Sir ji life me kisi ne itne pyar se or itne ache se nhi samjhaya jitna acha aapne samjhya ...aapki videos ko dekhne k bad mujhe phli baar fill huaa ki mujhe bhi ab kuch aata h ...lots of love sir ji bhagwan aapko khubh tarrakki de or hmesha ap khush rakhe or aapki femily bhi always happy rahe or healthy rahe 🥰❤️🔥🙏🙌
Nice 👍 video 👌 Waiting for your next video on complete calculation on quantity of reinforcement including OVERLAPPING,BENTUP BARS , EXTRA BARS ETC ,hope to see soon Thank you Appreciate your efforts
Sir Jii thanks a lot for this video But ek request h sir ek aur video banaiye jismei rodd ka quantity nikaliye for foundation work and beam coloumn during boundary work please iska v video banaiye
Good Morning, your effort is appreciable. Just a query, will u provide rod in only one layer? Secondly if u indicate the quantity of fitters( i.e no of fitters / helper for bending and then laying assuming 30 metre or 50 m lead) per ton, it will be more useful for freshers. Thanks and Regards,
Nicely explained.. you must uploaded one more video consequently covering the details and expenditure towards cement, concrete and labour charges to fill the entire slab in one stroke.
You did not consider the development length in case of continuous slab which goes into another slab. Also the L shape length in discontinuous slab. Also bent up and extra bars. Can you also make video on that please?
Sabse aasan to yahi hai bhai... Columns Me Generally Main bar 12mm ki hoti hai... Apne column ka length nap lo kitna hai with footing ... Suppose aapka Length aaya 9 meter ab isme foundation me L bhi hota 0.4 L bhi add kar lo ... Ab 9 meter single rod to hogi nahi qki single rod laga denge to failiure k chance badh Jate hain isliye isko har 4 meter k baad kaat k jod diya hai hai or wahan pe lagta hai lap joint 0.6 meter ka, so 9/4 = 2.25 + 1 = 3.25 times lap of length 0.6 meter Length of one bar = 9 + 0.4 + 3.25(0.6) = 11.35 Meter No. Of bars = ek column me genrally 4 rod hote hain x no. Of column suppose 4 = 16 Weight of 1 meter length 12mm dia of bar is 0.82 standard (No. Of bars) x (length of one bar) x (0.82) = 16 x 11.35 x 0.82 = 148.912 kg
Yr bro amazing.. bht detail m ap samjhaty ho.. Allah apko kamiyab krn.
Thanks brother
Slab ma 12 mm 10mm tmt is best (yes or no )
@@zaidahmad6531 Yes
@@zaidahmad6531 but we always take 8 mm or 10 mm in slab
Crank ka nahi diye
Explanation is better...
Easy to understand.....
Great job sir...
Thanks brother keep watching n keep loving
Sir now days there has no given such type of information for making a slab. It's a amazing video.
ਸੌਖੇ ਤਰੀਕੇ ਨਾਲ ਸਮਝਾਇਆ ਹੈ।Good and simple!
Really great yet simple explanation
Very easy way to get very important information for all.Thanks big bro.
बोहोती सरल और आसान भाषा का उपयोग करके आप समझाते हो सर,, ऐसेही ज्ञान देते रहो सर
Brother u doing great work
U go bright in future also
Give education for us always
Ofcourse brother
ofcourse keep watching & keep loving
Bahot sandar sir......maza aa gya....itna asan to math k teacher nhi batate the
Yr bro amazing.. bht detail m ap samjhaty ho.. Allah apko kamiyab krn.
Sir ji life me kisi ne itne pyar se or itne ache se nhi samjhaya jitna acha aapne samjhya ...aapki videos ko dekhne k bad mujhe phli baar fill huaa ki mujhe bhi ab kuch aata h ...lots of love sir ji bhagwan aapko khubh tarrakki de or hmesha ap khush rakhe or aapki femily bhi always happy rahe or healthy rahe 🥰❤️🔥🙏🙌
Nice 👍 video 👌
Waiting for your next video on complete calculation on quantity of reinforcement including OVERLAPPING,BENTUP BARS , EXTRA BARS ETC ,hope to see soon
Thank you
Appreciate your efforts
yes ofcourse brother soon keep watching ❤️
Thank you sir ,this is the best vdo,, bilkul details bata diye apne clrly,,thank you sir
welcome brother keep watching n keep loving
Sir Jii thanks a lot for this video
But ek request h sir ek aur video banaiye jismei rodd ka quantity nikaliye for foundation work and beam coloumn during boundary work please iska v video banaiye
Sir apko allah ik din bohut bhara insan banayega
And i am waiting to see you a big personality.
