Impacted As-Planned MIP 3.6 - Delay Analysis
ฝัง
- เผยแพร่เมื่อ 21 ส.ค. 2023
- In this video, I explain the Impacted As-Planned MIP 3.6 according to the AACEI RP 29R-03.
Check out our comprehensive Power BI course at the below link
www.smartpmtraining.com/courses
Check out other comprehensive project control courses at the below link
www.smartpmtraining.com/courses
Very good tutorial, thanks.
You're welcome. Thanks for your kind words!
Very Nice Calculation 💐💐💐
Thanks!
Hello, Mr. Osama. One issue troubles me a lot recently. Could you help me? Everytime I open the project, it just go to the bottom of the whole project, like" Take over date". But I want it show the "milestone" when I open one project like before, the top of project, but I don't find how to solve this issue. P6 version 19 and 21 have the same problem.
1. Create a level 1 WBS called Key Dates and Milestones and place it just below the Level 0 WBS or Project Name line.
2. Add milestones like Project Commencement Date, Take/Hand Over Date and other milestones under the WBS
3. Link the each milestone you have there to the respective activities leading to that completion of the milestone with FF.
That should solve your troubles 😉
@@ehidiamenmichaele.4082 Thanks for your reply. My project is just made by these steps, but it doesn't work