Worked Example, NRM2 Take-Off & BQ production

แชร์
ฝัง
  • เผยแพร่เมื่อ 24 ก.ค. 2024
  • This video will guide you step by step how in taking-off a small structure in accordance with NRM2 and produce a Bill of Quantities.
    00:00 Substructure, Site prep
    11:42 Substructure, Foundations
    13:17 Walls
    23:45 Bill of Quantities production

ความคิดเห็น • 20

  • @geoffhodgson2492
    @geoffhodgson2492  4 หลายเดือนก่อน +1

    Thanks for your kind comments, very much appreciated. I will be doing many more videos so keep watching. Geoff

  • @OwenNjogu-bz9ob
    @OwenNjogu-bz9ob 2 หลายเดือนก่อน +1

    Thanks alot for the simple breakdown,,as a student this is more than important

  • @BANN9444
    @BANN9444 3 หลายเดือนก่อน

    Geoff, this is incredibly value information. Thank you for taking the time to put this together. You are a natural on camera and provide great commentary.

    • @geoffhodgson2492
      @geoffhodgson2492  3 หลายเดือนก่อน

      Thanks for your kind comments. Very much appreciated

  • @thehalokidster7102
    @thehalokidster7102 3 หลายเดือนก่อน +1

    Great video, many thanks! It's great the way you bring it all back to referencing the NRM2. Some NRM1 videos would be absolutely amazing, with a focus on writing descriptions as well. :)

    • @geoffhodgson2492
      @geoffhodgson2492  3 หลายเดือนก่อน

      Glad your licked them and thanks for your comments

  • @Vincent-MA94
    @Vincent-MA94 4 หลายเดือนก่อน +1

    Thank you so much for this incredibly helpful video on NRM2 Take-Off & BQ production! 🙏 As a student in Quantity Surveying, clear explanations like these are absolute gold. Your breakdown of the process was spot-on and really clarified some key concepts for me. Can't wait to see more content from you in the future - your videos are a fantastic resource for students like myself trying to deepen our understanding of the field. Keep up the great work! Best Ever!

    • @geoffhodgson2492
      @geoffhodgson2492  3 หลายเดือนก่อน

      Thanks for your kind comments

  • @JulyFighting
    @JulyFighting 3 หลายเดือนก่อน

    My word I wish this was available when I was a student, this is really great stuff.

  • @iaincrawford5472
    @iaincrawford5472 3 หลายเดือนก่อน

    Geoff, these videos are great for everone new and old to the construction industry. It would be fantastic if you could show drainage and roads take off, and how these take-offs then form the BOQ. Very impressed by the level of quality and information in your videos.

    • @geoffhodgson2492
      @geoffhodgson2492  3 หลายเดือนก่อน +1

      Thanks for your very kind comments Iain. I will be preparing a tutorial on drainage take-off and I also am considering tutorials on the Method of Measurement for Highway Works as well if I sense there is a demand.

  • @ceemapanda4811
    @ceemapanda4811 3 หลายเดือนก่อน

    wow thank you for breaking it down so clearly.

  • @MarkeziProducer
    @MarkeziProducer หลายเดือนก่อน

    Great video Geoff, thank you for explaining this to the details, it really helps.

    • @geoffhodgson2492
      @geoffhodgson2492  13 วันที่ผ่านมา

      Thanks for your comments and glad you have found the channel useful. There will be more videos so keep checking back

  • @charlesokoro2100
    @charlesokoro2100 3 หลายเดือนก่อน

    I chanced on your channel just today and it has been such a blessing. I look forward to more contents. Thanks a lot.

    • @geoffhodgson2492
      @geoffhodgson2492  3 หลายเดือนก่อน

      Thanks, I shall be more so watch this space

  • @dennismponda7805
    @dennismponda7805 หลายเดือนก่อน

    Absolutely Amazing,🔥

  • @breemurage
    @breemurage 3 หลายเดือนก่อน

    thank you for this

  • @bigpot
    @bigpot 2 หลายเดือนก่อน

    Is disposal of excavated measured as an item without quantities, cos the excavated trench will be filled with blockwork and the remaining backfilled and excess taken off site😊

    • @geoffhodgson2492
      @geoffhodgson2492  หลายเดือนก่อน

      Yes; under NRM2 Disposal, (5.9.1&2) is measured as an 'Item' as you say but... to calculate the amount of Filling obtained from excavated material, m3, (5.11.2) and Imported Filling, m3, (5.12.1,2 or3), the arithmatic of volume of excavation less the volume of the structure in the excavation is still maintained.