Is it true that ES is the same as the previous activity's EF (around 34:57)? PMBOK (5th ed) does not show this (see Figure 6-18), but instead shows ES = previous activity EF+1.
Dear Karol Skadiang, You are right the early start of successor is actually EF of predecessor plus 1 day.. In the provided diagram & explanation you should you should read finish day as end of that day & Start day as the start of next day. For Example Activity 1 finishes on day 3 which means end of day three, further start day of Activity 2 is written as 3 which means start of day 4. Indicating this way would help the calculation become simplier i.e. 3+3=6 the finish day and so on. However, for the same thing you can also put day-4 as the starting day of Activity 2, but while calculating finish day you should use -1 to get the correct finishing day... For example the duration of Activity 2 is 3 days, if I add 3 to start day 4 it will become 7 which is wrong (i.e. 4+3 = 7).. In this case you should calculate like this 4+3-1 = 6, which will give you correct value. Hope this helps...!?
Hi Chakaravarthy We are upgrading the content therefore the old videos have been removed. We will be adding new videos very soon. You can join our course to get all our videos: www.simplilearn.com/project-management/pmp-certification-training?Time-Management-uTBGw56ztJ8&SC&
Hi Smrtdis, All the material will be provided only to the people who signed up for our courses. You can always check back these tutorials whenever you need. We will be updating the PMP tutorial playlist with new videos: th-cam.com/play/PLEiEAq2VkUULnZpxaLHNBoalEM868K2_p.html
Hi Archie :) To get the entire set of videos and 90 days of access to 14+ instructor-led online training classes please signup for the course: www.simplilearn.com/project-management/pmp-certification-training?Time-Management-uTBGw56ztJ8&SC&
Hi Musa We are sorry but the videos are not downladable. You can join our course to have access to more of such videos: www.simplilearn.com/project-management/pmp-certification-training?Time-Management-uTBGw56ztJ8&SC&
🔥PMP® Certification Training - www.simplilearn.com/project-management/pmp-certification-training?TBGw56ztJ8&Comments&TH-cam
🔥Professional Certificate Program in Project Management - www.simplilearn.com/pgp-project-management-certification-training-course?TBGw56ztJ8&Comments&TH-cam
This is an awesome lesson!
Thanks Cleyton :) If you are thinking of signing up for the course, please click on the link for more information: www.simplilearn.com/project-management/pmp-certification-training?Time-Management-uTBGw56ztJ8&SC&
Excellent recap!! Nice voice to listen to :)
This is an awesome lesson. many thanks
Thanks Musa :) You can watch more PMP videos here: th-cam.com/play/PLEiEAq2VkUULPx4heWRZFC-fxQ9zWDaEf.html
Thanks for such a great explanation!
You are welcome!
Is it true that ES is the same as the previous activity's EF (around 34:57)? PMBOK (5th ed) does not show this (see Figure 6-18), but instead shows ES = previous activity EF+1.
Dear Karol Skadiang,
You are right the early start of successor is actually EF of predecessor plus 1 day.. In the provided diagram & explanation you should you should read finish day as end of that day & Start day as the start of next day. For Example Activity 1 finishes on day 3 which means end of day three, further start day of Activity 2 is written as 3 which means start of day 4. Indicating this way would help the calculation become simplier i.e. 3+3=6 the finish day and so on.
However, for the same thing you can also put day-4 as the starting day of Activity 2, but while calculating finish day you should use -1 to get the correct finishing day... For example the duration of Activity 2 is 3 days, if I add 3 to start day 4 it will become 7 which is wrong (i.e. 4+3 = 7).. In this case you should calculate like this 4+3-1 = 6, which will give you correct value.
Hope this helps...!?
Thanks Chandra MR(Simplilearn Team) for answering the query. Cheers !!
Most of the videos are coming as Private videos & I am Unable to view. Whether they are Removed? we can only view first 3 only
Hi Chakaravarthy
We are upgrading the content therefore the old videos have been removed. We will be adding new videos very soon. You can join our course to get all our videos: www.simplilearn.com/project-management/pmp-certification-training?Time-Management-uTBGw56ztJ8&SC&
Is there a way to get the PPT used?
Hi Smrtdis, All the material will be provided only to the people who signed up for our courses. You can always check back these tutorials whenever you need. We will be updating the PMP tutorial playlist with new videos: th-cam.com/play/PLEiEAq2VkUULnZpxaLHNBoalEM868K2_p.html
Where is lesson 5 please? I did lessons 1-4 but can only find Lesson 6 now?
Hi Archie :) To get the entire set of videos and 90 days of access to 14+ instructor-led online training classes please signup for the course: www.simplilearn.com/project-management/pmp-certification-training?Time-Management-uTBGw56ztJ8&SC&
is it downloadable ?
Hi Musa
We are sorry but the videos are not downladable. You can join our course to have access to more of such videos: www.simplilearn.com/project-management/pmp-certification-training?Time-Management-uTBGw56ztJ8&SC&