LATEST UPDATE | UNEXPECTED PROGRESS OF RING 3 THROUGH DONG NAI AND THU DUC CITY !!

แชร์
ฝัง
  • เผยแพร่เมื่อ 2 ต.ค. 2024
  • #Đườngvànhđai3 #Tiếnđộmớinhấtvànhđai3 #CầuNhơnTrạch #Quận9 #NhơnTrạch #thànhphốThủĐức #seenee
    3rd Ring Road HCMC HCMC officially started construction on June 18, 2023, and expected to basically complete the engineering by the end of 2025, and open to traffic in 2026. The project has a total length of about 76.34 km, passing through Ho Chi Minh City. HCMC and 3 neighboring provinces (Dong Nai, Binh Duong, Long An); are divided into 8 independently operated component projects. The total investment of the project is up to VND 75,378 billion.
    Specifically, the 3rd Ring Road at the beginning of District 9, Ho Chi Minh City is a component 1B project with a total length of 8.7km, which will start from: Nhon Trach bridge towards Ho Chi Minh City Expressway. HCM - Long Thanh - Dau Giay and the end point at intersection 2 (Hanoi Highway) at junction 3 Tan Van. Total capital is nearly 4,000 billion VND. Particularly, the site clearance for this project costs more than VND 1,053 billion.
    The Tan Van - Nhon Trach 3rd Ring Road under the 1A component project has a length of 8.2km, of which the section through Dong Nai is 6.3km long and 1.9km passes through Ho Chi Minh City. HCM. The scale is a level 3 plain road, design speed of 80km/h; The road is 20.5 - 26m wide, including 4 motor lanes and 2 mixed lanes. The construction period is 3 years.
    -------------
    VIDEO CONTENT:
    00:01 - Introduction
    00:32 - Ring 3 overview
    00:41 - Progress of Ring 3 interchanges
    ---------------
    SEE MORE VIDEO REVIEW PROJECTS:
    👉 Eaton Park - Gamuda Land: • EATON PARK | ƯU VÀ NHƯ...
    👉 Phan Thiet Airport: • NGẮM NHÌN SÂN BAY PHAN...
    👉 Cam Lam Vinh Hao Expressway: • MỚI NHẤT | CẬN CẢNH TI...
    👉 Bien Hoa Vung Tau Expressway: • MỚI NHẤT | CẬN CẢNH CA...
    👉 Ben Luc Long Thanh Expressway: • MỚI NHẤT | SOI TIẾN ĐỘ...
    👉 4 PROJECTS WORTH BUYING: • 4 DỰ ÁN ĐÁNG CÂN NHẮC ...
    👍 Phu Quoc Sunset Town: • MỚI NHẤT | PHÚ QUỐC - ...
    👉 Collection of the best real estate project review videos: th-cam.com/users/pl....
    -------------
    Contact: 0344 191619 (zalo)
    Fanpage: / seenee.vn
    Join Zalo group: zalo.me/g/gpkb...
    Website: seenee.vn/
    Protected by DMCA: www.dmca.com/r...
    #SEENEE

ความคิดเห็น • 10

  • @thongocdethuong2010
    @thongocdethuong2010 7 หลายเดือนก่อน +4

    Nên giải tán Đồng Nai cắt đôi ra rồi sáp nhập vào Bình Dương và TPHCM

    • @martiniphan
      @martiniphan 7 หลายเดือนก่อน

      Sao thế bác

    • @SeeNee
      @SeeNee  7 หลายเดือนก่อน

      Bác có ý tưởng lớn quá

    • @Cuoc_Song_Quanh_Ta
      @Cuoc_Song_Quanh_Ta 7 หลายเดือนก่อน

      Quá dữ luông

    • @marybrown375
      @marybrown375 6 หลายเดือนก่อน

      Ý tưởng hết hồn luôn

    • @Emerald214
      @Emerald214 5 วันที่ผ่านมา

      Yeah, Đồng Nai làm việc lộn xộn, trễ nãi quá.

  • @phimpkl18
    @phimpkl18 7 หลายเดือนก่อน +1

    Quay đẹp chi tiết quá bạn.Cầu Nhơn Trạch 2,3 tháng nay không thấy tiến triển gì luôn.Mấy ông Đồng Nai tung hoành bao nhiêu năm

    • @SeeNee
      @SeeNee  7 หลายเดือนก่อน +1

      Mình thấy có làm thêm các dầm chuẩn bị gác qua cầu

    • @Cuoc_Song_Quanh_Ta
      @Cuoc_Song_Quanh_Ta 7 หลายเดือนก่อน

      Dầm quan trọng lắm b. Vừa làm vừa kiểm tra đo lường thường xuyên. Chứ đâu có cơ hội thứ 2 đâu