គម្រោងស្តារ និងលើកកម្រិតគុណភាពផ្លូវជាតិលេខ៤ ($110Millions). សម្រេចបានជាង៥០% គ្រោងបញ្ចប់ចុងឆ្នាំ២០២៦

แชร์
ฝัง
  • เผยแพร่เมื่อ 4 ก.ค. 2024
  • Welcome to my Channel ! Subscribe for more: bit.ly/3SIobn0
    The project to restore and improve the quality of National Road No. 4 (Phnom Penh-Sihanoukville) has reached 54.80% by the end of June 2024 and is scheduled to be completed on December 31, 2026.
    The National Road No. 4 Rehabilitation and Improvement Project is under the implementation of a project and program funded by the World Bank (WB) with a budget of 110 million US dollars, planned to be implemented for 8 years (2018-2026) and implemented by Ministry of Public Works and Transport. This funding will be used for the repair and maintenance of National Road No. 4, 196.10 km long, by widening the road, digging canals and repairing old bridges, building new bridges, and using it to update the road data management system and provide technical training to government institutions.
    According to HE Pheng Sovicheano, Secretary of State and Director of the National Road No. 4 Rehabilitation and Upgrading Project, the project plans to rehabilitate and maintain National Road No. 4 with a total length of 196.10 kilometers, including:
    1. Part 1: Km 19 + 700 to Km 60 + 000 in Kandal and Kampong Speu provinces. Four lanes are 28.80 km long and two lanes are 11.50 km long with a total length of 40.30 km.
    2-Section 2: km 60 + 000 to km 101 + 000 in Kampong Speu province. The four lanes are 2.68 km long and the two lanes are 38.32 km long and the total length is 41.00 km.
    3-Section 3: km 101 + 000 to km 143 + 000 in Kampong Speu and Koh Kong provinces. The four lanes are 0.30 km long and the two lanes are 41.70 km long and the total length is 42.00 km.
    4-Section 4: km 143 + 000 to km 186 + 000 in Koh Kong and Preah Sihanouk provinces. Four lanes are 0.93 km long and two lanes are 42.07 km long, with a total length of 43.00 km. The fourth section was postponed because the contractor did not build on time, so the ministry canceled the contract and confiscated a deposit of about 800,000 (eight hundred thousand) US dollars. The ministry will re-procure the fourth batch in August.
    5-Section 5: Km 186 + 000 to Km 215 + 800 in Sihanoukville. Four lanes are 7.30 km long and two lanes are 22.50 km long, with a total length of 29.80 km.
    6-Package 6: km 48 + 695 to km 202 + 688, repairing 24 old bridges, 8 box drains, 9 round drains and replacing 5 old bridge components in Kampong Speu, Koh Kong, Sihanoukville.
    7-Package 7: Km 38 + 076 to Km 204 + 973 Construction of 8 new bridges in Kampong Speu, Koh Kong and Sihanoukville.
    -គម្រោងសាងសង់ផ្លូវ ស្ពាន កំពង់ផែ ព្រលានយន្តហោះសំខាន់ៗ ក្នុងប្រទេសកម្ពុជា
    Link: shorturl.at/crFRY
    -គម្រោងផ្លូវល្បឿនលឿនភ្នំពេញ-បាវិត Phnom Penh-Bavet Expressay Project
    Link: bit.ly/3JgxGWs
    -ព្រែកជីកហ្វូណនតេជោ FUNAN TECHO CANAL
    Link: bit.ly/449F8uI
    -គម្រោងផ្លូវរថភ្លើងប្រទេសកម្ពុជា Cambodia Railway Project
    Link: bit.ly/3Pii2O9
    -គម្រោងផ្លូវល្បឿនលឿនភ្នំពេញ-សៀមរាប Phnom Penh-Siem Reap Expressway Project
    Link: bit.ly/3qM2g4a
    - បណ្តាញផ្លូវជាតិសំខាន់ៗ របស់កម្ពុជា Cambodia Road
    Link: bit.ly/3Ni4zn5
    -គម្រោងព្រលានយន្តហោះប្រទេសកម្ពុជា Cambodia Airport Project
    Link: bit.ly/43LilFB
    -គម្រោងផ្លូវក្រវ៉ាត់ក្រុងទី ៣ Phnom Penh Ring Road 3rd
    Link: bit.ly/3JiB9UE
    -គម្រោងផ្លូវក្រវ៉ាត់ក្រុងទី ៤ Phnom Penh Ring Road 4th
    Link: bit.ly/3JiB9UE
    -ព័ត៌មានការអភិវឌ្ឍន៍អន្តរជាតិ International Development News
    Link: bit.ly/3qNrRtk
    -គម្រោងកំពង់ផែធំៗ របស់ប្រទេសកម្ពុជា Cambodia Port Project
    Link: bit.ly/4421deH
    -ក្របខណ្ឌ និងការប្រលងក្រសួងសាធារណការ និងដឹកជញ្ជូន Ministry of public works and Transport
    Link: bit.ly/3qPI2Xd
    -ច្បាប់ស្តីពីផ្លូវថ្នល់ Law on Road
    Link: bit.ly/3CvkBVL
    មើលវីដេអូជាច្រើនទៀត bit.ly/3pCk1z3

ความคิดเห็น • 4

  • @samrithy4069
    @samrithy4069 4 วันที่ผ่านมา +1

    ត្រង់ចំណុចកំពង់សីលាគ្រវីក្បាលដូចគោស្រងទិច បើកមិនប្រយ័ត្នទេ រអិលចេញពីផ្លូវហើយ ឈូសឆាយធ្វើផងអស់លោកក្រសួង !

  • @vannakkh964
    @vannakkh964 3 วันที่ผ่านมา +1

    ធ្វើចង់៣ឆ្នាំហើយ😅

  • @arnsambo2686
    @arnsambo2686 4 วันที่ผ่านมา +1

    ធ្វើមួយអួត១០

  • @thovithyea8690
    @thovithyea8690 4 วันที่ผ่านมา

    ល្មមធ្វេីហេីយ អា ធ្វេី មុន សឹក បណ្តេីរ ល្មម