Rate Analysis of Shuttering and Form work OR Shuttering Cost Calculation Method

แชร์
ฝัง
  • เผยแพร่เมื่อ 24 เม.ย. 2019
  • Dear Friends,
    In This video i have explained about the how to calculate the cost o shuttering works, and how to calculate Rate Analysis of Formworks / shuttering for conventional from works.
    Rate Analysis of Shuttering
    Rate Analysis of Form works
    Cost calculation of Shuttering works
    Cost for Conventional Formwork.
    Rate Analysis for Ply & Batten Shuttering

ความคิดเห็น • 93

  • @FactualCivilEngineering
    @FactualCivilEngineering  5 ปีที่แล้ว +16

    Please comment if you have query, Must Hit the Like Button if you learn something new..thanks

    • @NaveenKumar-px1if
      @NaveenKumar-px1if 5 ปีที่แล้ว

      I have already send a mail id for meet up you ask me

    • @honourableadvocate3499
      @honourableadvocate3499 3 ปีที่แล้ว +1

      Sir! U should have come much earlier. May Allah bless u!

    • @syedjamal27
      @syedjamal27 3 ปีที่แล้ว

      Baqi members ka bhi detailed video daliye sir, bohot zabardast...

    • @vaibhavchavan6040
      @vaibhavchavan6040 3 ปีที่แล้ว

      Sir please provide your contact number on vaibhavchavan605@gmail.com

    • @mcx330
      @mcx330 2 ปีที่แล้ว

      Ye dono books ka name kiya hei...kaha milega

  • @Yasir3314
    @Yasir3314 5 ปีที่แล้ว +4

    This kind of information only available your TH-cam channel, very nice video, keep it up sir

  • @mohammadshoeb4539
    @mohammadshoeb4539 5 ปีที่แล้ว +5

    Amazing sir, now I understand why CPWD DAR has MS shuttering rate analysis instead of plywood.

  • @lovefirstvoice8768
    @lovefirstvoice8768 5 ปีที่แล้ว +4

    Masterpiece, Bahut achhi information di h aap ne sir

  • @pawanjunghare6544
    @pawanjunghare6544 5 ปีที่แล้ว +5

    After lot of search I found this video... Thank you so much sir .👍. Please make for Mivan formwork

    • @FactualCivilEngineering
      @FactualCivilEngineering  5 ปีที่แล้ว +1

      th-cam.com/video/7n06l38ALY8/w-d-xo.html, uploaded for Mivan Shuttering Cost

    • @Pratik_VOLG_GLOV
      @Pratik_VOLG_GLOV 3 ปีที่แล้ว

      Can I get excel of RA pl
      My email is ptmhatre@yahoo.com

  • @Abhishekyadav-ff5me
    @Abhishekyadav-ff5me 5 ปีที่แล้ว +3

    Thank you sir it is very useful for us pls upload full tender rate analysis if possible such as excavation and material consumption.

  • @sbk19cricketcollections92
    @sbk19cricketcollections92 5 ปีที่แล้ว +2

    Please upload difference between conventional and mivan shuttering and its cost. Thanks once again for your very informative video

  • @mohammedmahboob9110
    @mohammedmahboob9110 5 ปีที่แล้ว +2

    Thank you very much..... Keep uploading new videos "Daily sir please" 🙂🙂🙂🙂

  • @kamalsingh2272
    @kamalsingh2272 4 ปีที่แล้ว

    lot of information in this video
    Thanks for this valueable information

  • @ashishbarnwal7856
    @ashishbarnwal7856 2 ปีที่แล้ว

    Knowledgeable...

  • @shazebalikhan9407
    @shazebalikhan9407 4 ปีที่แล้ว

    Very nicely and thoroughly explained.

  • @JitendraKumar-ic4ih
    @JitendraKumar-ic4ih 5 ปีที่แล้ว +1

    Thanks sir for your kind information...

  • @maheshj660
    @maheshj660 5 ปีที่แล้ว

    sir very nice,aap bahut neck kaam kar rahe ho hame career mein aage badhane k liye aise sab chizo ki bahut jarurat hoti hai,sir aap jab koi video upload karte ho toh uske saath uska file bhi attach kardo .
    thanku so much sir

  • @AKhan-xi7xj
    @AKhan-xi7xj 5 ปีที่แล้ว

    Very very informative plz sir keep uploading rate analysis videos..... 👍👍👍

  • @easyciviltech.8030
    @easyciviltech.8030 2 ปีที่แล้ว

    Nice video good information.

  • @jigneshlad9449
    @jigneshlad9449 2 ปีที่แล้ว

    Dear Sir,
    it is nice explanation
    need rates analysis for single items like footing column beam slab.

