Difficult network diagram example with lag solved

แชร์
ฝัง
  • เผยแพร่เมื่อ 8 ม.ค. 2015
  • Check out www.engineer4free.com for more free engineering tutorials and math lessons!
    Project Management Tutorial: Difficult network diagram example with lag solved.
    Please support my work:
    PATREON | / engineer4free
    Every dollar is seriously appreciated and enables me to continue making more tutorials

ความคิดเห็น • 234

  • @ellie3821
    @ellie3821 3 หลายเดือนก่อน +4

    Hello, I can't describe how much this video has helped me with studying for my masters in PM. I was so lost while trying to figure out what's in the lectures as there's no explanation. I am really glad I found this video! thanks a lot

    • @Engineer4Free
      @Engineer4Free  3 หลายเดือนก่อน +2

      Glad to hear it! Plenty more PM videos on the channel, or also engineer4free.com/project-management ☺️

  • @mg7831
    @mg7831 ปีที่แล้ว +2

    Man I'm in Uni studying Civil Engineering with a mid coming up in two days and not alot of time to understand this video greatly helped especially the gant chart the professor never used it your a lifesaver I truly wish you happiness in life. Lots of Love From Jordan

  • @wizardOfRobots
    @wizardOfRobots 6 ปีที่แล้ว +30

    Hey man, I'm a software engineer by profession and I totally needed this for my work. Know that you are being appreciated from halfway across the world. Lots of love from India!

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว +3

      That's awesome, I'm glad to hear it helped, and thanks a lot for the really kind words!!!

  • @tf1266
    @tf1266 ปีที่แล้ว

    Fantastic, because my lecturer has made really difficult lagging problems for both the gantt charts and for the critical path method. This has helped heaps thank. Love your channel.

  • @joshuaniranjan2078
    @joshuaniranjan2078 8 ปีที่แล้ว +1

    I have my engineering project management exam today and this video has helped me finally understand how to compute forward and backward passes with various relationships and lag. Thank you so much!

    • @Engineer4Free
      @Engineer4Free  8 ปีที่แล้ว

      +Joshua Niranjan That's awesome!!! Thanks for letting me know, I always like to hear success stories :)

  • @febeangulo4844
    @febeangulo4844 5 ปีที่แล้ว +2

    My professor expects us to know all these just by reading the book. We don't do exercises in class, we don't practice at all. Your videos have helped me a lot! I am currently studying the Masters in Project Management. YOU ARE AWESOMEEEE :) !! Thanks a lot!

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Thanks for the awesome comment Febe!!! Glad I can help =)

  • @skanderhaffar6958
    @skanderhaffar6958 6 ปีที่แล้ว +41

    That moment when you get the PDM structure from a video better than the noted one from your professor's seminar. Here take my like bro! cheers for the tutorial :D

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว +2

      Thanks for this comment bro, cheers!!

    • @skanderhaffar6958
      @skanderhaffar6958 6 ปีที่แล้ว +2

      I was watching your video as I was preparing for my PM final today. Yep my professor was mean enough to get us a similar complicated network and yep I totally nailed that shit! Many thanks!

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว +3

      hahaha word, always expect and be prepared for the worst... glad this video helped you crush it!!

    • @csgoawping9665
      @csgoawping9665 5 ปีที่แล้ว

      hahahaha !!!! SO DAMMMMMNNNNNNN TTTTTRRRUUUUEEEEE !!!!!!

    • @aamirashai4072
      @aamirashai4072 3 ปีที่แล้ว

      @@skanderhaffar6958 I'm going to accomplish that feat tomorrow. Wish me luck! :)

  • @alcxy8563
    @alcxy8563 6 ปีที่แล้ว +2

    pretty easy now to understand actually, took me half the video to realise what was happening, but now it all makes perfect sense! thanks a ton man!

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว

      haha yeah these ones are weird, but very likely to show up on exams because of their weirdness. Glad you like it, it's video #22 out of 46, do check out the rest at engineer4free.com/project-management or just the youtube playlist th-cam.com/play/PLOAuB8dR35oeyKU0ojIxD8Muf6Mwc8ugW.html =)

  • @tpopejr
    @tpopejr 9 ปีที่แล้ว +2

    Been studying for the Project+ cert. Your videos have been very helpful. They're presented clearly and concisely using simple terms. Your descriptions gave me several 'ah ha' moments. Thanks!

