PMP Q&A - How Well Do You Know PMBOK 7th Ed? (Qs 31 to 40)

แชร์
ฝัง
  • เผยแพร่เมื่อ 21 พ.ย. 2024

ความคิดเห็น • 39

  • @hailedc6725
    @hailedc6725 ปีที่แล้ว +7

    Thank you David! your videos helped me to pass the PMP last week with AT in all!

  • @hamedmiralam9973
    @hamedmiralam9973 7 หลายเดือนก่อน +4

    such a decent and clam person.. lots of love from Berlin! Thanks for the videos!

  • @MisterStubstep
    @MisterStubstep ปีที่แล้ว +6

    These were tricky but still learning a lot!

  • @ashwinkumarhits
    @ashwinkumarhits ปีที่แล้ว +4

    Very tough and tricky questions. Thank you once again!

  • @kamdev4989
    @kamdev4989 5 หลายเดือนก่อน +1

    At leas read 10 different questions with the help of you....!!

  • @asyrafafandi9851
    @asyrafafandi9851 3 หลายเดือนก่อน +1

    Hello thanks for the video, will the questions on the exam be of this difficulty or will it be harder

  • @SS-mn5ki
    @SS-mn5ki ปีที่แล้ว

    Fantastic Questions & tricky on Schedule, Accuracy & precision, ROM cost!

  • @yumaha
    @yumaha 15 วันที่ผ่านมา

    Good questions, could not agree with some answers ))

  • @frankscott2526
    @frankscott2526 ปีที่แล้ว +2

    At 24:38 - confused by how I'd determine how much work can be done in 3 months by multiplying cycle time by throughput. Throughput is the number of units you can complete in a given period of time and cycle time is how long to complete "work in progress" for 1 unit. I think I want to multiply the throughput value by the number of periods that makes up 3 months, right? TP = 90 units per month. In 3 months 270 units are completed.

    • @GetTheZedl
      @GetTheZedl 2 หลายเดือนก่อน

      I am absolutely with you on that one. There is no need for cycle time here.

    • @ruenhamakuni6596
      @ruenhamakuni6596 2 หลายเดือนก่อน

      @@GetTheZedl Totally agree too. The cycle time has already been accounted for in the Throughput

  • @sumitmitra7336
    @sumitmitra7336 ปีที่แล้ว +2

    Supremely tricky. Very helpful & informative

    • @MrNikhilgherwar
      @MrNikhilgherwar ปีที่แล้ว

      and I made only 2 correct :( need to improve!

  • @oilerz8054
    @oilerz8054 ปีที่แล้ว

    Can you please double check Q40. If you change to Finish-to-Finish, then that means successor finishes at the same time as predecessor. So by adding in lead time for successor, it could cause the successor to finish earlier than predecessor. Do you agree?

    • @davidmclachlanproject
      @davidmclachlanproject  ปีที่แล้ว

      Finish to Finish in precedence diagramming means:
      The second activity cannot finish before the first activity finishes.
      PMBOK 6, page 190.
      Hope this helps.

  • @mahdi_k27
    @mahdi_k27 5 หลายเดือนก่อน +1

    Thank you for this great content

  • @mahmoudatwa3564
    @mahmoudatwa3564 ปีที่แล้ว +1

    Great Video, Thanks alot!

  • @justin9605
    @justin9605 11 หลายเดือนก่อน +1

    Thank you.

  • @nareshsem333
    @nareshsem333 ปีที่แล้ว +1

    Great job again David❤

  • @kerimisam4517
    @kerimisam4517 3 หลายเดือนก่อน

    For the First question
    Would you please elaborate on how to have the vision statement without the scope or requirements?
    In my google search, i understood that the vision statement should have the end goal identified

  • @surajbhagat473
    @surajbhagat473 ปีที่แล้ว

    Hi David, Can we get a pdf copy of these questions

  • @AlessandroFavia
    @AlessandroFavia ปีที่แล้ว

    Wow, the last one is so tricky. I was looking at start to start, because of the parallel thing, and I completely forgot the lead... one question what is the BAU?

    • @davidmclachlanproject
      @davidmclachlanproject  ปีที่แล้ว +2

      Apologies for the jargon, it is "Business as Usual", or normal operations.

    • @AlessandroFavia
      @AlessandroFavia ปีที่แล้ว +1

      @@davidmclachlanproject Thanks so much! English is not my native language, so I need some more explanation sometimes! your videos are such an inspiration, thank you!

  • @doclebj1241
    @doclebj1241 ปีที่แล้ว

    Hi David. In Q35, is there a range that delineates high accuracy vs low accuracy. For eg in early estimating Q34 the range was -25 to 75% which seems low accuracy but when does that shift into high accuracy? do we use the -5 to 10% range guide as high accuracy? or will another estimating range also be considered high accuracy?

    • @davidmclachlanproject
      @davidmclachlanproject  ปีที่แล้ว +1

      Good question. There doesn't seem to be any official documentation on high versus low accuracy ranges, but I like your thoughts and they do make sense (the +75% versus +10% ones). I think any question will give some context that we can use.

  • @Sachlani
    @Sachlani ปีที่แล้ว

    Your answer (option B) for Q 39 is incorrect. The correct answer is "Multiply throughput per month by three".

  • @varundutta2381
    @varundutta2381 10 หลายเดือนก่อน

    Did not find the video for Questions 11 to 20.

  • @brahmiimen3804
    @brahmiimen3804 9 หลายเดือนก่อน

    Thank you soooooo much

  • @nabilkondwilkar7237
    @nabilkondwilkar7237 ปีที่แล้ว

    Where to find these practice question

  • @janbo894
    @janbo894 ปีที่แล้ว +3

    Question #33 is a bit confusing since, in your videos on rolling wave planning, you state that rolling wave is both for agile and predictive (th-cam.com/video/PwESbblSdQ0/w-d-xo.html). I thought B was the answer here since you postpone detailed planning (e.g. until more knowledge available), something that is not apparent in option C.

    • @davidmclachlanproject
      @davidmclachlanproject  ปีที่แล้ว +3

      Very good point. I agree - good thinking on your part. Both answers fit and would work on the real exam. The only addition I would make is that we were trying to replace the WBS activity itself. The answer chosen is like a WBS, but in an Agile way with agile terminology.

    • @scottchals
      @scottchals ปีที่แล้ว +2

      ​@@davidmclachlanproject Both would work on the real exam? What does that mean? Some questions will have multiple correct answers of equal value?

  • @AlokKumar-dj5dt
    @AlokKumar-dj5dt ปีที่แล้ว +2

    In Q32 sponsor wants to gain business value as quickly as possible then why not use incremental approach. In option C we are delivering high risk in the sprint.

    • @djpershan
      @djpershan 8 หลายเดือนก่อน

      Exactly my thought! I thought one of the reasons for incremental is to bring value ASAP, which is exactly what the project sponsor is requesting!

    • @AphrodisiaCK
      @AphrodisiaCK 6 หลายเดือนก่อน

      Because high value is not in routine work but high value components. I imagine it as a project who has run time part and one time part. Run time is maintainsnce delivering improvements and one time delivers high value

  • @javeriaejaz6953
    @javeriaejaz6953 ปีที่แล้ว +1

    got almost all wrong. Tricky questions