They usually set up their tools and equipment on a Friday evening, rig the machine Saturday, Sunday do isocenter and move into the vault on the cabling/extended rigging side, Monday or early Tuesday morning they have covers on ready to turnover.they will get done Monday evening most times depending on the rig path or situation of the site .
DO. YOU INSTALL REFURBISHED VARIAN TRUE BEAM
How long does it take to install this linac?
They usually set up their tools and equipment on a Friday evening, rig the machine Saturday, Sunday do isocenter and move into the vault on the cabling/extended rigging side, Monday or early Tuesday morning they have covers on ready to turnover.they will get done Monday evening most times depending on the rig path or situation of the site .