Navigating Divergent Diamond Interchanges in Rexburg
ฝัง
- เผยแพร่เมื่อ 30 พ.ค. 2024
- The Rexburg north interchange will receive traffic signals. University Blvd (Exit 332) and Main Street (Exit 333) interchanges will be reconfigured for divergent diamond interchanges. Please watch the video to learn more about how drivers will navigate through the new interchanges.
The following is ITD’s most recent construction schedule:
March 8: Construction begins
June 10-June 28: University Blvd (Exit 332) Full Closure
July 8-July 22: University Blvd (Exit 332) Single Lane/Single Ramp Closure
July 29-August 23: SH33/Main St (Exit 333) Full Closure
August 26-September 13: SH33/Main St (Exit 333), Single Lane/Single Ramp Closure
October 31: Construction expected to conclude
To learn more about the project, visit ITD’s Rexburg project webpage.