PMP Situational Questions 2022 QUIZ - If you ACE it , There's HOPE!

แชร์
ฝัง
  • เผยแพร่เมื่อ 29 ส.ค. 2022
  • These have all the tricks in the book that the sleazy question writers come up with! Gain KNOWLEDGE to COMBAT the PMP Exam!
    New 2021 Exam?
    Sign up: projectmanagementmasterclass.com
    FREE PMP PODCAST: pmradio.org (available on audible and all platforms)
    Hybrid Bootcamp: hpmexam.com
    Agile Practice Guide Bootcamp: agileprinciple.com
    PMP Exam Immersion Book:
    PDF: praizion.dpdcart.com/cart/add...
    HARDCOPY: www.lulu.com/shop/roy-schilli...
    Other courses:
    praizion.com
    Podcast:
    open.spotify.com/show/46uJBml...
    Online Agile Training for PMP Exam: vimeo.com/ondemand/agilepmp
    MAIN SITE: www.praizion.com
    Praizion Media specializes in project management education and professional development. Please visit: www.praizion.com for project management and PMP Exam training materials.

ความคิดเห็น • 27

  • @SuhFarina
    @SuhFarina ปีที่แล้ว +2

    Hi phill, question #10. EV,AC,BAC and PV have been provided.SPI and CPI are both above 1, which to me is proof that D is the appropriate answer.

  • @kannanm9322
    @kannanm9322 ปีที่แล้ว +1

    Very nice set of questions. Got 7/10. Thanks Phil.

    • @Praizion
      @Praizion  ปีที่แล้ว

      Great job Kannan!

  • @olalekanolusanya4433
    @olalekanolusanya4433 ปีที่แล้ว +1

    Your youtube contents really helped me in preparing and passing my PMP exam.

    • @Praizion
      @Praizion  ปีที่แล้ว

      CONGRATS PMP BOSS! Great to hear!

  • @famfun8838
    @famfun8838 ปีที่แล้ว +1

    Superb excercise sir 👍

    • @Praizion
      @Praizion  ปีที่แล้ว

      Thank you so much 👍

  • @yannlathro256
    @yannlathro256 9 หลายเดือนก่อน +1

    Great questions and explanations. On the last question, is the budgeted cost of work performed the same as EV? thanks

    • @Praizion
      @Praizion  8 หลายเดือนก่อน

      Yes, exactly! BCWP = EV

  • @sumitmitra7336
    @sumitmitra7336 ปีที่แล้ว +1

    For Q#8, @21:59 ,Option A: Refer to the stakeholder management plan seems more suitable. The Plan will help identifying the strategies, developing approaches & actions required to promote productive involvement of stakeholders in project. Primarily strategies for how we are going to change the current level of stakeholder to desired .( Project approving/ supporting/ leading etc)
    Option C: Collaboration, Openness & transparency appears to be incorrect on 2 counts
    1. They are more of Agile principles, while the general thumb rule is that the scenario in any question is considered to be Predictive unless stated otherwise either explicitly or implicitly.
    2. How does being collaborative , open & transparent really help in ensuring that the local party gets inclined towards approving the project. We also need to contemplate if their approval is really mandated ? Are they significant enough to hamper or stall the project in any way. All that would be generally found in the stakeholder engagement plan .
    Your thoughts Please

    • @Praizion
      @Praizion  ปีที่แล้ว

      Thanks for the question.
      This is more problem solving than stakeholder engagement. There is an issue now, so what do you do?
      Referring to the stakeholder engagement plan will not help move this situation forward. The problem has happened (the engagement plan has not prevented it). It stopped at checking the plan. And then what? Nothing else is alluded to.
      So what do you do next? You have to apply interpersonal skills and communications. This is what makes the exam challenging. 90% of the answers will be to do something that promotes a humanistic point of view vs. check a plan. In 2022, this is what PMI expects. Even if the answer is agile-sounding, the question can be viewed as hybrid and you still need to lean on selecting things that move situations along better, than just referring to a plan.
      90% of PMP questions have ZERO ITTO or PROCESS names in both the questions and answers.

