How To Create Milestones In Smartsheet - All You Need To Do

แชร์
ฝัง
  • เผยแพร่เมื่อ 28 พ.ย. 2024

ความคิดเห็น • 4

  • @one9ooh6
    @one9ooh6 ปีที่แล้ว +1

    I have a timeline with subtasks, but I can't edit the duration for the main task because the subtasks. How would I assign a milestone? Unfortunately, I can't edit the duration for the main task. Smartsheet's message "Because this row has sub-tasks, this cell is a summary value and cannot be edited directly. You can edit cells beneath this row to change its value."

    • @ProperProjectManagement
      @ProperProjectManagement  ปีที่แล้ว

      Hi Julius. The main task is an amalgamation of the subtasks below. So you would need to update them, and it will roll up.