Mam I have a question if we get two critical paths and both parts don't have common points For example 1-2-3-4& 2-4-5 in this case what shall we do for finding the optimal cost ?
Hello maam, I have a doubt here at 14:21 u are saying that the hrs will remain same for other paths other than critical past for 4 hrs however 5-6 activity is in both the paths wont the critical path then be 28 hrs ? Itll be very helpful if u could clarify this doubt.
on 3-5 activity you will incur cost of 50 and on 2-5 cost of 45 in total which is 95.....adding this to the previous cost 3385 and reducing indirect cost of 50 by 2 days i.e; 3385 +(50+45) -(2*50)=3380 this is more than what you will incur(3375) if you only crash activity 5-6 by 2 days as shown in the video, so crashing 5-6 will be the better option as objective is to incur minimum cost .
Mam I have a question if we get two critical paths and both parts don't have common points
For example 1-2-3-4& 2-4-5 in this case what shall we do for finding the optimal cost ?
This was a wonderful class ma'am. Really understood the concept with simple steps😄. Hare Krishna!!🙏🙏
Nice explanation mam !
Thank you 👍
Hello maam, I have a doubt here at 14:21 u are saying that the hrs will remain same for other paths other than critical past for 4 hrs however 5-6 activity is in both the paths wont the critical path then be 28 hrs ? Itll be very helpful if u could clarify this doubt.
Yes the critical path will reduce, but to 29 hours when you chose 5-6 for crashing...
Thank you. Superb explanation
Best best best explanation..
Please also upload FM BOARD BOOK problems specially capital budgeting new syllabus...
Your classes are very good...best conceptual clarity hai mam...
Hello mam , pls bring a Marathon on Cost accounting for Last day revision !
Hello Mam, at 26:12 can't we take activity 3-5 and 2-5 through this we'll be able to get cost=3370.. Please reply..!! 🙏🏻🙏🏻
on 3-5 activity you will incur cost of 50 and on 2-5 cost of 45 in total which is 95.....adding this to the previous cost 3385 and reducing indirect cost of 50 by 2 days i.e; 3385 +(50+45) -(2*50)=3380 this is more than what you will incur(3375) if you only crash activity 5-6 by 2 days as shown in the video, so crashing 5-6 will be the better option as objective is to incur minimum cost .
Hello mam CMA inter group 1 kaa MCQ compiler pdf banao naa. 30 marks secure ho jayenge humaare.
Thank you ma'am
Ma'am final ki bhi vdo dalo
❤️❤️❤️