How to estimate amount of cement and sand needed for your block work

แชร์
ฝัง
  • เผยแพร่เมื่อ 5 ก.ย. 2024
  • In this tutorial I explain how to estimate the amount of cement and sand needed for laying certain amount of block. And also amount of cement and sand needed for plastering a certain area of wall.
    An example was treated to the detail. The method discussed in this tutorial can be for estimation of any area of wall or amount of block.

ความคิดเห็น • 26

  • @Bluesky_construct2567
    @Bluesky_construct2567 2 ปีที่แล้ว +5

    You remain the one person to bring justice to this estimation on this TH-cam so far. By the way, kindly avail us how you arrive at 0.275
    You swift response will be highly appreciated.
    Thanks a lot

  • @georgerether79
    @georgerether79 หลายเดือนก่อน

    Nice work mister

  • @franklinobiukwu3483
    @franklinobiukwu3483 4 ปีที่แล้ว +1

    I find this video educating.
    You're doing great!

    • @9-5data
      @9-5data  4 ปีที่แล้ว

      Thank you

  • @georgerether79
    @georgerether79 หลายเดือนก่อน

    How did the Height of the horizontal mortar change into 275mm or 0.275

  • @dapoabolarinobj8105
    @dapoabolarinobj8105 4 ปีที่แล้ว +1

    Bravo, Engr!

    • @9-5data
      @9-5data  4 ปีที่แล้ว

      Thank you sir.

  • @abbafary1445
    @abbafary1445 ปีที่แล้ว

    The vid is educative sir kudos. My Question here is, how did uou arrived at getting 0.275 vertical mortar? Thank you best regards

  • @obadex
    @obadex 3 ปีที่แล้ว

    Great work keep it up

  • @tushabejoseph7377
    @tushabejoseph7377 2 ปีที่แล้ว

    And by calculation how did you get the 10 blocks ? Minus assuming

  • @folexkendrick
    @folexkendrick ปีที่แล้ว

    Please does this account for the plastering too?

  • @tushabejoseph7377
    @tushabejoseph7377 2 ปีที่แล้ว

    How did you obtain 0.0637 in the calculation of bed mortar/horiz mortar??? . explain am lost from dt very point

  • @garpeeroberts5580
    @garpeeroberts5580 2 ปีที่แล้ว +3

    Hi, how did you obtained the 0.275 in the vertical mortar area calculations?

  • @AguEmmanuel-kn8qt
    @AguEmmanuel-kn8qt 4 หลายเดือนก่อน

    Pls how did u get the 0.275

    • @temidayoafolabi7344
      @temidayoafolabi7344 2 หลายเดือนก่อน

      for the vertical, the height of the block is 225mm. Now add the 25mm mortar at the top and also the one at the bottom of the block. You will have 25mm + 225mm + 25mm = 275mm, You can check the diagram at 2:44 . Check the red boxes.

  • @theslickking-majura5799
    @theslickking-majura5799 2 ปีที่แล้ว

    Sir kindly explain how you arrived at 0.275

  • @divinennate3226
    @divinennate3226 ปีที่แล้ว

    Pls how did you arrive at 1.3 and 1.1 as percentage of 30 and 10 respectively

    • @temidayoafolabi7344
      @temidayoafolabi7344 2 หลายเดือนก่อน

      This is how, assume the wet volume is 1 cubic meter, we are told that the dry volume is 30% more that the wet volume. What this means is that you will add 30% of wet volume to the 1 cubic meter value of the wet volume.
      see,
      Wet vol. = 1m3
      Dry vol. = (30% of 1) + 1
      =(30/100 * 1) + 1
      =(0.3 * 1) + 1
      = 0.3 + 1
      = 1.3.
      therefore, for every 1 m3 of wet volume, we have 1.3 m3 of dry volume. 1.3 in other words is a constant.

  • @olatundelateefat5177
    @olatundelateefat5177 4 ปีที่แล้ว +1

    🙌🙌🙌🙌

  • @acheampongkoranteng4847
    @acheampongkoranteng4847 3 ปีที่แล้ว

    Can this be applied to solid blocks?

    • @9-5data
      @9-5data  3 ปีที่แล้ว

      Check the channel to see video on solid blocks

  • @emmanuelodoba4623
    @emmanuelodoba4623 4 ปีที่แล้ว

    Barca go still go trophyless

    • @9-5data
      @9-5data  4 ปีที่แล้ว

      Hmmmmm. Thanks for your concern

  • @alsemi-back-up579
    @alsemi-back-up579 ปีที่แล้ว

    TOO COMPLICATED!!!!!!!!!!!!!
    HOW MANY BAGS OF MASONARY FOR HOW MANY BLOCKS!!!!!!!
    IT IS NOT ROCKET SCIENCE MAN!!!!!!!!!!!!!!