Great content my friend. However, I allow myself to clarify something. The UDF method is not going to work at the WBS roll up level simply because it’s running totals of the activities below instead of getting the Max value. The finish date variance, is great call and widely more used
It Depends on contract limitation. This video is relevant to activities delay report, not project delay . What makes difference between UDF and Variance finish date is calendar . So it depends on contract. Also already explained that at WBS level UDF will total.So at WBS level its wrong. Their are some cases ,we required only activities delay instead of project delay. So we can use it.
You are doing excellently well
Thanks appreciated your review and comment
Thanks Brother! great Job.
Welcome
Sir, While applying global change I am doing
Delay = Finish but not getting - in operator, in my system it is only showin & sign
@@pradeepsingh2853 not get your question. Can you explain
thanks
Welcome
Respected sir. Can you please upload a video of Making PMS report .
@@taimurhassan3800 ok sure
Great content my friend. However, I allow myself to clarify something. The UDF method is not going to work at the WBS roll up level simply because it’s running totals of the activities below instead of getting the Max value.
The finish date variance, is great call and widely more used
It Depends on contract limitation.
This video is relevant to activities delay report, not project delay .
What makes difference between UDF and Variance finish date is calendar .
So it depends on contract.
Also already explained that at WBS level UDF will total.So at WBS level its wrong.
Their are some cases ,we required only activities delay instead of project delay. So we can use it.
Good job!! Can you also make a video on how to incorporate an electrical schedule into the main schedule? Thanks
Video is already their.
Watch from below link
th-cam.com/video/Z5U7Gc_-pfI/w-d-xo.html