  • @lalitkumar-lo9cs
    @lalitkumar-lo9cs 5 ปีที่แล้ว +2

    Full of knowledge

  • @vikramsuryawanshi2836
    @vikramsuryawanshi2836 5 ปีที่แล้ว

    Amazing sir.... Thanks for best information 👍👍👍👍👍

  • @miteshparmar2015
    @miteshparmar2015 2 ปีที่แล้ว

    Narayan Bless 🙏 You

  • @sexymtoy
    @sexymtoy 4 ปีที่แล้ว +2

    Thanks sir it is very informative...sir can you upload or send rate analysis boq excel file it will be very helpful to study on that.

  • @dimpalrana7183
    @dimpalrana7183 3 ปีที่แล้ว

    Great sir ji...

  • @mfaisaldilshad6784
    @mfaisaldilshad6784 5 ปีที่แล้ว +5

    Sir in high rise tower using shuttering (SlipForm)

  • @dikshantarora4988
    @dikshantarora4988 3 ปีที่แล้ว

    Very informative

  • @sachinmalwadkar1484
    @sachinmalwadkar1484 3 ปีที่แล้ว

    Nice explanation

  • @easyciviltech.8030
    @easyciviltech.8030 2 ปีที่แล้ว

    Thanks sir g

  • @ravikumarpillai1473
    @ravikumarpillai1473 2 ปีที่แล้ว

    Sir very good and useful information about Formwork rate analysis
    Also
    I need for False ceiling works and Labour Productivity and output coefficients.
    Waiting for your reply

  • @karansaroj7766
    @karansaroj7766 2 ปีที่แล้ว

    Sir please retaining wall k liye form work ki analysis bnaye

  • @menganaveen8665
    @menganaveen8665 3 ปีที่แล้ว

    Sir, Pl Upload Videos Comparing Rate Analysis with DAR analysis to actual industrial estimates ( As many of us follow coefficients of DAR )

  • @rahulchaudhary-qn3nj
    @rahulchaudhary-qn3nj 4 ปีที่แล้ว +1

    But bro site pr to 8 repetition consider krte 4 one side or 4 other side. Please clarify it.

  • @shadabmojib4910
    @shadabmojib4910 5 ปีที่แล้ว

    Dear sir please make a separate play list, for BBS, RATE ANALYSIS, FORM WORK ETC

  • @navidpatel7645
    @navidpatel7645 4 ปีที่แล้ว

    Dear sir, please make rate analysis calculations for plaster and brickwork(half and full brick)

  • @harshshah9828
    @harshshah9828 4 ปีที่แล้ว

    sir 1 is type ka video slab , beam and column shuttring pe bi banaye jis me slab snagging me ms ka material use hota ho

  • @Mixxeddtube
    @Mixxeddtube 3 ปีที่แล้ว

    1) That 315 per sqm rate contains labour rate also (labour for making sides) then i dont understand how u hv taken it for calculation as material rate for below 10 sqm calculation?? I think it must be exclusive of labour rate (labour for making sides)
    2) Why again nails have calculated for 10 sqm because we have already calculated in material cost....also plz tell where binding wire will be required? Thanks)

  • @allaboutcivil9563
    @allaboutcivil9563 3 ปีที่แล้ว

    Sir plz start a course for billing and qs from basic to advance in a manner

  • @umeshmor
    @umeshmor 5 ปีที่แล้ว

    Hello, sir
    please make a video on only labour rate work.
    This video is all about work with the material.
    I am confused with how can I determine the only labour rate from CPWD DSR. please help

  • @smileplease3600
    @smileplease3600 3 ปีที่แล้ว

    Sir frist wala point nhi smjh aya 1165 total are usko reptation se dived kia to 233 one use ply ka area hua na to isko to smjhao sir

  • @lalitkumar-lo9cs
    @lalitkumar-lo9cs 5 ปีที่แล้ว

    I liked it

  • @AmitKumar-yd8il
    @AmitKumar-yd8il 4 ปีที่แล้ว

    Thank u sir,

  • @nirblakumari1604
    @nirblakumari1604 ปีที่แล้ว

    sir please can u tell me staircase flooring measurement

  • @er.dineshyadavsatyatech9403
    @er.dineshyadavsatyatech9403 5 ปีที่แล้ว

    Sir pls upload all items rate analysis

  • @sabiransari2842
    @sabiransari2842 ปีที่แล้ว

    Why add water charges in rate analysis??

  • @adityaduttapmp6394
    @adityaduttapmp6394 3 ปีที่แล้ว +1

    Iska excel sheet kaise milega ?

  • @ahmadaffan6509
    @ahmadaffan6509 3 ปีที่แล้ว +1

    Can you please send me NABHI's Analysis of Rates pdf copy if you have one?