    • @Engineer4Free
      @Engineer4Free  9 ปีที่แล้ว

      Tom Pope That's awesome to hear! You can find all of the PM videos that I made here: engineer4free.com/project-management Good luck on your certification!

  • @pankajsingla9565
    @pankajsingla9565 5 ปีที่แล้ว +2

    Thanks for sharing it. I watched to multiple times to understand however it clears my doubt about FS, SS, SF, FF

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Awesome glad to hear it!! If you want some more detailed videos on FS, SS, SF, FF then check out videos 16 - 22 here: engineer4free.com/project-management =) =)

  • @SelamSuk
    @SelamSuk 2 ปีที่แล้ว +4

    I really like your teaching approach. And thank you for breaking down this into simpler forms. I found you when I study for a construction and scheduling class.

  • @blatantlyniv
    @blatantlyniv 7 ปีที่แล้ว

    thanks for uploading this! it made me understand pdm which i have been struggling for days!!

    • @Engineer4Free
      @Engineer4Free  7 ปีที่แล้ว +1

      Happy that I was able to help!

  • @alexhamm6096
    @alexhamm6096 5 ปีที่แล้ว +1

    Thank you!!!! My scheduling professor is HORRIBLE lol........ive been lost for a couple weeks and your 12min. vid just answered all my questions...why did I not check youtube sooner lol

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Haha, sorry to hear that Alex but glad I can help =)

  • @urwa91
    @urwa91 6 ปีที่แล้ว

    Thanks for the video man!

  • @KM-yl9lc
    @KM-yl9lc 3 ปีที่แล้ว +1

    Excellent video, from an excellent channel. Thank you very much!

  • @elenigk8938
    @elenigk8938 5 ปีที่แล้ว +1

    You are my savior man! There is a hope to pass the exam now! Thanks a lot

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Thanks Eleni, hope the exam goes well!!

    • @raymondsamman4015
      @raymondsamman4015 3 ปีที่แล้ว

      Lol. . Engineer4free always do the best

  • @nipunimanage9061
    @nipunimanage9061 2 ปีที่แล้ว

    You are a life saver. THANK YOU!!!!!

  • @fachrierireza2643
    @fachrierireza2643 8 ปีที่แล้ว

    Thank you so much. Your explanation was vivid & clear.

    • @Engineer4Free
      @Engineer4Free  8 ปีที่แล้ว

      +Fachri Eri Reza Thanks for the feedback! You can check out all 45 PM tutorials I made here: www.engineer4free.com/project-management.html :)

  • @syedmuhammadalishah4344
    @syedmuhammadalishah4344 6 หลายเดือนก่อน

    I was searching for this type of example thanks dude

  • @muhammadjamalmaruf4141
    @muhammadjamalmaruf4141 3 ปีที่แล้ว

    Well done Man .. appreciated

  • @AshanPeirisNCVU
    @AshanPeirisNCVU 8 ปีที่แล้ว

    awesome video. Thanks man

  • @muhdkhairulamirinum3985
    @muhdkhairulamirinum3985 6 หลายเดือนก่อน

    thank you. it is very clear

  • @ameurrs
    @ameurrs 2 ปีที่แล้ว

    Very Very helpful! Thank you so much:)

  • @dervisorhan2737
    @dervisorhan2737 2 ปีที่แล้ว

    Excellent Job

  • @jaimegarlick6388
    @jaimegarlick6388 4 ปีที่แล้ว +1

    Thanks for the help! Really appreciate it!

  • @bahran-tutorials8845
    @bahran-tutorials8845 2 ปีที่แล้ว

    you are a brilliant teacher

  • @ualihanomarov3401
    @ualihanomarov3401 6 ปีที่แล้ว

    Thank you brother, it really helped me to pass my midterm 👍🏻

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว

      Glad t hear it! Thanks for watching and commenting :)

  • @mohamedhafidi4911
    @mohamedhafidi4911 หลายเดือนก่อน

    you are the best, thank you

  • @anasahmed6305
    @anasahmed6305 2 ปีที่แล้ว

    Well explained!

  • @bagyaranathunga2942
    @bagyaranathunga2942 5 ปีที่แล้ว +1

    Thank you very much.really helpful and great explanation.

  • @wissalbenamor8503
    @wissalbenamor8503 6 ปีที่แล้ว

    you, sir, are my savior. thanks!

  • @manewyalew2410
    @manewyalew2410 2 ปีที่แล้ว

    great. your make for me clarity for that I missed the one class and more than that.

