  • Basics of Re order point Planning,
    Manual Re order point planning,
    Automatic Re order point planning,
    Net Requirements Calculation for Reorder Point Planning,
    Forward Scheduling for External Procurement,
    Setting the Purchasing department processing time in Configuration
    SPRO → Materials Management → Consumption-Based Planning→ Plant Parameters → Carry Out Overall Maintenance of Plant Parameters.
    Considering External Requirements, Setting external requirements indicator in Configuration in
    SPRO → Materials Management → Consumption-Based Planning → Master Data → Check MRP Types,
    Display and explanation of standard Customizing settings for MRP types VB (Manual re order point planning ), VM (Automatic re order point planning ) V1 (Manual re order point planning with external requirements) and V2 (Automatic re order point planning with external requirements), Exercise on Create a material master record with MRP 1 and MRP 2 views and how to determine the availability date for a material
    My other videos on MRP are as given below
    SAP MM MRP_Overview of MRP Part 1_Consumption based planning
    • SAP MM MRP_Overview of...
    SAP MM MRP_MRP Procedures Part 2 Consumption based planning
    • SAP MM MRP_MRP Procedu...
    SAP MM MRP_Material Master Record Part 3 Consumption based planning
    • SAP MM MRP_Material Ma...
    SAP MM MRP_Planning run Part 1 Basics of the planning run
    • SAP MM MRP_Planning ru...
    SAP MM MRP_Planning run Part 2 Executing the planning run
    • SAP MM MRP_Planning ru...
    SAP MM MRP_Test Exercise on Executing the planning run
    • SAP MM MRP_Test Exerc...
    SAP MM MRP_Planning run Part 3 Planning Result in MRP Planning Run
    • SAP MM MRP_Planning ru...
    SAP MM MRP_Test Exercise on Planning run Part 3 Planning Result
    • SAP MM MRP_Test Exerci...
    SAP MM MRP_Planning run Part 4 Section A Planning Evaluation
    • SAP MM MRP_Planning ru...
    SAP MM MRP_Planning run Part 4 Section B Planning Evaluation
    • SAP MM MRP_Planning ru...
    SAP MM MRP_Planning Run Part 4 Section C Planning Evaluation
    • SAP MM MRP_Planning Ru...
    SAP MM MRP_Planning Run Part 4 Section D Planning Evaluation
    • SAP MM MRP_Planning Ru...
    SAP MM MRP Lot Size Calculation
    • SAP MM MRP Lot Size Ca...

ความคิดเห็น • 14

  • @SenthilKumar-gh5zn
    @SenthilKumar-gh5zn 4 ปีที่แล้ว +3

    Excellent explanation on re order point planning in SAP MM. Thank you very much,....

  • @pro.shaivipandey
    @pro.shaivipandey 4 ปีที่แล้ว +3

    Appreciate the effort

  • @ankitaggarwal586
    @ankitaggarwal586 4 ปีที่แล้ว

    Very nice explanation. Thank you very much.

  • @pavankumar-tx5ko
    @pavankumar-tx5ko 4 ปีที่แล้ว +1

    Eagerly waiting for further sessions.

    • @expertcoachinginsapmmwmsrm1593
      @expertcoachinginsapmmwmsrm1593  4 ปีที่แล้ว +1

      Hi pavan, Thank you for your interest in my videos. I was very busy in some urgent SAP Project. I will share other videos on MM soon. Please share my videos to your friends working in MM or interested in learning MM.

    • @mahikanna1241
      @mahikanna1241 4 ปีที่แล้ว

      @@expertcoachinginsapmmwmsrm1593 sure sir ..i am interested to learn MM i hope i have completed 65% so with MM which module i cant learn sir(if i am adding another sap module) ..i mean with MM which sap module will be the best to get jobs in supply chain dep and power user sir..i am MBA final year student my course is supply chain management my UG is BE in ECE and Diploma in ECE sir ..i need your help

    • @prathaphassan5164
      @prathaphassan5164 3 ปีที่แล้ว

      Hi sir . Soo far the best ......

    • @prathaphassan5164
      @prathaphassan5164 3 ปีที่แล้ว

      Everyone would do a simple topic but u have gone far and explained some important real time topics which is required for interview

    • @prathaphassan5164
      @prathaphassan5164 3 ปีที่แล้ว

      I would like to learn from ..my name is vivek sap mm and ewm consultant with 2 yrs of exp .could you please drop ur number so that i can learn by connecting with u

  • @ruchancakaloglu
    @ruchancakaloglu 4 ปีที่แล้ว

    I want to keep some FERT stocks at a certain level all the time .. they are sold regularly. So can I use reorder point planing ? Or is it only for purchased material ?
    Regards.

    • @expertcoachinginsapmmwmsrm1593
      @expertcoachinginsapmmwmsrm1593  4 ปีที่แล้ว

      Re order point planning is mainly for externally procured materials. FERT materials are mainly sold to customers. If you procure FERT materials from external vendors for selling to customers then you can use re order point planning.

    • @ruchancakaloglu
      @ruchancakaloglu 4 ปีที่แล้ว

      @@expertcoachinginsapmmwmsrm1593 one of my customer produces finished goods and they don't want to enter forecast from md61 , instead they want their finished materials to be produced automatically whenever the stock level decraces below a certain level. That's why I want to use VB .. İnstead of using VB , do you recommend any other way to manage this? Regards.

    • @expertcoachinginsapmmwmsrm1593
      @expertcoachinginsapmmwmsrm1593  4 ปีที่แล้ว +1

      @@ruchancakaloglu I think you can use VB if you are using planned order to produce the finished material in plant. In such case whenever the stock falls below re order point system will create a planned order which will convert into production order. Iin this way you can maintain the stock of the material.
      You can test one cycle in test system and make sure it is as per your requirement.