Sir, many thanks for enlightening with the nuances of mix proportioning. Two queries: 1. In some questions by IS 10262 method, the given data in the exam question is say, 0.9 or so, CF as workability, not in terms of slump. But, T-2 is in terms of slump. So, how to convert CF into known slump to be able to use T-2 of 10262, to proceed for max. Which table should be used from IS: 456 or IS 10262, for conversion? 2. If u can kindly add an example of mix proportioning in DOE method.
Sir im s.naveen raj im civil engineering student can you please clarify my doubt in volume of dry concrete=1.5*volume of wet concrete Hows that 1.5 comes sir will u please explain in comment sir And is that details available in anycode book sir
Sir, many thanks for enlightening with the nuances of mix proportioning. Two queries: 1. In some questions by IS 10262 method, the given data in the exam question is say, 0.9 or so, CF as workability, not in terms of slump. But, T-2 is in terms of slump. So, how to convert CF into known slump to be able to use T-2 of 10262, to proceed for max. Which table should be used from IS: 456 or IS 10262, for conversion?
2. If u can kindly add an example of mix proportioning in DOE method.
what is Water content for slump less than 25 mm???
Sir im s.naveen raj im civil engineering student can you please clarify my doubt in volume of dry concrete=1.5*volume of wet concrete
Hows that 1.5 comes sir will u please explain in comment sir
And is that details available in anycode book sir
U have to consider voids in C.A(30%) and F.A (20%) = total voids in dry state is 20+30=50%
Dry /wet = 1+ (50%/100)= 1.5