Assalamualaikum sir I am a civil engineer looking for job in ksa for batching plant inspector , i am certified Aci concrete field teating technician grade 1
which code you are following , as you said each test should be followed by 30 minutes and you might know the cement initial setting time is 45 minutes after that concrete starts setting so there will be a huge difference after 30 minutes of slump value.
very informative videos engineer saib Allah de kamyaab ao khushala satta
Thank you sir, very informative.
Please upload a vedio about construction of flexible pavement in KSA...and all the tests which are done ....
What standard do you used you are twisting the slump cone?
Hi sir my name is Ahmad Anwar And me work in villa ready mix saudi Arabia
what is the meaning of trial mix
you shown only temp & slump
If slump test fail what will be do next?
Than Go to for Water Cement ratio or ?
No.
Slump cone test is not properly done. Stroking shall be done in sitting posture. Here technician is standing leading to improper compaction
Does this thing mentioned in any standard?
Twisting the slump cone 😂😂
😂
sir,iam a concrete field technician
i need this job? Have a vecancy
Assalamualaikum sir
I am a civil engineer looking for job in ksa for batching plant inspector , i am certified Aci concrete field teating technician grade 1
which code you are following , as you said each test should be followed by 30 minutes and you might know the cement initial setting time is 45 minutes after that concrete starts setting so there will be a huge difference after 30 minutes of slump value.
Dear this is trial mix at batching plant before the approval of mix design
@@CivilEngineerAtSite Ok sir thanks
Where are trail mix details?????
Which details
Not fully information . you miss all standard ,
Dear this is a trial mix so what you need more
Assalam u alakium sir ap k number