Explain Difference between Delete and Dissolve Activity in Primavera P6

แชร์
ฝัง
  • เผยแพร่เมื่อ 26 ต.ค. 2024
  • #Softedemy,#PrimaveraP6,#Dissolve
    In this tutorial, let us learn the Difference between Delete and Dissolve Activity in Primavera P6
    As part of project scheduling, you might be feeling that some activities are no longer required whenever there is a change in the scope of work.
    some users simply delete the unwanted activities, but by doing that the relationships will also be removed and the linked activities will then be open-ended.
    So in this video, I will show you how to use the dissolve activities feature, which allows us to remove activities and bridge the gap in the logic.
    Let's take a sample project and see how this works now.
    I am creating a sample project now.
    Let me add activities A-1, A-2, A-3, and A-4.
    Link all these activities Finish to Start
    Give durations as 4 days for 4 activities and schedule this project. You will see the Gantt chart like this with relationships.
    Now, suppose if we want to nullify activity A-3 from the schedule.
    If we directly delete activity A-3, see that the relationships will be broken with activity A-2 and activity A-4, which is not good practice and not recommended.
    Now, let us dissolve activity A-3 by right-clicking and selecting the Dissolve option. Click Yes to confirm.
    If you have enjoyed this tutorial, please give me a like, share, and comment.
    Contact Details
    Email for Contact: Softedemy@gmail.com
    Facebook Group Link: tinyurl.com/yz...
    LinkedIn Page: tinyurl.com/ke...

ความคิดเห็น • 5

  • @SoftEdemy
    @SoftEdemy  3 ปีที่แล้ว

    For any query contact us on our email : info@softedemy.com

  • @yousef2508
    @yousef2508 2 ปีที่แล้ว

    Great explanation. Thanks for sharing.
    Please explain how to quickly analyse a schedule, when we go to a project that is partially done.
    Thank you

    • @SoftEdemy
      @SoftEdemy  2 ปีที่แล้ว +1

      Dear yousef. There is no process to review a schedule. For a quick review. I recommended the progress line review technique and earned value management review of each WBS. From EVM we can easily determine the Schedule performance. There are a lot of other techniques I used to do for quick review. That I cannot explain in text. Let's have a quick online meeting I will share my tricks.

    • @yousef2508
      @yousef2508 2 ปีที่แล้ว

      @@SoftEdemy Thanks buddy, that would be great; I'll send you a meeting invitation on your email.

    • @SoftEdemy
      @SoftEdemy  2 ปีที่แล้ว +1

      Sure. We will decide the timing on email. Because I have busy schedule