MS Project 8 - Tracking Task Progress and Variance

แชร์
ฝัง
  • เผยแพร่เมื่อ 27 พ.ค. 2021
  • In this tutorial we will track progress through our projects using a couple weekly updates. Having established a baseline we will see our variance in both cost and schedule from our plan.
    The MS Project Series:
    MS Project 1 - Introduction "The Environment" ( • MS Project 1 - Intro (... )
    MS Project 2 - Display Settings and Saving a Template ( • MS Project 2 - Intro D... )
    MS Project 3 - Project Info and Task Entry ( • MS Project 3 - Project... )
    MS Project 4 - Task Precedence/Dependencies ( • MS Project 4 - Task Pr... )
    MS Project 5 - Entering and Assignment Resources ( • MS Project 5 - Resourc... )
    MS Project 6 - Resource Conflicts and Levelling ( • MS Project 6 - Resourc... )
    MS Project 7 - Establish a Baseline ( • MS Project 7 - Setting... )
    MS Project 8 - Tracking Progress and Variance ( • MS Project 8 - Trackin... )
    MS Project 9 - Earned Value ( • MS Project 9 - Earned ... )
    MS Project 10 - Managing Change Orders ( • MS Project 10 - Managi... )
    MS Project 11 - Crashing the Project ( • MS Project 11 - Projec... )
    MS Project Quick Tips
    Common Resource Pool ( • MS Project Quick Tip: ... )
    Master Project File ( • MS Project Quick Tip: ... )
    #PatJHeffernan

ความคิดเห็น • 14

  • @elegantuseducation2421
    @elegantuseducation2421 ปีที่แล้ว +3

    Thank you for making this process less complex. I enjoyed it

  • @nibirchowdhury3837
    @nibirchowdhury3837 ปีที่แล้ว +3

    Great video Sir. Thanks for the share.

  • @affanshakirwan6354
    @affanshakirwan6354 2 ปีที่แล้ว +2

    Thank a lot prof

  • @phemmy2008
    @phemmy2008 ปีที่แล้ว +2

    Keep up the good work

  • @abubakriqbal2355
    @abubakriqbal2355 8 หลายเดือนก่อน +1

    Thanks prof

  • @zulfikarian
    @zulfikarian 3 หลายเดือนก่อน

    Great video. But I want to ask, if somehow actual material resources used is more than what's planned. How do we express it in tracking gant?

    • @PatJHeffernan
      @PatJHeffernan  3 หลายเดือนก่อน

      Hi. The tracking Gantt shows time variance compared to plan. Resource variance is tracked numerically in the database and reported separately.

  • @zachguest3588
    @zachguest3588 ปีที่แล้ว

    What about a task that is split, or one that wasn't intended to be split and was performed in a split matter?

    • @PatJHeffernan
      @PatJHeffernan  ปีที่แล้ว +1

      Hi Zack... did I mention I hate splitting tasks... sometimes necessary, but normally to be avoided as it typically affects efficiency. No biggie... if you've split a task (and then baselined your project), just make the changes for the task to reflect actual (including any splits) and then mark it as complete the same as if it wasn't split. The program effectively ignores the space between the task components.

  • @emirtm
    @emirtm ปีที่แล้ว +1

    A little bit confused, weren't you suppose to have "baseline duration" and then change only "Actual Duration? In first instance the task "stud walls" was supposed to be completed as per the baseline but was only half way through once you changed durations

    • @PatJHeffernan
      @PatJHeffernan  ปีที่แล้ว +1

      The stud wall task still took the same amount of time, but started a day late because its predecessor (demolition) was delayed in finishing. This is reflected in the tracking gantt.

  • @Engineerselva
    @Engineerselva 26 วันที่ผ่านมา

    I cannot find the Task board option in my MS PROJECTS 2019. Can you help me in this?

    • @PatJHeffernan
      @PatJHeffernan  26 วันที่ผ่านมา

      I’m sorry, that must be frustrating. Unfortunately, I’m not setup to do troubleshooting assistance.