Nice video sir could you please tell me in a scenario if we are doing manual excavation 2.5m in deep what type of permit required or how many certificates and supporting documents required in this scenario because adnoc officer asked me this question but unfortunately i puzzled at that time.
If excavation is more then 1.2 meter deep in Adnoc we need critical work permit, confined space certificate, excavation certificate, rescue plan and observer.
Thanks alot for your services Dear❤
Much appreciated video
Keeping going bro
Tks sir
Road closer certificate also
Depends on the location whether there is any road that needs to be closed
Nice video sir could you please tell me in a scenario if we are doing manual excavation 2.5m in deep what type of permit required or how many certificates and supporting documents required in this scenario because adnoc officer asked me this question but unfortunately i puzzled at that time.
If excavation is more then 1.2 meter deep in Adnoc we need critical work permit, confined space certificate, excavation certificate, rescue plan and observer.
@@safetytips9601I answered exactly Atmospheric test record form JSA level 2. But he's asking what are the other supporting documents.
@@umersaeed9742 Method statement and drawing ,scaning report of underground services and Noc.
@@safetytips9601 Thank You Sir❤️