    I appreciate your good work. You are really helping us. I have a question please. The question is how do you establish the first one meter before transferring it round other pillars. Do you measure the first one with tape from the floor. Before transferring others with dumpy Level?

    • @SURVEYOR_TEEWHY2021
      @SURVEYOR_TEEWHY2021  ปีที่แล้ว

      exactly sir.
      I always add 5cm to it to cater for the finishing floor materials.

  • @cheteemeka5399
    @cheteemeka5399 2 ปีที่แล้ว +1

    Good job!

  • @bensonlazaro2351
    @bensonlazaro2351 2 ปีที่แล้ว +1

    Nice videos can we have few knowledge on how to determine camber from cl level and slope given

    • @SURVEYOR_TEEWHY2021
      @SURVEYOR_TEEWHY2021  2 ปีที่แล้ว

      Don't get your question.
      make it clear, so I can answer it here

    • @ahmedemmanuel8978
      @ahmedemmanuel8978 3 หลายเดือนก่อน

      Hello sir,asper there the site level sir..how do you established it sir

  • @makindeisaiah4394
    @makindeisaiah4394 ปีที่แล้ว +1

    How can one establish a bend mark?

    • @SURVEYOR_TEEWHY2021
      @SURVEYOR_TEEWHY2021  ปีที่แล้ว

      Do you measure the first one with tape from the floor. Before transferring others with dumpy Level?
      This is what I do always.

  • @bensonlazaro2351
    @bensonlazaro2351 2 ปีที่แล้ว

    On road constraction