  • @delphinengwa4412
    @delphinengwa4412 5 ปีที่แล้ว +1

    Thanks very much for the video. It was quite educative.

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Hey you're welcome, thanks for watching =)

  • @Stabey
    @Stabey 4 ปีที่แล้ว

    Your the best mate

  • @officialmintt
    @officialmintt 5 ปีที่แล้ว +1

    So clear. Thank you!

  • @abbaska2967
    @abbaska2967 ปีที่แล้ว

    Nice explanation

  • @dheeraj6364
    @dheeraj6364 3 ปีที่แล้ว +1

    THANKYOU, SO MUCH FOR THIS LECTURE

    • @Engineer4Free
      @Engineer4Free  3 ปีที่แล้ว +1

      You're welcome Dheeraj! =)

  • @farnazansari9697
    @farnazansari9697 4 ปีที่แล้ว +1

    You are a life saver!!! Thanks🧡

  • @sohaib3903
    @sohaib3903 8 ปีที่แล้ว

    Great Video, I got same kind of question in my examination and I nailed it . Thanks (Y)

    • @Engineer4Free
      @Engineer4Free  8 ปีที่แล้ว

      +Sohaib Iqbal Glad to hear it, that's awesome!!!!

  • @omedkakarash4780
    @omedkakarash4780 2 ปีที่แล้ว

    Thank you

  • @treashel718
    @treashel718 8 ปีที่แล้ว

    excellent sir. it's. tricky bt totally correct.

  • @ugurkose5825
    @ugurkose5825 4 ปีที่แล้ว +1

    Thank you for sharing with us. I really priciate that

    • @Engineer4Free
      @Engineer4Free  4 ปีที่แล้ว +1

      Glad you like it, thanks for watching!!

  • @lylyyy279
    @lylyyy279 2 ปีที่แล้ว

    Believe it or not, our teacher has written the same question on her pamphlet for us, thank u so much

  • @interiorarttv8449
    @interiorarttv8449 3 ปีที่แล้ว +1

    Thank you so much, that was so helpful

    • @Engineer4Free
      @Engineer4Free  3 ปีที่แล้ว +2

      Glad to hear it!! The full playlist is here too: engineer4free.com/project-management =)

  • @prakharkhatri5228
    @prakharkhatri5228 8 หลายเดือนก่อน

    thanks man

  • @venkataramana3718
    @venkataramana3718 9 ปีที่แล้ว

    Thank you. Very helpful

  • @Ff-gs1kt
    @Ff-gs1kt 5 ปีที่แล้ว

    understandable videos great

  • @bashayeralm5640
    @bashayeralm5640 7 ปีที่แล้ว

    Thankyou

  • @stephenwearen8564
    @stephenwearen8564 7 ปีที่แล้ว +1

    Great Videos, very helpful. How would the total and free float be calculated when there is lag and also where the are finish to finish relationships? Thanks

    • @saharchapuk688
      @saharchapuk688 7 ปีที่แล้ว +1

      Did you get the answer for your question please, if you did, can you share it.
      Thank you.

  • @alirehman6937
    @alirehman6937 5 ปีที่แล้ว +2

    Awesome, please upload for LEAD relationship as well

  • @madhusudankc8218
    @madhusudankc8218 7 ปีที่แล้ว

    Useful one

  • @sayalihake2725
    @sayalihake2725 7 ปีที่แล้ว

    really useful

  • @Sam-qd4pv
    @Sam-qd4pv 2 ปีที่แล้ว

    Thanks

  • @moksha8694
    @moksha8694 7 ปีที่แล้ว

    helpful . a lot!

  • @csgoawping9665
    @csgoawping9665 5 ปีที่แล้ว +1

    Loved it !!!!!

  • @22cranbrookave
    @22cranbrookave 8 ปีที่แล้ว

    Great video. Helped to solve one question for assignment.:)))

  • @zakariyeabdullaahi6076
    @zakariyeabdullaahi6076 2 ปีที่แล้ว

    thanks sir

  • @zakiya2925
    @zakiya2925 8 ปีที่แล้ว

    and I did have that type of teacher....thanks for your video, this is very tricky stuff

    • @Engineer4Free
      @Engineer4Free  8 ปีที่แล้ว

      +Zakiya Mitchell haha glad to hear it's helping! You can check out the rest of my PM tutorials here: www.engineer4free.com/project-management

  • @areumdapta2228
    @areumdapta2228 4 ปีที่แล้ว

    how do you solve for the free float with that one?

