  • @judyl.7811
    @judyl.7811 3 หลายเดือนก่อน +1

    0:35
    with installed capacity of 440 MW, megawatt which was
    built under BOO, Build Own Operate concession agreement.
    power purchase agreement, PPA life: 25 years.
    Total Project Cost: over 800 million
    attracted debt financing of 510 million on non-recourse basis. (which is 75%)
    construction date: December 1996
    operations date: January 2000
    1:10
    philipines power plant development landscape:
    4:50
    PPA
    offtaker:
    structure: take or pay
    payment structure: capacity, O&M, energy fees,
    payment indexation: US dollar
    annual revenue 1st year:
    6:25
    EPCM contract
    Contractor:
    Contract structure:
    Guarantees: completion date & performance.
    6:50
    O&M contract, operation & management contract:
    7:30
    coal supply contract:
    coal suppliers:
    structure: put or pay
    guarantees: financial guarantees.
    8:20
    currency and country risk:
    exchange rate: PPA denominated in US$
    country risk: EXIM Bank insurance
    political & economic landscape: improving
    debt rating: upgrading
    9:35 turn-key EPC project.

  • @AugustinTomasOBrienCaceres
    @AugustinTomasOBrienCaceres ปีที่แล้ว +1

    We have 6 powerplants to finance in Brazil today

  • @AugustinTomasOBrienCaceres
    @AugustinTomasOBrienCaceres ปีที่แล้ว

    Agreed

  • @skolastikacynthia8108
    @skolastikacynthia8108 8 หลายเดือนก่อน

    what is sovereign guarantee?

  • @shodapad07
    @shodapad07 14 วันที่ผ่านมา

    5:45. All payments indexed to US Dollar. The reason and consequences would be appreciated!