How to implement an Audit Process Cycle according VDA 6.3, IATF 16949 & ISO 19011:2018
ฝัง
- เผยแพร่เมื่อ 16 ก.ย. 2024
- The Success of an organisation's management system is dependent on the Internal Audit Process's ability to effectively detect the system's weaknesses and implement systematic corrective actions to continuously meet the customer's requirements.
The Audit Process cycle includes the following steps
1) Managing the Audit Programme
2) Audit request
3) Preparing for the Audit
4) Conducting the Audit
5) Evaluation - writing the report
6) Presenting the results to the organisation's management
7)follow-up and closure
The Audit Process Cycle is applicable to all management standards
VDA 6.3, IATF 16949, ISO 9001, ISO 14001, ISO 45000, ISO 50000
Thank you very much.
Amazing video, this video very helpful to me
Thank you
Great
Thanks
It's really fantastic
what is the meanjng of IODT
Dont understand the question. To which scene are you referring?
@@QualityComSolutionsI refer this :clarifying the initial situation with the IODT at about 37 second of the viedo,I am not sure the word was “IODT”,tks
Hi, clarifying the situation with the “Auditee’ The organization or department being audited. All my future videos will have better quality voiceovers. Thank you for clarifying. I appreciate it.
@@Route33ClassicPorscheandCoffee I get it,thank you very much.