Do you know if it is possible to add an hourly rate to the human resources working on the project? In this way the real cost of the project could be calculated based on the hourly rate * the number of hours worked. Thanks
Hi, thanks for the comment. I believe that's the default, actually. But if it's not you might be able to trick the dataverse to lock the fields by using field level security... but that's pretty technical
Hi Jollyadivasi, Projectum has a global partner network with maybe even a local partner that can assist you in implementing the solution. In the description text, you can find a link to the "let's talk" page. There's also a QR code at the end of the video in case you want to use that instead. You can reach out to us through that link to get in touch with the right (local) partner. Regarding the line limitation, Project for the web currently has a 500 rows limitation, but Microsoft mentioned the following in their Ignite presentation: "With the increase of task limits, plans built in Project for the web can scale up to 1,000 tasks to take on those larger projects."
Great video Erik! It’s exciting to see how PowerPPM is maturing. The integration with Project for the Web looks really good.
Totally agree! And happy to hear from you.
Looking forward to meeting you tomorrow afternoon in person. Would love some more feedback on this solution
Do you know if it is possible to add an hourly rate to the human resources working on the project? In this way the real cost of the project could be calculated based on the hourly rate * the number of hours worked. Thanks
This does take some customization but is an option in dataverse for sure.
Can i assign tasks to someone but not allow them to edit the dates ? Just want them to update % complete
Hi, thanks for the comment. I believe that's the default, actually. But if it's not you might be able to trick the dataverse to lock the fields by using field level security... but that's pretty technical
is this product available in KSA (saudi arabia) or in Abu dhabi
Also the plans that are more than 200 lines tend to break in this view or in project online. is this managed here? or its only for smaller portfolios?
Hi Jollyadivasi,
Projectum has a global partner network with maybe even a local partner that can assist you in implementing the solution. In the description text, you can find a link to the "let's talk" page. There's also a QR code at the end of the video in case you want to use that instead. You can reach out to us through that link to get in touch with the right (local) partner.
Regarding the line limitation, Project for the web currently has a 500 rows limitation, but Microsoft mentioned the following in their Ignite presentation: "With the increase of task limits, plans built in Project for the web can scale up to 1,000 tasks to take on those larger projects."