Hi Anca, thanks for the nice feedback :) Unfortunately, you cannot add a date on top of the chart via a thinkcell function (if you still want to do it, you would need to use a simple PowerPoint text box). You can only add a date below the Gantt Chart with a respective line as of your specific date. See minute 14:25 where I insert such a milestone/time stamp that you can also pull to the right or left to the current date and label it respectively. Hope this helps!
Thanks for the video! I was wondering if there is any possibility to add also more columns on the left side or to move the "Responsible" / "Status" column to the left side of the chart.. Thanks in advance
Hi there! To my knowledge, it is unfortunately not possible to move the "responsible" / "status" column to the left and I also doubt, that you can add more columsn to the right. If you want to include more information you would probably have to insert a simple table or text boxes besides the ThinkCell chart. Hope that helps
Hi, thanks for the helpful tutorial. Could you help me with the following? After making the gantt chart manually, adding all the items, I don't see the data in the imbedded excel sheet. I thought it's automatically filled in, or am I missing something? Thanks
Hi, I have Think Cell 28300 installed, I've tried to create a Gantt chart just like you did, but the scale "week" does not display the number of weeks, but rather shows the days per weeks (01, 08, 15, 22). Do you know if there's something I could configure to change that? Flawless explanation!
Is there a way to change the Text Box colour of Milestones? It seems only if the milestone is within the Date specified by the Bar the colour will adapt, otherwise the text box will be white.... This is a bit of a nightmare for readability.... especially when there are many columns in my gantt
very nice tutorial, also the speed and length is good. Long enough to learn something, but also fast enough to not get boring! Merci
Thanks for the feedback!
This video is underrated! Thanks for the amazing content and perfect explanation :)
Thank you so much, Laurent! Glad that I could help you out :)
Thanks for the video! Could you, please, clarify how can i change the color of the week separator?
Good video
One question, is it possible to modify the dimensions of mileston symbols (Eg. Triangle)?
Hey, Nice video.
can you please teach me how to display delay in schedule using this tool?.
Hi, Did you get an answer to your question? I am trying to do the same thing.
Thanks for the video. Very nicely explained :-). I have a question: How do you add the current date (today date) top a chart? Thank you in advance!
Hi Anca, thanks for the nice feedback :) Unfortunately, you cannot add a date on top of the chart via a thinkcell function (if you still want to do it, you would need to use a simple PowerPoint text box). You can only add a date below the Gantt Chart with a respective line as of your specific date. See minute 14:25 where I insert such a milestone/time stamp that you can also pull to the right or left to the current date and label it respectively. Hope this helps!
@@PresentationMastery thank you for your feedback. I was wondering on the chart if it is possible to ad a line similar with the milestone one. 😊
I request you make videos on each type of chart available in the think-cell
Thanks for the video! I was wondering if there is any possibility to add also more columns on the left side or to move the "Responsible" / "Status" column to the left side of the chart.. Thanks in advance
Hi there! To my knowledge, it is unfortunately not possible to move the "responsible" / "status" column to the left and I also doubt, that you can add more columsn to the right. If you want to include more information you would probably have to insert a simple table or text boxes besides the ThinkCell chart. Hope that helps
Is there a way to show movement when activities/milestones move?
Hi, thanks for the helpful tutorial. Could you help me with the following? After making the gantt chart manually, adding all the items, I don't see the data in the imbedded excel sheet. I thought it's automatically filled in, or am I missing something? Thanks
Hi, I have Think Cell 28300 installed, I've tried to create a Gantt chart just like you did, but the scale "week" does not display the number of weeks, but rather shows the days per weeks (01, 08, 15, 22). Do you know if there's something I could configure to change that? Flawless explanation!
Hi Oscar, clicking on the "week" scale (it should be a right click) you should be able to also choose the display format of the weeks. Hope that helps
lovely voice :)
Is there a way to change the Text Box colour of Milestones? It seems only if the milestone is within the Date specified by the Bar the colour will adapt, otherwise the text box will be white.... This is a bit of a nightmare for readability.... especially when there are many columns in my gantt
Hi, Using think cell, while creating a Gantt chart, is it possible to provide links to the bars? The links could be external slide or external link.
what should I do if I have may activities and not fit for just 1 page ?
How to add progress % in the Gantt chart?