Maine Cube acceptance criteria k bhut Sara video dekha h wo v details me but Really jo aj ap ne itne short time me itna bada doubt clear Kiya hai I just want to really thanks boss🙏 Great information
I do provide quality - related knowledge for the activities happening on their site throughout the project. This is a one-time fee of ₹500/- which covers my services for the entire duration of the project. Let me know if You are interested.😊
I do provide quality - related knowledge for the activities happening on their site throughout the project. This is a one-time fee of ₹500/- which covers my services for the entire duration of the project. Let me know if You are interested.😊
As per IS 456 :2000 for a group= 4 samples mean fck+3 and individual fck-3 3 samples mean fck+4 individual fck-2 1 sample fck+4 minimum But what about 2 samples is there any individual
Nice explain sir .... but I want to know that .as for example no of samples 1 Grade of concrete M-40 & test results is (37.8+47.1+47.1)=Average 44 Mpa. so sir that result is accepted or not please reply
Informative...
Maine Cube acceptance criteria k bhut Sara video dekha h wo v details me but Really jo aj ap ne itne short time me itna bada doubt clear Kiya hai I just want to really thanks boss🙏
Great information
😀
🙏👍👷
Very informative
Thank you
Sir, Hand mixe M-35 grade concrete kaise banaye???
I do provide quality - related knowledge for the activities happening on their site throughout the project. This is a one-time fee of ₹500/- which covers my services for the entire duration of the project. Let me know if You are interested.😊
How many cubes to make for how much quantity of m3 ??
As per IS 456. Clause 15.2.2
Please share the latest version of IS 456 and IS 516
I do provide quality - related knowledge for the activities happening on their site throughout the project. This is a one-time fee of ₹500/- which covers my services for the entire duration of the project. Let me know if You are interested.😊
7 days cube strength percentage kon sa is code pe mentioned hai
IS 456 AMENDMENT-4 ya 5 me hai.. it is 60%.... which was earlier 65%
As per IS 456 :2000 for a group= 4 samples mean fck+3 and individual fck-3
3 samples mean fck+4 individual fck-2
1 sample fck+4 minimum
But what about 2 samples is there any individual
It is same for 2 & 3...
You should rather ask for sample no. 5 & 6 & 7
Nice explain sir .... but I want to know that .as for example no of samples 1 Grade of concrete M-40 & test results is (37.8+47.1+47.1)=Average 44 Mpa. so sir that result is accepted or not please reply
Accepted.. because as per the condition for round off value as per IS code, you can rewrite 37.8 as 38.00
Thank you so much sir for your valuable replies