    Being able to spot correct near-critical activities of the project schedule is as important as managing critical activities.
    Hope this video will help you learn the correct way of finding near-critical activities.

  • @shahjalal2946
    @shahjalal2946 10 หลายเดือนก่อน

    Make a video on concurrent delay

  • @munkhbatnagdalsuren5238
    @munkhbatnagdalsuren5238 14 วันที่ผ่านมา

    Hello, really appreciated to your video, but in my p6 program my float path column is blank. what should i do?

  • @Hasshirkhanbri
    @Hasshirkhanbri 10 หลายเดือนก่อน +1

    Thanks for this video. dear i've a query. if a project is in -90days of total float and total activates are more then 1000, then there will be many activates which causes -ve float of project. 1st: how can i get the total list of activities which causes -ve float? 2nd: how can i get the major activity out of 1000 which cause -ve float.

    • @krishnachiddarwar505
      @krishnachiddarwar505  10 หลายเดือนก่อน

      Answer to first question: there is a simple filter which will give you the list of activities with negative float. Second Answer: sorting out the activities will give you the tasks with maximum float.
      More sophisticated way to do it is create alternate float lines

  • @munawarjack91
    @munawarjack91 3 ปีที่แล้ว +1

    Hi Sir i m watch ur p6 videos to learn p6 my request you to prepare advance tutorial as well most important Recovery/ Revised/EOT/ Mitigation/ Contingency... Etc Schedule asap

    • @krishnachiddarwar505
      @krishnachiddarwar505  3 ปีที่แล้ว

      Thanks for watching and your suggestions, will try to make videos on your suggested topics as well!!

  • @sayyedalkhamash9502
    @sayyedalkhamash9502 2 ปีที่แล้ว +1

    i have critical activites i want to make them non critical how

    • @krishnachiddarwar505
      @krishnachiddarwar505  ปีที่แล้ว +1

      Sorry Sayed, it does not work that way. On paper you do things which add float to your activities make something else critical 😄😄