Thank yu brother ❤️
apko b
Itna badhiya explain kiya ki sab samaj me aa gaya Thank you 😇
Yours is so educative as well as simple for all to follow ! Difference counts a good teacher !
Bahut acchi tarike se bataya aapne ✌✌✌✌✌✌✌✌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌👌
Thank u so much sir.. Baht achhe tarike samjhaya.. It's amazing.. 😊😊😊
Nice video sir keep doing it 🔥🔥🔥🔥
yes ofcourse
Civil site pe best video Banate he Bhai aap Dhanyawad
Sir Very Nice video,
Same area please make a video from foundation, column plinth
Really good video sir Thanj you so much... yeh mere liye bahut important video hein because abhi company mein training par hu so..
Thanks for this amazing helping video sir
welcome brother keep watching
Watches this video improve my knowledge thank you sir....
Love from Odisha
Good Morning, your effort is appreciable. Just a query, will u provide rod in only one layer?
Secondly if u indicate the quantity of fitters( i.e no of fitters / helper for bending and then laying assuming 30 metre or 50 m lead) per ton, it will be more useful for freshers.
Thanks and Regards,
ऐसे ही सब का उत्साह वर्धन करते रहिए
Sir, in this Bending isn't included, which would take some more quantity of steel..
Great video Sir....
But , there is no cinsideration of Lap length, bar bending amd other wastages like cut pieces that incour on site
brother allah bless you bahut hi achi tareeke se aapne samajhaya bahut bahut shukriya aapka
Sir good video but could you please upload 1more video .How much concrete material must required for this.
check playlist you will get lot of video on it
Nicely explained.. you must uploaded one more video consequently covering the details and expenditure towards cement, concrete and labour charges to fill the entire slab in one stroke.
Mene bohot video dekha he but kuch samajh nehi aya Par sirf app ne ek bar me simply samjha diya You are really Great..Brother..❤️
You did not consider the development length in case of continuous slab which goes into another slab. Also the L shape length in discontinuous slab. Also bent up and extra bars. Can you also make video on that please?
I think with your calculation, we might come up with less steel. So we will again have to order.
yes ofcourse brother soon on it too
this estimation is on simple slab which is not consideration nowadays
Do not consider Crank bar and extra bar. plz explain Crank bar calculate.and extra bar
@@civilsitevisit then what type of slab is used nowadays and will you please tell us the estimation calculation of that.
Good bro, ache se samjaya...... Good
Bhai ye to plain Reinforcement band diya aapne. Crank ya extra reinforcement ( L/4) jo har support per aayega wo keha gaya?
Lapping vi nahi hai...
Top extra bar nhi hae, beam ke bar ki calculation nhi hae
Top extra L/4 ya L/3 length tak 2 x spacing mein Dena hota hae.
Bahot khob sir me apka sary video daykata hn par bahot knowlge mila hy mujy
Does the size of steel rods are same for all the, 1st floor, 2nd floor and 3rd floor.
Nice explian, God may bless you for ur work
Sir I want to know about how to calculate concrete volume for slab
Thanks for explaining in so simple and understandable language..
Sir , plz column k steel weight calculation bta dijiye
Sabse aasan to yahi hai bhai... Columns Me Generally Main bar 12mm ki hoti hai... Apne column ka length nap lo kitna hai with footing ... Suppose aapka Length aaya 9 meter ab isme foundation me L bhi hota 0.4 L bhi add kar lo ... Ab 9 meter single rod to hogi nahi qki single rod laga denge to failiure k chance badh Jate hain isliye isko har 4 meter k baad kaat k jod diya hai hai or wahan pe lagta hai lap joint 0.6 meter ka, so
9/4 = 2.25 + 1 = 3.25 times lap of length 0.6 meter
Length of one bar = 9 + 0.4 + 3.25(0.6) = 11.35 Meter
No. Of bars = ek column me genrally 4 rod hote hain x no. Of column suppose 4 = 16
Weight of 1 meter length 12mm dia of bar is 0.82 standard
(No. Of bars) x (length of one bar) x (0.82) =
16 x 11.35 x 0.82 = 148.912 kg
Thnx for this video sir. आपने इसी वीडियो मे cement, सैंड , ऐग्रीगेट कितना लगेगा वो वीडियो भी बनाना चाहिये था.
