How to Estimate Activity Duration in Primavera 6 Using Productivity Rate Part 4

แชร์
ฝัง
  • เผยแพร่เมื่อ 17 ม.ค. 2022

ความคิดเห็น • 13

  • @abinsuresh4648
    @abinsuresh4648 10 หลายเดือนก่อน

    Good

  • @hanofwvlogs
    @hanofwvlogs 7 หลายเดือนก่อน

    Gud pm po Sir! Ask lang po. Paano niyo po kinumpyut isa-isa ang Activity Duration ang 31.25 lang po ang tumama sakin?

  • @ferhawnqureshi6770
    @ferhawnqureshi6770 8 หลายเดือนก่อน

    Thanks for the great explanation. Can you share this excel file?

  • @noillsmatter9090
    @noillsmatter9090 2 ปีที่แล้ว

    Sir Carl good day, tanong lang sir. Halimbawa sa post tender BOQ ang lumabas na project cost 1,200,000.00 pesos after costing sa tender department, ngayon nenegotiate ng client and cost to 1,100,000.00 pesos at pumayag nman ang contractor na nag tender para makuha lang ang project. ngayong sir sa planning anong amount ba gamitin natin , ang 1.1M ba na enagree both party? Thank you.

    • @carlmoss4335
      @carlmoss4335  2 ปีที่แล้ว

      yung pong approved contract cost na sign ng client at contractor na nakalagay sa BOQ ang gagamitin sa baseline schedule at sa billing

    • @noillsmatter9090
      @noillsmatter9090 2 ปีที่แล้ว +1

      @@carlmoss4335 so mangyari nyan sir e adjust mo lahat ng cost pef item sa excel, Tama ba sir?

    • @kingofonepiece88
      @kingofonepiece88 9 หลายเดือนก่อน

      oo adjust mo @@noillsmatter9090

  • @johnvincenthernando6714
    @johnvincenthernando6714 2 ปีที่แล้ว

    Sir goodeve,ask ko lang if paano kayo nag come up sa "output per hour", output po ba sya ng each workers or yang 1.4m3 po is yung total outputs nilang lahat na pinagsama? and if ever po na ang sagot nyo is yan ay outputs ng each workers,ibig po ba sabihin na pareparehong 1.4m3 yung outputs ng ibat ibang skilled workers (foreman,mason,labor)?

    • @carlmoss4335
      @carlmoss4335  2 ปีที่แล้ว

      ang 1.4cu.m per hr.ay productivity rate base on actual experience ng mga contractor sa pilipinas.Ang manpower po na kailangan para makagawa ng 1.4cum.per hr. ay 1 forman,4 skilled laborers at 8 semi skilled laborers.

    • @masayahingkusinera5142
      @masayahingkusinera5142 9 หลายเดือนก่อน

      This is noted po sir​@@carlmoss4335. Ask ko din po kung yung pong productivity rate ay pwedeng gamitin either sa whole floor or sa per area? Incase po sa akin given ang data based sa per floor accomplishment pero ang required po ay per area na duration. Salamat po

  • @ravindrankrishnan2964
    @ravindrankrishnan2964 2 ปีที่แล้ว

    Hi, I am from india. Your explanation in the Videos is good. Also, can you pls share your excel working sheets ( Labour / Equipment Productivy and Materials Qty - which you are uploading in Primavera ) in the channel or to my mail id.

  • @kingofonepiece88
    @kingofonepiece88 9 หลายเดือนก่อน

    5:04 san nakuha yung 31.25 days sir?

    • @carlmoss4335
      @carlmoss4335  9 หลายเดือนก่อน

      250 hrs. divide by 8 hrs per day equals 31.25 days or 32 days