My last bit on "Why do we not hire a lawyer to run projects, and why project managers cannot twist the meaning of the contract to fit for his/her own interest" is based on my other rather interesting stories. This is an important reminder. Part 2 and Part 3 coming. Give me some time. I am tied up by work in England these days. =)
Oh hi! Sorry for replying late I was tied up by work these days. A compensation event is any event under Cl. 60 of NEC ECC. A notification of a compensation event triggers the contractual process. Cl. 61 onwards. After notification, an event may turn out to be not a compensation event at all.
My last bit on "Why do we not hire a lawyer to run projects, and why project managers cannot twist the meaning of the contract to fit for his/her own interest" is based on my other rather interesting stories. This is an important reminder.
Part 2 and Part 3 coming. Give me some time. I am tied up by work in England these days. =)
請問NEC4裡, CE 同 NCE 有乜分別呢? Thx
Oh hi! Sorry for replying late I was tied up by work these days.
A compensation event is any event under Cl. 60 of NEC ECC.
A notification of a compensation event triggers the contractual process. Cl. 61 onwards. After notification, an event may turn out to be not a compensation event at all.