    • @sumitmitra7336
      @sumitmitra7336 ปีที่แล้ว

      @@Praizion Got it... Thanks Phill❤

  • @joywithiniyan2720
    @joywithiniyan2720 ปีที่แล้ว +1

    Hi Phill, could you please explain more on cost efficiency in question no.6 and also in question no.1,budgeted cost of work performed is EV right, then if i calculate SPI= EV/PV and CPI= EV/AC both SPI & CPI are above 1 , so in this case Option A holds good ?

    • @Praizion
      @Praizion  ปีที่แล้ว

      Not sure I follow. Q1 (slide 2?) Is not about EVM.
      Question 6, reads "to increase cost efficiency" you are already way efficient. 250% efficient. Spending $1 but getting $2.50 out. So option A is not the best to choose.

  • @sumitmitra7336
    @sumitmitra7336 ปีที่แล้ว +2

    Q#9, Stakeholder register has" communication requirements "& "communication frequency "of stakeholders. But it doesn't have "communication flow channels" ? Pls correct if wrong

    • @Praizion
      @Praizion  ปีที่แล้ว

      That is not so Sumit. The COM REQ and COM FREQ is determined in PLANNING. Stakeholder Register is created in INITIATING.
      ---------------
      PMBOK SAYS: The main output of the Identify Stakeholders process is the stakeholder register. Mainly it has:
      ** Identification information. Name, organizational position,
      **Assessment information. Major requirements, expectations, potential for influencing project outcomes, AND
      phase of the project life cycle where the stakeholder has the most influence or impact.
      **Stakeholder classification. Internal/external, impact/influence/power/interest, or any other classification model chosen by the PM

  • @xxchuangtzu6186
    @xxchuangtzu6186 ปีที่แล้ว

    @26:00,. Coaching does not presume that the team member has shared the confidential information. After all, the question says the senior manager _asked_ for it, not that the senior manager "obtained". We can assume the manager is niot privy to the informartion; otherwise he/she would not have asked a team member for it. So B does not make sense.

    • @Praizion
      @Praizion  ปีที่แล้ว

      Coaching the team member instead of attending to the requestor's needs, leaves the requestor high and dry and the problem is not solved. Being privy to information does not mean the individual has the technical capacity to retrieve it. What ever the case, the exam will test problem-solving. Coaching here does not solve the immediate problem here.

  • @Raw12375
    @Raw12375 ปีที่แล้ว +2

    Really tricky and tough

    • @Praizion
      @Praizion  ปีที่แล้ว

      Thanks Kunal. I hope it helps beef up PMP muscle! Cheers!

  • @user-rl2fe1bh2h
    @user-rl2fe1bh2h ปีที่แล้ว +1

    Is definition of done defined in team charter or project charter?

    • @Praizion
      @Praizion  ปีที่แล้ว

      Team Charter! Thanks for commenting and best wishes!

    • @Praizion
      @Praizion  ปีที่แล้ว

      Remember that the this is something the team decides on. Not the higher-ups under most normal agile circumstances. If the Team Charter is not an option, it could come down to the "Agile Project Charter" as a last ditch effort.

  • @abilashthota458
    @abilashthota458 ปีที่แล้ว +1

    Good to know you from the same family Honeywell...

    • @Praizion
      @Praizion  ปีที่แล้ว

      Lovely company! I greatly enjoyed my work there!

  • @PMPEngineerPE
    @PMPEngineerPE ปีที่แล้ว

    Why wouldn't you communicate? I thought communication is a key stone of pm?

    • @Praizion
      @Praizion  ปีที่แล้ว

      Can you expand on which question this is in reference to? Sometimes communicating does not solve problems. It is a red herring on many questions.