Nice vidio bro... But,Its implimention is highly impossibele ...
how sir
Best video📹🎥📹 and good way👍
Sir for column reinforcement estimation and cement also
check playlist you will get video on it
क्या बात हे,,,,,
समझनेक तरिका भहुत खूब हे,
सुंदर,
सर,,, शुक्रिया,
सर, फाऊंडेशन और कॉलम के बारेमे भी जनकारी दिजिये। प्लिज,
Sir how much Cement concrete require for this
Visit #itimixpointnepa
You are best civil engineer bro
Sir you have not mentioned Bent-up Baar length.why?
I will upload soon video on it
Thank you Sooo much Sir..
Bhttt achi trha samjaya sb clear ho gya
Thank u very much, bt sir what about BEAMS... BEAMS also included in Slab.. Sir plss explain including with beams..
flat slab brother
Nice work sir.. You are clear concept very easy...
Thanks brother keep watching na keep loving
Normally 10 mm steel are used for roof casting and 8 mm is used for the ring itself or 8 mm steel is used for the kitchen racks etc..
yes ofcourse
Bhut achhe se aaj smjh me aaya hai sir🙏
Sir Please Upload How to Calculate Foundation Steel Quantity Video.
yes ofcourse sir keep watching
Civil Site visit
sir how to calculate beam and columns stel plz ya vdo lao na sir
Thank you so much Sir. ...
For providing great knowledge about slab stell with quantity. ...
God bless you sir. ..
How much it costs for centring work
i will make video on it soon
thank you brother 😊😊 so simple way to explain 👏👏
Uncomplite Knowledge for calculate steel mesh total quantity Because you should mention steel weight of beam
in next video you will get all knowledge
Beam should include in slab cost also please include in this video only
Very useful for me this kind of type videos.
How much steel is required (8 mm & 10 mm ) for slab of 50*48 ft single floor bungalow?Which company & what grade steel is good for slab work?
Amazing & informative video thank you so much 👏👏
Very well explained bro.....thanks a lot!
excellent slab reinforcement bar , steel , total weigh calculation price #👍👍
Thanks for giving this information....I really like it
Thank you very much for your detailed analysis very helpful
Best ho sir g aap......aapke under job mil jaye to kitna accha hoga😍
Thanku sir apne to mere jaise thodi knowledge rakne wale insan ko bohat ache se tech kiya thanks sir
Very Informative Video Sir.... kuch Hafto baad mujhe 4 slab dalwani hai...thanks
Thnku sir je...i found my slab bars for casting
Very useful information thanks dear love you from Oman
Bahut badiya samjaya appne
thanks brother
Sir apne meri puri life mai sabse easy language mai mujhe sikha diya thanku sir
And please sir beam and column ka bhi bata diye mahrbaani hogi
Thanku sir video bahut he aacha hai thanku so much concept clear karna ka liyea
Very useful information..Bhai thanks 😎😎👍👍
Thanks brother keep watching & Keep loving
Staicase ki bhi video bano sir............
Thank you so much sir
College ki teacher se axa ap sikhate hai thanks
Amazing Brother 🤩❤
Thank you sir for give me best information
Bahut hi saral tarika bataya sir thank you
Very helpful video👍
Sir ji mujhe video bhut pasand aaya thank you
Superb video bro love from Afghanistan 🇦🇫
baho hi achha samjay bhai ..thanks
Very good video ani your explanation sir super... 👍👍
Accha smjhaya aap ne.
Kirpeya neev dalte waqt or column dalne ka kharcha bhi bta dete or cement rodi reta kitna lagta ye bhi
Sir bahut achhe se samjh agya thanks sir
Very well and easily explained. Thank a lot. And upload more✌
Video bahut hi achhi lagi
It’s very helpfully thnkuuu Brother ..... keep it up
Bacho k liye achhi video hai jo fresher hai 1 month experience walo k liye ye kuchh v nahi
Sir aap bhut acha samnjha te ho ,
Very nice explanation....keep it up sir....its very helpful to us
Bhai ye to ho gya...thank you
... Concrete aur labor cost bhi bta dijiye
Lv u sir u are master of civil engineering
Bahut hi achchha sir
Bahut badiya bhai 👍
Nice. I learn lot pf things
great bro bahut bdiya samjaya aap ne ise baat pe like bantha
Sr kab se bhatak raha thaa iske lea aab ja kr k sukun mila,, Or sir kya columns or beams k lea b koi simple and accurate way h apke paas