sand pouring cylinder Calibration kaise karte hai
ฝัง
- เผยแพร่เมื่อ 16 ก.ย. 2024
- friends The pouring cylinder shall be filled so that thw level of the sand in the cylinder is within about 10mm of the top.
friends galti se 5 cm bol gye hai vedio me
10mm top se down hona chahiye sand.
sand pouring cylinder calibration kaise karte hai
THE SAND REPLACEMENT METHOD
#quality
Hi,
i am Hariom Singh
Having B.Tech with 9+ years of experience in Civil Engineering with the industry experience of Quality
Control Laboratory as well as in major projects such as Highways(Nh-11 Sikar bypass to Bikaner bypass Rajasthan 267 km And 47.5km 4 lane project Nh-151 A ), Railways( Track work for Dual line 626km Rewari to Iqbalgarh WDFC Project), High rise buildings, Railway Over Bridges & etc.
Company experience 1. L&T Construction Ecc Devision
2. GR LTD.
3. Monte Carlo LTD.
4. Adani Road & Transport LTD.
This is Vedio About - sand pouring cylinder calibration as per is code 2720 part 28
• Free swelling Index of... FSI Test procedure
#civil Engineering
#Quality control Laboratory
#construction
#Highways
#Roads
#soil
#quality
#ctsb
#fdd
sand pouring cylinder calibration
Pura video bataya karo with calculation
Achi video
Sir GSB and WMM ke liye konsa dia ka clyander se FDD karte hai
Thickness pe depend krta hau
Agar GSB me 200mm Thickness hai to 200mm ka cylinder use krte hai
Ek condition or hai ki 200 mm dia ke cylinder se 150 Thickness ka bed ko check kr skte
As per engineer
200 mm
Thank you
Calculation bhi dala kro
Uploaded kar diya hai pls check
Sir calculation bhi daalo
Noted
Bilkul nhi pasnd aaya kyo ki pura video nhi h
Dhnyawaad
Kya jan na hai bataye