25 - Control Modules - Introduction to Fire Alarms

แชร์
ฝัง
  • เผยแพร่เมื่อ 18 พ.ย. 2024

ความคิดเห็น • 75

  • @peterclark99
    @peterclark99 3 ปีที่แล้ว +10

    As someone new to this industry, this has been by far the most helpful resource I've been able to find. Wanted to say thank you for taking the time to do these videos.

  • @IrishMexican
    @IrishMexican 3 ปีที่แล้ว +11

    Dude, my company is using your videos for our fire alarm learning modules lol

  • @Ancientlaws
    @Ancientlaws 5 ปีที่แล้ว +2

    I've gone back to watch this video several times to remember how this all works. Very well done video and i hope you come back soon!

  • @tylerrodgers7928
    @tylerrodgers7928 11 ปีที่แล้ว +6

    Thanks for coming back to this series it's a big help with my education towards fire system programming and installation, can't wait for your next video to continue in this valuable series

  • @alexandermontoya6891
    @alexandermontoya6891 4 ปีที่แล้ว

    Sir, you just same my life, now, i have to watch every single of your videos. Thank you very much

  • @caleb0606
    @caleb0606 6 ปีที่แล้ว +1

    OMG your videos are so helpful and educational. i didn't know how addressable systems work until i watched your videos.

  • @oiramargenacob2057
    @oiramargenacob2057 9 ปีที่แล้ว +3

    New to FA your videos are very helpful thank you for continuing to share your knowledge.

  • @NickyVeee
    @NickyVeee 11 ปีที่แล้ว +2

    Very nice explanation, Joe! Glad you're back making videos. I was wondering how the power was supervised going to the module, thanks for the explanation.

    • @jepps1021
      @jepps1021 3 ปีที่แล้ว

      The newer notifier modules have a built in power supervision and if disconnected they automatically tell the panel "module _ loss of power " etc.

  • @Cornbread12345
    @Cornbread12345 4 ปีที่แล้ว +5

    This set up gives me anxiety lol and makes me happy I work for simplex.

  • @mava5634
    @mava5634 4 ปีที่แล้ว +2

    hats off for this man

  • @chasetech1
    @chasetech1 11 ปีที่แล้ว +1

    Thanks for coming back!

  • @elyseh9386
    @elyseh9386 11 ปีที่แล้ว +1

    I love your video joe keep them up

  • @lor332
    @lor332 2 ปีที่แล้ว

    Thanks for explaining this.

  • @miguelbernabe753
    @miguelbernabe753 ปีที่แล้ว

    Thanks for the great information. Please make a video with a FRM- 1 .

  • @jgyrwa
    @jgyrwa 5 ปีที่แล้ว +3

    Hey Joe, where can I get my hands on the software you are using in your videos?

    • @JoeKlochan
      @JoeKlochan  5 ปีที่แล้ว +2

      It's just microsoft paint and then screen capture software called Snagit

  • @Efficientelectricalequipment
    @Efficientelectricalequipment 8 หลายเดือนก่อน

    Thanks Joe for these amazing videos. I just have a question on this particular video, since we have four strobes connected to terminals 6 & 7, how can we address them to communicate with the addressable panel since we have two dials only on the FCM?

    • @jcnash02
      @jcnash02 3 หลายเดือนก่อน

      They aren’t addressed, they all go at once when the FCM tells them to.

  • @rainfordmiller3046
    @rainfordmiller3046 หลายเดือนก่อน

    Does the panel provide it own 24 volts

  • @JosephJimenez-s7m
    @JosephJimenez-s7m 9 หลายเดือนก่อน

    Would you need a EOL at speaker and strobe?

  • @peterjozefowicz6074
    @peterjozefowicz6074 6 ปีที่แล้ว

    With your current setup, the AVs won't sync per ADA standard. But if you use the Control Module to trip a BPS with sync capability and land the AVs on the BPS NACs. Only time you should use a Module to fire an AV directly is if your doing an outdoor AV for ring by tenant.

    • @JoeKlochan
      @JoeKlochan  6 ปีที่แล้ว

      Peter Jozefowicz that depends on what's powering your control module. If the power feeding the control module is already synchronized, the sync will pass through the control module.

    • @peterjozefowicz6074
      @peterjozefowicz6074 6 ปีที่แล้ว

      Joe Klochan the only 24v power source that you should be using are either the 24v R/NR contacts off the the FACP or the AUX on a BPS so it's a supervised source. What exactly are you using for 24v power?

    • @JoeKlochan
      @JoeKlochan  6 ปีที่แล้ว

      Peter Jozefowicz that depends on the setup. There are situations where FCPS panels are setup to be always on (aux power jumpered to input 1) and then the outputs feed control modules. That's typical in strip mall applications. In that case, the FCPS is the master sync. What are you going off when you say the ONLY power I should use is off the panel?

