    Good evening Mr. Paul,
    Great presentation
    i would like to ask you for a claim dispute and i need your feedback please,
    the contract is a lumpsum contract - General conditions under Fidic Red Book 1999 , we should supply the steel in a certain duration but the Employer had change the design of the raft which taken around 2 months delay,
    the Cause is the Raft redesign
    the Effect is that the steel prices had been increased due to the delay
    the entitlement (actually the contract is a lumpsum contract but the delay beyond our control and the employer had a benefit for such redesign but we loss a lot of money)
    i believe that the unforeseeable physical condition clause cannot considered in that case as its not a physical case, but i need your help to give me another supported clause which can be rely on it.
    thanks

    • @instconstclaimspractitioners
      @instconstclaimspractitioners  ปีที่แล้ว

      Unfortunately, we don't have the resources to respond to each question, but we regularly offer live question-and-answer sessions in the form of Construction Clinics. Please subscribe to our newsletter to be kept informed of our events schedule. www.instituteccp.com/subscribe/