ACE Fort Lauderdale BIM Session 2023-03-08
ฝัง
- เผยแพร่เมื่อ 14 ธ.ค. 2024
- Watch the Video and Answer the 8 Questions Below:
1: What does BIM stand for:
A) Building Improvement Model
B) Building Improvement Module
C) Building Information Model
D) Building Information Module
2: Which one is an advantage of BIM:
A) Schedule Improvement
B) Reduction of Cost
C) Design Flexibility
D) All of the above
E) None of the above
3: Certification is required to operate in a BIM process.
True
False
4: How many Level of Details are there:
A) 3
B) 5
C) 7
D) 4
5: Which Level of Detail has the most detail:
A) Level 300
B) Level 400
C) Level 500
D) Level 600
E) Level 700
6: Which software is used to detect clashes:
A) Revit
B) Navisworks
C) SketchUp
D) Trimble
7: How many men are required to run a Robotic Total
Station:
A) One man on the controller and one man on the robot
B) Two men on the robot
C) Does not require anyone
D) One man on the controller
8: Which one is not a hardware you would take into the
field:
A) Drones
B) Virtual Reality
C) Robotic Total Station
D) Augmented Reality
Extra Credit:
What is the brand and model of the drone on the slide?