How to do a production order confirmation in SAP (CO11N)

แชร์
ฝัง
  • เผยแพร่เมื่อ 29 ต.ค. 2024

ความคิดเห็น • 6

  • @GusSawicki
    @GusSawicki 3 หลายเดือนก่อน +1

    Hi, when the times get confirmed for setup, machine, labor, breakdown, does that data automatically update the times in the system or does it just track the variance until someone can physically change the operation time in the system?
    Thanks!

    • @KHZeeds
      @KHZeeds  2 หลายเดือนก่อน

      If you enter time during the confirmation, it is considered as the actual values. Planned values come from the routing to production order. Same will be come to CO11N screen as planned values. User can change the values during the confirmation

  • @bondjames9936
    @bondjames9936 6 หลายเดือนก่อน +1

    Hello sir! I have 3 operation and 3 phase(0020, 0040, 0060) and control key with milestone (1). Will my phase be automatically set to 0060 or not? and what happens if I select phase 0020 or 0040? Surely I have automatic confirmation of all phases if I select the last phase (0060)?

    • @KHZeeds
      @KHZeeds  6 หลายเดือนก่อน

      What is your control key?

    • @bondjames9936
      @bondjames9936 6 หลายเดือนก่อน

      @@KHZeeds Control Key PI03 (for last phase) with confirmation 2

  • @abhijeetg5336
    @abhijeetg5336 4 ปีที่แล้ว +1

    Good