  • @andysunny90
    @andysunny90 7 ปีที่แล้ว

    Great to solve with you.

  • @shreyashsmart9270
    @shreyashsmart9270 2 ปีที่แล้ว

    Thankyou 🙌 from india.

  • @lalitnaryan8104
    @lalitnaryan8104 5 ปีที่แล้ว +1

    great solution.

  • @sheilacavino7294
    @sheilacavino7294 3 ปีที่แล้ว +1

    thank very much ,now i can solve the network diagram

    • @Engineer4Free
      @Engineer4Free  3 ปีที่แล้ว

      Mission accomplished! The full playlist can be found at engineer4free.com/project-management if you're interested in checking it out!

  • @ritaindahlestari4065
    @ritaindahlestari4065 8 ปีที่แล้ว

    Thank you for the videos on precedence notation diagram! it is very helpful for students like me as it is very clear!
    But, may I ask what will you do in this situation.
    There are 2 activities e.g. activity A and B, and they have the same successor, activity M. A have FF relationship with M while B have normal FS relationship with M, but B to M (FS relationship) has a larger value of ES than A to M (FF relationship).
    Which value will you choose in this case?

    • @Engineer4Free
      @Engineer4Free  8 ปีที่แล้ว +1

      +Rita Indah Lestari In that case, the duration of A, B, and M are all significant too. For the A-M relationship, you can first find the EF of M, then subtract the duration to find the ES of M. Then you need to check the B-M relationship. You can first find the ES of M based on E. You would then compare the ES of M given by A and then also as given by B, and chose the larger value. You must chose the larger value in the forward pass because in order to satisfy both predecessors. As you can see, the logic AND the durations of all activities in question would affect the outcome. Hope that helps!

  • @Kohyongkeng
    @Kohyongkeng 2 ปีที่แล้ว

    Hi, for this example. is there ways to calculate Total Float and Free Float?
    Thank you

  • @PannegarSachin
    @PannegarSachin 5 ปีที่แล้ว +1

    You made it look so simple .

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Thanks, hope you found it helpful

  • @reverbnation2389
    @reverbnation2389 4 ปีที่แล้ว +1

    thank you very much.love from sri lanka.

  • @botaniizzet7066
    @botaniizzet7066 6 ปีที่แล้ว

    Ohhh thank you so much now i get it have exam tomorrow!

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว

      Awesome, hope it went well!!!

  • @amanbanga6506
    @amanbanga6506 5 ปีที่แล้ว +2

    Life saver❤️

  • @amansen8200
    @amansen8200 7 ปีที่แล้ว

    thank you

  • @aamirashai4072
    @aamirashai4072 3 ปีที่แล้ว +1

    My life is complete today... Such a beauty you are.

    • @Engineer4Free
      @Engineer4Free  3 ปีที่แล้ว +1

      Thanks Aamir! Check out engineer4free.com/project-management and you're life will be even more complete =)

    • @aamirashai4072
      @aamirashai4072 3 ปีที่แล้ว +1

      Definitely. I've already subscribed to this channel. Hope to see great content in future too.

  • @mihilaadithya1205
    @mihilaadithya1205 ปีที่แล้ว

    hay man You are a save my life thanks a lot sr 0_0 love you so much keep it up !

  • @ugurtiryaki8361
    @ugurtiryaki8361 4 ปีที่แล้ว +1

    PERFECT !

  • @erickademe
    @erickademe ปีที่แล้ว

    Having my Exam next week thank you for saving me

  • @malondyshange6576
    @malondyshange6576 ปีที่แล้ว

    Very helpful in my school work... Can you please do a video on Line of balance control, please tag me on one if was already uploaded

  • @karlxia9459
    @karlxia9459 ปีที่แล้ว

    My teacher is juse mean like this. Thank you for the video.

  • @sadammbabali8436
    @sadammbabali8436 6 ปีที่แล้ว

    thanks

  • @dumstzzile
    @dumstzzile 5 ปีที่แล้ว +1

    working backward, is there a method of reading the gant chart to get the values or a formula to quickly and with less effort get them values?

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      You can only read the ES and EF values off the Gantt chart. The numbers that each activity on the Gantt chart start and stop on are the ES and EF values. You could use them to populate the network diagram and skip the forward pass, but you will still need to do the backward pass. I recommend drawing the gantt chart and network diagram, and doing the actual forward pass, and then quickly checking the ES/EF values against the gantt chart to make sure that it looks like you have no errors. That's more valuable to you then using then using the Gantt chart to skip a step.