  • @brittajohn7540
    @brittajohn7540 4 ปีที่แล้ว

    It's very awesome I'm learn some experience from you but I'm stuck and I need help please how to wire a sounder wire and smoke detector to the control panel

  • @simeonpalenzuela9241
    @simeonpalenzuela9241 3 ปีที่แล้ว

    May I ask a question about the wiring of speaker strobe connected to the FCM-1 module. Do we need to run 24volt DC from fire alarm panel to the FCM-1 module? I understand there is an amplified signal already connected to the module.

    • @JoeKlochan
      @JoeKlochan  3 ปีที่แล้ว +1

      No, there wouldn't be 24 volts going to that module, only SLC, the audio signal from the amplifier, and then the output to the speakers. Those are the only circuits connected to the module.

    • @simeonpalenzuela9241
      @simeonpalenzuela9241 3 ปีที่แล้ว

      Thank you very much, from the Philippines.

  • @alejandrotorres3444
    @alejandrotorres3444 3 ปีที่แล้ว

    Hello. Is there any code regarding to location this control module has to be located? Any distance from the Panel? Or any distance from the notification appliance used?

  • @hummermusik2037
    @hummermusik2037 7 ปีที่แล้ว +1

    Can a addressable zone connected to module ?

  • @hassanhassun2300
    @hassanhassun2300 5 ปีที่แล้ว

    Thank you so much for your information

  • @kjvsoulwinners6756
    @kjvsoulwinners6756 4 ปีที่แล้ว

    Does the auxiliary power need to be resettable even though it’s on standby? And if so how can you make it resettable, because it appears that it cannot be resettable with just the power supervision relay?

    • @JoeKlochan
      @JoeKlochan  4 ปีที่แล้ว

      I haven't watched this video in a long time, so I don't remember exactly what I got into, but power feeding control modules shouldn't need to be resettable. If it was a zone monitor module (the type that requires external power to feed conventional smokes), that would require resettable power, which can be achieved by installing an addressable relay and programming it for resettable power, depending on the panel.

  • @andrewhiv1728
    @andrewhiv1728 3 หลายเดือนก่อน

    Dear Sir. May I have one question. If external DC 24V power supply broken, is the panel show trouble for this FCM module? One of my project the alarm bells are connected with FCM module. Now client want to off alarm bell at the day time and on back in the night time. I am planning to disconnect external power supply to this FCM module.Is it possible?
    TIA
    Andrew

  • @gideonduncan8211
    @gideonduncan8211 3 หลายเดือนก่อน

    Will you be kind enough to share some knowledge on how annunciators work and tie in to an FACP?

    • @JoeKlochan
      @JoeKlochan  3 หลายเดือนก่อน +2

      Typically it's a data signal called EIA-485. Some panels require 2 data wires, some require 4 because they require a return. All will also require 2 24 volt power cables as well.

    • @gideonduncan8211
      @gideonduncan8211 3 หลายเดือนก่อน

      @@JoeKlochan thank you so much Joe for taking the time to reply. And thanks for the videos they have been very informative. I knew what they were supposed to operate in theory but never how they really worked to this extent. You delved deeper into how they operate the animations really helped bring them together.

  • @randomvideo9551
    @randomvideo9551 10 หลายเดือนก่อน

    Can you use class a on a control module?

  • @MrPpotempa
    @MrPpotempa 11 ปีที่แล้ว

    You could also use the power supervision relay with the EOL resistor on the NAC circuit to avoid using an additional module. However that is only beneficial of your EOL device is close to your power source as running the source power all the way to the EOL device is impractical at long distancea.

  • @caleb0606
    @caleb0606 6 ปีที่แล้ว

    can you supply 12v to the control module for external power

  • @willlatino
    @willlatino 6 ปีที่แล้ว

    are you still doing more videos?

  • @lktrapboy2981
    @lktrapboy2981 4 ปีที่แล้ว

    Any chance you can make more videos like this with different devices

    • @JoeKlochan
      @JoeKlochan  4 ปีที่แล้ว

      Perhaps eventually, though I've fallen out of the phase of wanting to make more currently. When I get back in that phase, I already have a project that I started in mind.

  • @joserafaelvalecillosbricen2777
    @joserafaelvalecillosbricen2777 ปีที่แล้ว

    Buenas tardes, saludos por favor algún link para ver el video en español, gracias.

  • @kjvsoulwinners6756
    @kjvsoulwinners6756 4 ปีที่แล้ว

    Do those horn strobes have to be wired in series?

    • @JoeKlochan
      @JoeKlochan  4 ปีที่แล้ว

      Horn strobes are wired in parallel.

