Out of Sequence in Primavera P6

แชร์
ฝัง
  • เผยแพร่เมื่อ 26 ต.ค. 2024

ความคิดเห็น • 10

  • @PlanAcademy
    @PlanAcademy  2 ปีที่แล้ว +1

    Our NEW Progressing Course just launched. Check out the best Advanced P6 Training Available online:
    www.planacademy.com/

  • @peterwang1011
    @peterwang1011 2 ปีที่แล้ว +1

    Great job! Adjusting out-of-sequence activities is extremely useful for preparing an as-built programme to reflect actual progress. However it is limited in forensic delay analysis, i.e. why a planned successor runs ahead of its predecessor might come from a client instruction. The instruction constitites a owner delay activity which need be impacted into the baseline programme.

  • @reginaldibenne6875
    @reginaldibenne6875 8 หลายเดือนก่อน +1

    You are a lifesaver. Thank you so much, sir!
    Now, what of in a situation we have multiple out of sequence activities like 30 activities?

    • @PlanAcademy
      @PlanAcademy  8 หลายเดือนก่อน

      Gotta be detailed-oriented to schedule - dig into the details.

  • @hussainsiddiquee9970
    @hussainsiddiquee9970 2 ปีที่แล้ว

    Great work ❤️❤️

  • @mohammedabaza2782
    @mohammedabaza2782 11 หลายเดือนก่อน +1

    GREAT 👍

    • @PlanAcademy
      @PlanAcademy  11 หลายเดือนก่อน

      Thanks Mohammed!

  • @benzonjhermogeno
    @benzonjhermogeno 6 หลายเดือนก่อน

    Great

  • @safirmohamed2203
    @safirmohamed2203 2 ปีที่แล้ว

    I have one doubt in out of sequence.
    *The activities is completed 100% but the predecessor not yet started.* ( Relationship already invalid) or *Successor activity is completed while the predecessor activity didn't start yet.*
    I want to filter that particular activity using filter options,
    Can u please advice

    • @lisajonescastronova5599
      @lisajonescastronova5599 2 ปีที่แล้ว

      Safir, if you are trying to determine which activities have been performed out-of-sequence from planned logic, recalculate the schedule and ensure "Log to File" is checked in the Schedule calculation dialog box. After you recalculate, recalculate again, but this time in the Schedule calculation box select "View Log". Scroll through that scheduling report that should pop up using Notepad to find the list of activities that have been performed out of sequence. There will be a section in the report specifically displaying that information. You can then create a filter in P6 to retrieve those activity IDs where you can review those activities and their unsatisfied logic. The first step is to identify which activities they are, and the Scheduling Log/Report will tell you that. Another useful tool to find this information would be Acumen Fuse.