Load Flow Study Using ETAP | Part 2

แชร์
ฝัง
  • เผยแพร่เมื่อ 7 ม.ค. 2025

ความคิดเห็น • 17

  • @joeysaavedra56
    @joeysaavedra56 5 หลายเดือนก่อน

    Sir your tutorial is good and helpful, the voltage on this example is at 400V now, correct nominal voltage and what makes it 100.3%?

  • @erickmanangan4803
    @erickmanangan4803 ปีที่แล้ว

    Thank you PEE for sharing

  • @cbsuresh5631
    @cbsuresh5631 ปีที่แล้ว

    👍simple.. LF report generation you have not mentioned!?

  • @abdelmalek9682
    @abdelmalek9682 2 ปีที่แล้ว

    thank you sir! Just have two questions! what is the static load and lumped load represent ? what is the deferent between them and the induction motors??

    • @juliussalutan8006
      @juliussalutan8006  2 ปีที่แล้ว +2

      In a power system static loads are fixed loads which do not alter significantly, e.g. lighting system which draws power steadily over a period of time. This is opposite to dynamic loads that change rapidly, e.g. motor load which draws a large amount of power to start. In ETAP, lump load is composed of 80% motor loads and 20% static loads

    • @abdelmalek9682
      @abdelmalek9682 2 ปีที่แล้ว

      @@juliussalutan8006 thank you so much sir

  • @howcreated_ideas
    @howcreated_ideas 2 ปีที่แล้ว

    Sir where the information of impedance for the transmission line or cables? We need to provide data as well. Any information how to check it

    • @juliussalutan8006
      @juliussalutan8006  2 ปีที่แล้ว

      Impedande of cables have to be taken from the actual cable manufacturer.

    • @howcreated_ideas
      @howcreated_ideas 2 ปีที่แล้ว

      @@juliussalutan8006Sir Im asking in this tutorial ETAP software does not shown any information data of the transmission line cables, impedances, distance, and sizes.

    • @juliussalutan8006
      @juliussalutan8006  2 ปีที่แล้ว +1

      @@howcreated_ideas ETAP does not provide cable data for transmission line. It has to be manually encoded in ETAP library. You need to have data from other sources so that you can update your cable library.

    • @howcreated_ideas
      @howcreated_ideas 2 ปีที่แล้ว +1

      @@juliussalutan8006 Thank you Sir! Appreciate more video for tutorial..

  • @arielpineda4366
    @arielpineda4366 3 ปีที่แล้ว

    Can you share sir the differences of the four (4) operation mode - swing, mVAr, voltage and pf mode.

    • @juliussalutan8006
      @juliussalutan8006  3 ปีที่แล้ว +2

      I had briefly explain this operating modes on my first video (Load Flow first lesson video). If you have only one power grid or generator on your SLD, then it must be in swing mode. If you have power grid upstream and a generator somewhere downstream, then the power grid must be in swing mode while the generator could be any of the three i.e. voltage control, mvar control or pf control. Please note that there must be at least one swing machine for power grids or generators to be selected as a reference machine for the entire system.

    • @arielpineda4366
      @arielpineda4366 3 ปีที่แล้ว

      @@juliussalutan8006 yes sir i watched it. Thanks.

    • @juliussalutan8006
      @juliussalutan8006  3 ปีที่แล้ว

      @@arielpineda4366 welcome sir

    • @anandhakumaraiyaru
      @anandhakumaraiyaru 2 ปีที่แล้ว

      Hi

  • @abdelmalek9682
    @abdelmalek9682 2 ปีที่แล้ว

    ?????