVM vs PMI sometimes can be confusing when it comes to the word "BUDGET". No one expects to use Management reserves so EVM measurements are not based on it. Quoting from Humphrey's and Assoc: The standard definition of management reserve is an amount of contract budget set aside for management control purposes (known unknowns) rather than designated for the accomplishment of one or more tasks. It is not part of the performance measurement baseline (PMB), but is included in the total contract budget.

  • @arvindkakade1812
    @arvindkakade1812 4 ปีที่แล้ว +1

    Very good video!

  • @anthonyowolabi
    @anthonyowolabi 7 ปีที่แล้ว

    Nice vlog

    • @Praizion
      @Praizion  7 ปีที่แล้ว

      Thank you Toyin!

  • @davidmatlaw7833
    @davidmatlaw7833 6 ปีที่แล้ว +1

    99% of time, budgets are as unreliable as annual forecasts, except for super simple projects.