  • @asirfaysalrafin142
    @asirfaysalrafin142 4 ปีที่แล้ว +2

    Thanks for the great tutorial!
    In this diagram, we have 3 paths in total. They are (i) A-B-D-G-H, (ii) A-C-E-G-H, (iii) A-C-F-H
    If there were no lags, we could just add up all the durations of all activities in a single path to get the critical path (project duration).
    Now, is there any way to get the critical path by adding up the duration of the activities and ± lag?
    Kind regards.

    • @tarashankarsharma3372
      @tarashankarsharma3372 4 ปีที่แล้ว

      No, it is not that if there is no lag we simply add all the activities to get critical path and duration of project.
      We must follow the pattern of network diagram and work accordingly with it to get critical path and total project duration. And type of relationship given to activity must be taken in consideration.

    • @asirfaysalrafin142
      @asirfaysalrafin142 4 ปีที่แล้ว

      @@tarashankarsharma3372 I see. I tried an AOA network for a different table whlch helped me understand the concept more. Thanks for your reply. Have a great day!

    • @Engineer4Free
      @Engineer4Free  4 ปีที่แล้ว

      Thanks for all the good questions and answers to both of you 😊

    • @tarashankarsharma3372
      @tarashankarsharma3372 4 ปีที่แล้ว

      th-cam.com/video/qeKKW6-R-UU/w-d-xo.html
      Can you please subscribe my channel.

  • @abdoashraf9470
    @abdoashraf9470 5 ปีที่แล้ว +1

    Thanks sir

  • @ASHIKCHENGAPPA
    @ASHIKCHENGAPPA 7 ปีที่แล้ว

    I have a scenario wherein an merge activity node has got both FS of 5 days lag and SF of 20 days lags. How to make a network diagram for the same, Please could you post a video on the same.

  • @seanmcdermott8181
    @seanmcdermott8181 5 ปีที่แล้ว +2

    I'm still struggling with the backwards pass!! We saw one small example in a copy, no actual drawn out example and we have to do a 32 length activity with FS and SS events.

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Hey Sean, I recommend taking a step back then. Definitely watch videos 4-9 here: engineer4free.com/project-management and if you have time (like 2 hours or so) then I recommend just watching everything up to the video that we're commenting on (which is video 22). Going through them all will fill you in with bits of insight here and there and will just get you some more practice to get comfortable with the topic. Cheers let me know how your progress goes!

  • @tabark5792
    @tabark5792 2 หลายเดือนก่อน +1

    7:37 I don't understand the last activity H the relation is SF we should tack the ES of activity F its 3
    +2 lag its 5 and for activity G we should tack the ES its 7 +2 lag its 9 so we tack 9 in Forword not 11 and the CPM will become ABDGH

  • @jobellegelido
    @jobellegelido 3 ปีที่แล้ว

    Is the Gantt chart plotted for activity E correct? It says E can start 3 days after C finishes with a duration of 1. So if C finishes on day 3, E should be be plotted on day 4? Right?

  • @ekongekpenyong6320
    @ekongekpenyong6320 7 ปีที่แล้ว

    Hi, do you also have examples of network diagrams with subsequent tasks having 2 or more of the same predecessors?

    • @Engineer4Free
      @Engineer4Free  7 ปีที่แล้ว

      Hey Ekong, yeah check out video 15 here engineer4free.com/project-management

    • @ekongekpenyong6320
      @ekongekpenyong6320 7 ปีที่แล้ว

      Great, thanks a lot for the link. Will get busy, cheers.

  • @sauravyadav7984
    @sauravyadav7984 3 ปีที่แล้ว +1

    Which tool you are using to draw the diagrams?

    • @Engineer4Free
      @Engineer4Free  3 ปีที่แล้ว

      I've got a list of all the hardware and software here: engineer4free.com/tools =)

  • @Feri9
    @Feri9 5 ปีที่แล้ว +1

    this guy worth a million like

  • @yohanephiri5591
    @yohanephiri5591 7 ปีที่แล้ว

    good presentation

    • @Engineer4Free
      @Engineer4Free  7 ปีที่แล้ว

      Thanks!

    • @yohanephiri5591
      @yohanephiri5591 7 ปีที่แล้ว

      but why is it that the ES of each first activity in a CPM is a 0?