  • @vijaychaudhari920
    @vijaychaudhari920 3 ปีที่แล้ว

    Bhaya Mein labour rate batao Jara Mumbai ka centring plywood wala

  • @vipulmukherji2239
    @vipulmukherji2239 2 ปีที่แล้ว

    What should be the labour cost of shuttering

  • @KumarRaviray
    @KumarRaviray 3 หลายเดือนก่อน

    Amit Sir aap ki latest video nhi aa rhi hai

  • @minoor3533
    @minoor3533 3 ปีที่แล้ว

    Vdf trimix flooring ka rate analysis

  • @nareshrunkana9589
    @nareshrunkana9589 3 ปีที่แล้ว +1

    Hi sir, Subscribed the channel but i can able to download the formats and data. Please help

  • @kunaljha6837
    @kunaljha6837 2 ปีที่แล้ว

    Sir please can you share the excel sheet of this rate analysis

  • @aswadhisobha2980
    @aswadhisobha2980 2 ปีที่แล้ว

    How did u get the data abt no: of repetition of each type of formwork??

  • @arunbhadana6947
    @arunbhadana6947 4 ปีที่แล้ว

    Rcc drain ka labour rate kya hona chahiye

  • @SathishKumar-vi1ss
    @SathishKumar-vi1ss 5 ปีที่แล้ว +1

    Sir, can I buy this 2volumes is it worth to learn rate analysis?
    Amount is Rs.8000/-

    • @FactualCivilEngineering
      @FactualCivilEngineering  5 ปีที่แล้ว +1

      I recommend you first you understand basic by CPWD DAR Vol 1 & 2, which is free available on CPWD website, later on you can buy it @ 2500/- from amazon

    • @aniljha15
      @aniljha15 5 ปีที่แล้ว +1

      Hi Sir/Ma'am
      This is Anil Jha From Garg Ispat Udyog LTD,
      We're are Manufacturing Aluminium Fromwork and Scaffolding Systems and Supplying all India.
      For any kind of Requirements.Please feel free to call us. @ ± 91- 9873584257,9990992321
      Thanks & Regards
      Anil Jha
      (Sales and Marketing Manager)
      Call- + 91- 9990992321
      WhatsApp . 9873584257
      Email:- aniljha@gargispat.com
      aniljha36@ymail.com
      Website:- www.gargispat.com

    • @sanjaykamdar7054
      @sanjaykamdar7054 4 ปีที่แล้ว

      Which two volumes??

    • @sanjaykamdar7054
      @sanjaykamdar7054 4 ปีที่แล้ว

      @@FactualCivilEngineering sir plz mention where I get two volumes of rate analysis free.which site??

  • @mohammadnisarahmed8336
    @mohammadnisarahmed8336 4 ปีที่แล้ว

    Sir billing better hai qs..??

  • @mehulbhanushali1743
    @mehulbhanushali1743 3 ปีที่แล้ว

    How to download this excel sheet?

  • @karansaroj7766
    @karansaroj7766 2 ปีที่แล้ว

    Sir reaptation kaha mention hai

  • @jitendrasaini7408
    @jitendrasaini7408 4 ปีที่แล้ว

    Sir aap ki screen par text clear dikhai nhi de te

  • @Kanu3212
    @Kanu3212 3 หลายเดือนก่อน

    Repetition 5 kya hai koi btayega?

  • @mcx330
    @mcx330 2 ปีที่แล้ว

    Ye dono book kaha mila aapko..

  • @eraftabshaikh9255
    @eraftabshaikh9255 2 ปีที่แล้ว

    Sir please provide pdf/ppt on video

  • @multiworks5185
    @multiworks5185 4 ปีที่แล้ว

    sir ye dono book ki price kitni h?

  • @jitu2930
    @jitu2930 2 ปีที่แล้ว

    Please share the Excel sheets 🙏

  • @NooruddinMdAadil
    @NooruddinMdAadil ปีที่แล้ว

    can you share excel sheet

  • @swapnilchikhale2071
    @swapnilchikhale2071 ปีที่แล้ว

    Pls share excel sheet

  • @akshaysable6026
    @akshaysable6026 4 หลายเดือนก่อน

    Sir please send this excel

  • @Mixxeddtube
    @Mixxeddtube 3 ปีที่แล้ว

    1) That 315 per sqm rate contains labour rate also (labour for making sides) then i dont understand how u hv taken it for calculation as material rate for below 10 sqm calculation?? I think it must be exclusive of labour rate (labour for making sides)
    2) Why again nails have calculated for 10 sqm because we have already calculated in material cost....also plz tell where binding wire will be required? Thanks)

  • @saikiranbyram
    @saikiranbyram 4 ปีที่แล้ว

    please upload Excel of rate Analysis