  • @dhananajayparsad8512
    @dhananajayparsad8512 ปีที่แล้ว

    Thank you

  • @pallidinvestmentsfire6207
    @pallidinvestmentsfire6207 2 ปีที่แล้ว

    How Sir l would like to learn more about fire alarm lm from South Africa...how do l get full videos of installation and wiring whole fire panel /manual call point and smoke detectors

    • @JoeKlochan
      @JoeKlochan  2 ปีที่แล้ว

      I'm not sure anyone has made any

  • @irelandhm
    @irelandhm 3 ปีที่แล้ว

    What point on the panel would these start on?

    • @JoeKlochan
      @JoeKlochan  3 ปีที่แล้ว

      Not sure I totally understand the question. I haven't watched this video in a long time so I don't remember exactly what I covered in it, but the short answer is it would start at the SLC. That circuit would allow the module to communicate with the panel, then it would need some sort of power source, either 24 volts for horn strobes, or an amplifier circuit if it's for speakers. If you mean what address would it start at, on most panels that wouldn't matter, you could use any open address.

  • @ahmedsalemegy
    @ahmedsalemegy 3 หลายเดือนก่อน

    Need know if power cut in fcm
    Will give signal to panel its faulty

    • @JoeKlochan
      @JoeKlochan  3 หลายเดือนก่อน

      Good question. If it's an FCM, and so it's on a notifier panel, then most likely yes you'll get a trouble. But it depends on how that FCM is programmed and what it's doing. If its power source is 24 volts and it's triggering strobes or a NAC panel, then it should give you a power loss trouble. It's been a number of years since I've worked for a notifier distributor, so I'm a little out of practice. I don't remember all the different type codes. If it's tripping speakers, the FCM won't give you a trouble because you don't have 24 volts present on those terminals, rather it's a signal from the amplifier.

  • @lktrapboy2981
    @lktrapboy2981 4 ปีที่แล้ว

    Or if there’s any ways we can get in contact

  • @davidparedes9720
    @davidparedes9720 2 ปีที่แล้ว

    hola me puede explicar donde saca la alimentación para el modulo fcm 1, de la salida de los sensore o de la sirena en eso me pueden ayudar

    • @JuanEsquivel_uno
      @JuanEsquivel_uno ปีที่แล้ว

      la energía la puedes obtener de una fuente externa, si es mucha la distancia; si es menor a 50 o 60 mts del panel al dispositivo, la puedes obtener del mismo panel, solo valida si el panel cuenta con esa salida de fuente a 24v, saludos desde cdmx @ventassiensenet2695 th-cam.com/video/FPKStQyk8Ps/w-d-xo.html

  • @bustroff7937
    @bustroff7937 4 ปีที่แล้ว

    Молодец чувак😂👌

  • @tarun6444
    @tarun6444 6 ปีที่แล้ว

    Please do some more videos

  • @dhananajayparsad8512
    @dhananajayparsad8512 ปีที่แล้ว

    Good morning sir

  • @Kannanvel78
    @Kannanvel78 ปีที่แล้ว

    How to. Replace OLD FCM WITH NEW ONE

  • @hummermusik2037
    @hummermusik2037 7 ปีที่แล้ว

    Why we need a module?

  • @alejandrotorres3444
    @alejandrotorres3444 3 ปีที่แล้ว

    Please, advice:(

  • @betomendoza5981
    @betomendoza5981 2 ปีที่แล้ว

    I've never seen them be able to sync with control module. Project managers, service guys, head of fire alarm calling tech support, never seen it.

    • @JoeKlochan
      @JoeKlochan  2 ปีที่แล้ว

      I've never seen it not work. All the control module does is pass the input source to the output terminals when it's prompted. It doesn't interfere with sync at all. I just finished a job this week where we did this again, no sync issues. What kind of equipment are you working on?

    • @betomendoza5981
      @betomendoza5981 2 ปีที่แล้ว

      @@JoeKlochan fire lite, the new nac booster is altronix. Were getting 24v from the booster and tying in to control module it has slc. Yeah, if you can tell me how to synch'em I'll take the help.

  • @mdahsanalam5454
    @mdahsanalam5454 4 ปีที่แล้ว

    Please hindi me sir

  • @mdehsan6961
    @mdehsan6961 4 ปีที่แล้ว

    Sir Hindi me to

    • @JoeKlochan
      @JoeKlochan  4 ปีที่แล้ว

      I'm sorry, I've seen a few comments like this and I have no idea what that means. Can you help me understand?

    • @reddyprahlad
      @reddyprahlad 4 ปีที่แล้ว

      @@JoeKlochan he's asking you to explain in Hindi which is the national language of India