    • @Engineer4Free
      @Engineer4Free  7 ปีที่แล้ว

      Watch video #1 here: engineer4free.com/project-management . The 0 comes from the way that I draw Gantt charts, and gets directly translated into the way that I draw network diagrams. In that video you will notice that 0 represents the beginning of day one. 1 represents the end of day one and also the beginning of day two. 2 represents the end of day two, but also the beginning of day three, and so on. In that video, you can see this pattern, because activity A ends at 2 which is clearly the end of the second day, but activity B starts also at 2, but is the beginning of the third day. In a network diagram, the EF of A would be 2, and the ES of B would be 2. The same logic applies to why activity A stars at 0, not 1. Does that help?

  • @yashpratapsingh643
    @yashpratapsingh643 2 ปีที่แล้ว

    hello, I'm a masters student and i want to understand the concept of free float in the examples where lag is in picture i would be glad if you can help me out in regard to this. Thank u

  • @EdAg08
    @EdAg08 6 ปีที่แล้ว +1

    What do you do when you have 2 dependencies on one activity, one has a lag and the other doesn't. Any ideas?

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว

      On the forward pass, consider what the ES of the successor would be from each predecessor independently, factoring in lag if applicable and then take the largest ES of the scenarios as actual ES of the successor. For the backward pass, assess the LF of a predecessor for each of it's successors independently, taking any lag into consideration and then take the smallest LF of the scenarios as actual LF of the predecessor. You can find the ES or LF of one activity caused by a related activity whether or not lag is present, so if some relationships have lag and others don't, it won't affect the way that we approach the problem. Does that clear it up?

    • @EdAg08
      @EdAg08 6 ปีที่แล้ว +1

      Thank you for the response.

  • @dumstzzile
    @dumstzzile 5 ปีที่แล้ว +1

    My best by far. I also have an unrealistic problem to deal with

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Such is the life. Thanks for watching!!

  • @ICOD73
    @ICOD73 8 ปีที่แล้ว +1

    This is easier that the question the doctor gave to us in the assignment -_-

  • @mohdfaizankhan5729
    @mohdfaizankhan5729 5 ปีที่แล้ว +2

    can there be two critical paths in a network?

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Yes. If you find more than one, write them all down.

    • @FaizanKhan-kl9dr
      @FaizanKhan-kl9dr 5 ปีที่แล้ว

      @@Engineer4Free okay thanks a lot sir :)

  • @loikvokhidov7688
    @loikvokhidov7688 2 ปีที่แล้ว

    Will these kind of questions come up in PMP exam?

  • @KhetkiRaj
    @KhetkiRaj 6 ปีที่แล้ว

    We need more like how to find a Total float, free float, independent float, interfering float.

    • @Engineer4Free
      @Engineer4Free  6 ปีที่แล้ว +1

      I've just got a few videos on float, they are videos 13-15 here: engineer4free.com/project-management

  • @azmanman3454
    @azmanman3454 4 ปีที่แล้ว +1

    Hi there, what is the difference between Critical path method and Arrow diagram?

    • @Engineer4Free
      @Engineer4Free  4 ปีที่แล้ว +1

      Hi, sorry for any confusion brought about by the naming of each style of diagram. There are two types of network diagrams: Activity on Node (AON) and Activity on Arrow (AOA). In these videos I usually refer to AON as PDM, and AOA as CPM. That's local lingo for me that I originally learned, but you are actually better to use AON and AOA, it's more clear.

    • @azmanman3454
      @azmanman3454 4 ปีที่แล้ว

      @@Engineer4Free Thanks for the clarification

  • @josephikponmwosa3755
    @josephikponmwosa3755 ปีที่แล้ว

    Please can I start writing my Pdm From the left to right??

  • @Raffaelo08
    @Raffaelo08 4 ปีที่แล้ว

    what about successor ?

  • @tonyamichael8802
    @tonyamichael8802 ปีที่แล้ว

    It becomes something else to move from the gantt chart to the activity table. My lecturer just frustrated us with such as you turn to see weird pertchart...

  • @nuramajiedamohdnor6777
    @nuramajiedamohdnor6777 5 ปีที่แล้ว

    May I know how to calculate the critical path from this mixed network diagram?

    • @Engineer4Free
      @Engineer4Free  5 ปีที่แล้ว

      Critical path is formed by the sequence of activities that have LS = ES (LF = EF) that go from ES = 0 to EF = max EF. This can be read off the diagram once you have finished the forward and backward pass.