hi , wanted to ask one thing , There are 2 cyclic jobs A and B such that A is predecessor to B and A runs after every 2 minutes from end while B runs after every 1 minute from end. Problem is job B keeps on re running and failing even after one failure. I thought on adding'ON STATEMENT * CODE NOTOK DO STOP CYCLIC 'in steps of job B . Will this work? If not,What could be the workaround?
Thank you very much for creating videos on the control-m and these are very awesome. Please prepare more videos
thank you so much...
Hello, is it possible to capture two messages on the same ON line?
hi , wanted to ask one thing , There are 2 cyclic jobs A and B such that A is predecessor to B and A runs after every 2 minutes from end while B runs after every 1 minute from end. Problem is job B keeps on re running and failing even after one failure. I thought on adding'ON STATEMENT * CODE NOTOK DO STOP CYCLIC 'in steps of job B . Will this work? If not,What could be the workaround?
Looks
can you send me this job?